Federal contract award
W9128F23C0003
ENTIRE WORK COMPLETE FOR CONSTRUCTION - B 21 WASHRACK
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W071 ENDIST OMAHA |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1BZ — CONSTRUCTION OF OTHER AIRFIELD STRUCTURES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $76.4M |
| Current contract value | $76.4M |
| Potential contract value / ceiling | $77.8M |
| Start date | Dec 1, 2022 |
| Current end date | Apr 30, 2026 |
| Potential end date | Apr 30, 2026 |
| Latest award activity | Apr 16, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 26 of 26 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 16, 2026 | A00021 | $28.5K | CONSTRUCT NEW 56,811SF 2-BAY HANGAR FACILITY AND ASSOCIATED 25,648SM AIRFIELD APRON, SITE FEATURES, UTILITIES, AND INFRASTRUCTURE FOR MAINTENANCE OF B-21 AIRCRAFT. PROJECT INCLUDES DEMOLITION OF 2 EXISTING HANGAR BUILDINGS AND PAVEMENT. |
| Dec 18, 2025 | A00020 | $0 | CONSTRUCT NEW 56,811SF 2-BAY HANGAR FACILITY AND ASSOCIATED 25,648SM AIRFIELD APRON, SITE FEATURES, UTILITIES, AND INFRASTRUCTURE FOR MAINTENANCE OF B-21 AIRCRAFT. PROJECT INCLUDES DEMOLITION OF 2 EXISTING HANGAR BUILDINGS AND PAVEMENT. |
| Sep 8, 2025 | A00019 | $14.0K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00027 ADDITIONAL PIR BOXES - ESS EQUIPMENT |
| Jun 30, 2025 | A00018 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00018 WEATHER TIME EXTENSION MAY 25 - MAY 25 |
| Jun 17, 2025 | A00017 | $170.7K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00026 (R/20 M-STRIP & P-DRAIN AND R/26 PIR BOXES) |
| Feb 11, 2025 | A00016 | $110.7K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00022 RELOCATE TRAILERS/LAY DOWN |
| Jan 6, 2025 | A00015 | $271.4K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00021 ELECTRICAL RECEPTACLES FOR AGES |
| Dec 4, 2024 | A00014 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} - R00023 WEATHER TIME EXTENSION JUN 24 - OCT 24 |
| Oct 3, 2024 | A00013 | $-106.7K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00016 MINOR SITEWORK REVISIONS |
| Jul 19, 2024 | A00012 | $191.3K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00017 CIVIL IW LINES AND MANHOLES & AF PAVING |
| Jul 17, 2024 | A00011 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00018 WEATHER TIME EXTENSION NOV 23 - MAY 24 |
| Jul 16, 2024 | P00004 | $748.4K | EXERCISE OPTION CLIN 0012 |
| Apr 10, 2024 | A00010 | $144.9K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00012 SECURE AREA REVISIONS |
| Mar 26, 2024 | A00009 | $11.6K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00014 METAL WALL PANEL COLOR |
| Feb 29, 2024 | A00008 | $38.9K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00011 SOAP EQUIPMENT FITTING REVISION |
| Feb 1, 2024 | A00007 | $25.5K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R10009 |
| Jan 4, 2024 | A00006 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00013 WEATHER DAYS WEATHER TIME EXTENSION OCT 23 - OCT 23 |
| Dec 21, 2023 | A00005 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00007 IFC DRAWING SET |
| Sep 6, 2023 | P00003 | $63.0K | REDUCE QUANTITY FROM 2,500 CY TO 500 CY FOR CLIN 0017 AND EXERCISING THE OPTION. |
| Aug 30, 2023 | A00004 | $30.0K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00009 UNFORESEEN EXISTING UTILITIES |
| Aug 3, 2023 | A00003 | $0 | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00004 CITIZENSHIP & SECURITY REQUIREMENTS |
| Aug 1, 2023 | A00002 | $7.8K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00005 TRUNK LINE CONNECTION FOR 70 ROW E-STOP |
| Jul 31, 2023 | A00001 | $-87.1K | CD - B-21 WASHRACK & MAINTENANCE HANGER {EAFB} R00001 ELIMINATE DOOR TRACK DRAIN CLEANOUTS |
| Apr 14, 2023 | P00002 | $1.3M | EXERCISE OPTION LINE ITEM 0007. |
| Mar 13, 2023 | P00001 | $669.2K | EXERCISE CLINS 0008/0011 AND ADD DPAS RATING. |
| Nov 30, 2022 | 0 | $72.8M | ENTIRE WORK COMPLETE FOR CONSTRUCTION - B 21 WASHRACK |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.