Federal contract award

W9127S25F0046

SWL MINOR CONSTUCTION SATOC TASK ORDER #62. BULL SHOALS PAVING REPAIRS AT LEAD HILL, TUCKER HOLLOW, HWY 125, AND BUCK CREEK, MARION AND BOONE COUNTIES, ARKANSAS. COMPLETION 120 CALENDAR DAYS AFTER RECEIPT OF NTP. DATES ON CAR ARE ESTIMATES ONLY.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW076 ENDIST LITTLE ROCK
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1QA — CONSTRUCTION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicleW9127S20D0022
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$4.4M
Current contract value$4.4M
Potential contract value / ceiling$4.4M
Start dateMay 1, 2025
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityMay 4, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 4, 2026P00002$0SWL MINOR CONSTRUCTION SATOC TASK ORDER #62, PAVING REPAIRS, BULL SHOALS LAKE. EXTEND THE DELIVERY DATE TO 07/31/2026.
Jul 18, 2025P00001$0BULL SHOALS PAVEMENT REPAIR - MOD TO ADD END DATE TO DELIVERY SCHEDULE. NO CHANGES TO CONTRACT TERMS AND CONDITIONS.
Apr 22, 20250$4.7MSWL MINOR CONSTUCTION SATOC TASK ORDER #62. BULL SHOALS PAVING REPAIRS AT LEAD HILL, TUCKER HOLLOW, HWY 125, AND BUCK CREEK, MARION AND BOONE COUNTIES, ARKANSAS. COMPLETION 120 CALENDAR DAYS AFTER RECEIPT OF NTP. DATES ON CAR ARE ESTIMATES ONLY.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.