Federal contract award
W9128F22C0030
BILLY MITCHELL ANGB HYDRANT III FUELING SYSTEM
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W071 ENDIST OMAHA |
| NAICS | 237120 — Oil and Gas Pipeline and Related Structures Construction |
| PSC | Z2GC — REPAIR OR ALTERATION OF FUEL STORAGE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $50.1M |
| Current contract value | $50.1M |
| Potential contract value / ceiling | $50.1M |
| Start date | Sep 29, 2022 |
| Current end date | Jul 28, 2026 |
| Potential end date | Jul 28, 2026 |
| Latest award activity | Aug 11, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 24 of 24 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 9, 2026 | P00010 | $240.0K | REPLACE TYPE III HYDRANT FUEL SYSTEM, GEN. BILLY MITCHELL, WISCONSIN ANGB |
| Aug 11, 2025 | A00013 | $130.0K | CD R00017 CR17-1 NTE NTP 1ST PT RETAINING WALL FOR PFOS CONTAINMENT PUMP HOUSE AND CONTROL ROOM |
| Aug 6, 2025 | A00012 | $50.9K | CD R00013 CYBER SECURTIY 25 05 11.01 SPEC REV. PUMP HOUSE AND CONTROL ROOM |
| Aug 4, 2025 | P00009 | $708.2K | R00020 COMPENSABLE DELAY SETTLEMENT PUMP HOUSE AND CONTROL ROOM |
| Jul 8, 2025 | A00011 | $-49.6K | R00019 WATER LINE RE ROUTE PUMP HOUSE AND CONTROL ROOM |
| Jun 26, 2025 | A00010 | $58.9K | R00018 OFC TRAILER STAGING AREA PUMP HOUSE AND CONTROL ROOM |
| Jun 25, 2025 | A00009 | $14.3K | R00010 CR10 WATER FOR HYDROSTATIC TESTING TANKS REPLACE TYPE III HYDRANT BILLY MITCHELL |
| Jun 5, 2025 | P00008 | $6.4M | ADDITIONAL SOIL DISPOSAL |
| Apr 22, 2025 | P00007 | $1.6M | R00011 PFAS CONTAMINATED SOIL DISPOSAL II PUMP HOUSE AND CONTROL ROOM |
| Apr 2, 2025 | P00006 | $379.2K | CD-M R00008 PFAS CONTAMINATED GROUNDWATER TREATMENT REPLACE TYPE III HYDRANT BILLY MITCHELL |
| Jan 16, 2025 | A00008 | $42.0K | R00012 FSC DELAY COSTS PUMP HOUSE AND CONTROL ROOM 22C0030 BILLY MITCHELL |
| Sep 26, 2024 | P00005 | $1.2M | CD R00005 PFAS CONTAMINATED SOIL DISPOSAL PUMP HOUSE AND CONTROL ROOM |
| Sep 20, 2024 | A00007 | $-17.3K | CD R10006 FINAL CR 006-2 ADDITIONAL SOIL TESTING PFOS DISPOSAL PUMP HOUSE AND CONTROL ROOM |
| Sep 5, 2024 | P00004 | $2.6M | CD R00009 REA DELAYS PUMP HOUSE AND CONTROL ROOM |
| Jul 19, 2024 | P00003 | $266.4K | CD R30004 CR 004-4 FINAL ALTERNATE FOUNDATION IMPROVEMENTS PUMP HOUSE AND CONTROL ROOM |
| Apr 19, 2024 | A00006 | $278.0K | R20004 NTE 3RD PART ALTERNATE FOUNDATION IMPROVEMENTS PUMP HOUSE AND CONTROL ROOM |
| Mar 28, 2024 | A00005 | $15.7K | CDM R00007 INCREASE IN PERFORMANCE COSTS PUMP HOUSE AND CONTROL ROOM |
| Feb 9, 2024 | A00003 | $137.0K | R10004 CR 004-2 NTE ALT FOUNDATION IMPROVEMENTS PUMP HOUSE AND CONTROL ROOM |
| Feb 9, 2024 | A00004 | $82.1K | R00006 CR 006-1- NTP NTE ADD'T SOIL TESTING FOR PFOS DISPOSAL PUMP HOUSE AND CONTROL ROOM |
| Jul 28, 2023 | A00002 | $75.0K | CD R0004-1 ALTERNATIVE FOUNDATION IMPROVEMENT PUMP HOUSE AND CONTROL ROOM |
| Jun 14, 2023 | A00001 | $28.6K | CD R00003 WE ENERGIES UTILITY POWER PUMP HOUSE AND CONTROL ROOM |
| Apr 25, 2023 | P00002 | $668.1K | CD R0002 PFAS TESTING ADDITION W9128F22C0030 PUMP HOUSE AND CONTROL ROOM |
| Apr 5, 2023 | P00001 | $160.0K | EXERCISE OPTION CLIN 0015 (AUTOMATIC TANK GAUGING) AND ADD THE DPAS CLAUSE - RATED ORDER |
| Sep 29, 2022 | 0 | $35.2M | BILLY MITCHELL ANGB HYDRANT III FUELING SYSTEM |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.