Federal contract award

W9128F22C0034

PIPESTEM SPILLWAY MODIFICATION PROJECT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW071 ENDIST OMAHA
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCZ2KA — REPAIR OR ALTERATION OF DAMS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$201.1M
Current contract value$201.1M
Potential contract value / ceiling$201.1M
Start dateOct 15, 2022
Current end dateJun 8, 2026
Potential end dateJun 8, 2026
Latest award activityMay 7, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 44 of 44 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 7, 2026A00021$65.9KPIPESTEM SPILLWAY MODIFICATION
Mar 24, 2026P00022$648.3KPIPESTEM SPILLWAY MODIFICATION
Jan 30, 2026P00021$531.6KPIPESTEM SPILLWAY MODIFICATION
Oct 28, 2025A00020$469.3KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00043 METERING MANHOLE FREEZE PROTECTION
Oct 23, 2025P00020$890.9KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00042 2025 VEQ
Aug 20, 2025P00019$9.7MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R20041 TERM S-SLIDE IMPACT COSTS (NTE) PART-2
Jun 27, 2025P00018$11.0MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R10041 TERM S-SLIDE IMPACT COSTS (NTE) PART-1
May 29, 2025P00017$3.3MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R40035 TERMINAL STRUCTURE SLIDE PART-5 FINAL
May 19, 2025P00016$1.5MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00025 DOWNSTREAM (DS) TERMINAL STRUCTURE SLIDE
Apr 30, 2025A00019$88.2KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00031 DOWNSTREAM CUTOFF WALL EXCAVATION
Mar 25, 2025P00015$6.0MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R20035 TERMINAL STRUCTURE SLIDE (NTE) PART-4
Feb 25, 2025P00014$577.3KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00040 FULL TIME QC PERSONNEL 2025
Dec 13, 2024P00013$2.0MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00034 RCC APRON & CUTOFF WALL CRACK MITIGATION
Dec 3, 2024A00018$16.4KPIPESTEM SPILLWAY MODIFICATION PROJECT - R00039 RCC SECONDARY SECT FREEZE THAW BEAMS
Sep 20, 2024P00012$3.3MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R20035 TERMINAL STRUCTURE SLIDE (NTE) PART-3
Sep 13, 2024P00011$3.6MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R10022 RCC FORMED FACES, PART-2
Aug 21, 2024A00017$480.8KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00038 SOIL CEMENT AGGREGATE
Aug 7, 2024P00010$5.4MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R10035 TERMINAL STRUCTURE SLIDE (NTE) PART-2
Jul 31, 2024A00016$148.8KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00023 DEWATERING WELL FOULING REMEDIATION
Jul 17, 2024P00009$4.6MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00027 RIP RAP REV, ADD WATERSTOP AND RCC CLIN
Jul 1, 2024P00008$4.0MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00016 ROCK IN EXCAVATED MATERIALS
Jun 13, 2024P00007$875.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00035 TERMINAL STRUCTURE SLIDE (NTE) PART-1
May 21, 2024P00006$921.3KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00026 FULL TIME QC PERSONNEL
May 1, 2024A00015$476.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00032 INTERIM VEQ - GRAVEL (CLIN 0011)
Apr 8, 2024A00014$21.8KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00010: TREE PLANTING DETAIL & R00028: DESTRUCTIVE RCC TESTING AND COARSE AGGREGATE SHIPMENT
Mar 15, 2024P00005$1.0MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00022 RCC FORMED FACES PART-1 (NTE)
Mar 6, 2024A00013$0CD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00029 WEATHER TIME EXTENSION SEP '23 - JAN '24
Feb 27, 2024A00012$34.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00024 SURVEY LICENSES
Dec 14, 2023P00004$2.5MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00017 OVER-EX UNSUITABLE MATERIALS
Nov 30, 2023A00011$82.6KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00020 GOV OFFICE REV & R00021 ADD MATERIAL TESTING
Nov 3, 2023A00010$228.9KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00018 RIFLE RANGE CLEANUP & ADDITIONAL RIPRAP
Oct 26, 2023P00003$1.5MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R10015 RT ABUTMENT COULEE DRAINAGE SYSTEM FINAL-PART
Sep 19, 2023A00009$115.6KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00013 MH COVERS, CONNECTION BOOTS, FLAP GATES
Sep 5, 2023A00008$193.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00009 VEQ CLEARING AND GRUBBING
Aug 30, 2023A00007$25.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00004 IN-WELL MOVEMENT & P-WELL ABANDONMENT
Aug 21, 2023P00002$2.8MCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00008 EXCAVATE BELOW 1430
Aug 7, 2023P00001$436.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00015 RT ABUTMENT COULEE DRAINAGE SYSTEM PT-1
Jul 11, 2023A00006$21.4KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00005 QA QC LABORATORY ADDITIONS
Jun 30, 2023A00005$0CD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00012 WEATHER DAYS WEATHER DAYS EXTENSION APRIL- MAY 2023
Jun 29, 2023A00004$79.1KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00002 REDUNDANT VWPZS AND FLOW MEASURING EQPT
Jun 13, 2023A00003$48.8KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00001 QA QC LABORATORY LOCATION
Jun 1, 2023A00002$4.0KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00003 GOVERNMENT TRAILER FURNITURE
May 25, 2023A00001$9.4KCD: PIPESTEM SPILLWAY MODIFICATION PROJECT - R00011 GROUNDBREAKING CEREMONY
Sep 22, 20220$131.5MPIPESTEM SPILLWAY MODIFICATION PROJECT

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.