Federal contract award
W9128F23C0009
MINOT HELO OPS FACILITY CONSTRUCTION, MINOT AFB, ND.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W071 ENDIST OMAHA |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1BZ — CONSTRUCTION OF OTHER AIRFIELD STRUCTURES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $137.1M |
| Current contract value | $137.1M |
| Potential contract value / ceiling | $147.6M |
| Start date | Mar 31, 2023 |
| Current end date | Nov 9, 2026 |
| Potential end date | Nov 9, 2026 |
| Latest award activity | Apr 30, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 29 of 29 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 30, 2026 | A00019 | $178.6K | A NEW BUILDING SUPPORTING HELICOPTER SQUADRON AND TACTICAL RESPONSE ALERT CREW OPERATIONS, AIRCRAFT MAINTENANCE UNIT IN SUPPORT OF THE MINUTEMAN III INTERCONTINENTAL BALLISTIC MISSILE (ICBM) WEAPONS. (PN: QJVR153001) (P2: 465705) |
| Apr 23, 2026 | P00009 | $3.3M | A NEW BUILDING SUPPORTING HELICOPTER SQUADRON AND TACTICAL RESPONSE ALERT CREW OPERATIONS, AIRCRAFT MAINTENANCE UNIT IN SUPPORT OF THE MINUTEMAN III INTERCONTINENTAL BALLISTIC MISSILE (ICBM) WEAPONS. (PN: QJVR153001) (P2: 465705) |
| Jan 29, 2026 | A00018 | $127.2K | A NEW BUILDING SUPPORTING HELICOPTER SQUADRON AND TACTICAL RESPONSE ALERT CREW OPERATIONS, AIRCRAFT MAINTENANCE UNIT IN SUPPORT OF THE MINUTEMAN III INTERCONTINENTAL BALLISTIC MISSILE (ICBM) WEAPONS. (PN: QJVR153001) (P2: 465705) |
| Dec 5, 2025 | P00008 | $0 | CNS OF HELO/TRF/MTX FACILITY |
| Nov 18, 2025 | A00017 | $62.2K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00046 DOMESTIC WATER SERVICE ENTRANCE, R00048 ELECTRIC UTILITY/STORM SEWER CONFLICT, R00062 MASONRY LINTEL/CONTROL JOINTS |
| Oct 27, 2025 | P00007 | $585.6K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00037 STRUCTURAL CHANGES FOR VLFD HOISTS AND CABLES |
| Oct 9, 2025 | A00016 | $35.0K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00030 CONVERT OPS BRIEF 118 TO OPEN STORAGE |
| Sep 17, 2025 | A00015 | $0 | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00050 WEATHER TIME EXTENSION JUL24 - MAY25 |
| Sep 15, 2025 | P00006 | $540.4K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00032 CONVERT SIM APPROACH DRIVE TO CONCRETE & BIFOLD DOOR |
| Sep 3, 2025 | A00014 | $52.8K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00047 (MODIFICATIONS: R00022 DELETE CONCRETE FIRE RISER PITS, R00031 CONVERT TRF BRIEF 236 TO OPEN DISCUSSION, R00045 STRUCTURAL REVISIONS AT MASONRY, AND R00047 INCREASE SIZE OF MIC1 METERING CABINET) |
| Aug 24, 2025 | P00005 | $987.3K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00015-2 STRUCTURAL CHANGES AT VLFD'S (NTE) PART-2 (FINAL) |
| Jul 17, 2025 | A00013 | $-103.5K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00012 EXTERIOR COLD FORM STUDS RFI-0122 |
| Jun 27, 2025 | A00012 | $233.3K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00040 (R00033-HSS HEADER AT FIRST FLOOR CURTAINWALL, R00036 MINIMIZE ROOF DECK DEFLECTION RFI-0224, AND R00040 DECK SUPPORT FOR FLOOR BOXES) |
| May 21, 2025 | A00011 | $155.1K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00044 (R00025 AAR/SIM BRIEFING RM. REVISIONS, R00034 REVISE TPC ENTITY FROM GBCI TO GBI, AND R00044 FREE ZONE CHANGE BY SECURITY FORCES) |
| Apr 18, 2025 | A00010 | $-180.8K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00020 (R/18 REMOVE DRAFT CURTAINS, R/20 WALL TYPE CHANGES: METAL MESH/INSULATION) |
| Mar 28, 2025 | P00004 | $240.0K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00015 STRUCTURAL CHANGES AT VLFD'S (NTE) PART-1 |
| Feb 6, 2025 | A00009 | $3.0K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00016 UG ELEC. SS DECONFLICT/AIRCRAFT GRND, R00017 FTG. F10 STRUCTURAL REVISIONS FOR ELEC AND R00021 SIMULATOR BAY FLOOR TRENCH CHANGES |
| Oct 9, 2024 | A00008 | $40.5K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00010 216B WC REVISION, R00013 BAA DRIVEN ELECTRICAL CHANGES RFI-0127, R00019 CHANGE TO ELEC. PANEL S1DHX, AND R00023 CONVERT GLAZING AT SIM SUITE |
| Aug 21, 2024 | A00007 | $33.4K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00009 FUEL LINE DEMO R/5 & CRANE CHANGES R/9 |
| Aug 20, 2024 | A00006 | $0 | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00024 WEATHER TIME EXTENSION MAY 24 - JUL 24 |
| Aug 19, 2024 | P00003 | $0 | ADD THE DEFENSE PRIORITIES AND ALLOCATIONS SYSTEM (DPAS) TO THIS CONTRACT OF THE CNS OF HELO/TRF/MTX FACILITY. |
| Jul 11, 2024 | A00005 | $-62.2K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00011 ELEVATOR (R00003), ELECT FOOTINGS (R00008) & ROOF DECK (R00011) |
| Jul 3, 2024 | P00002 | $779.0K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00002 SIMULATOR SUITE FLOORPLAN |
| Jun 17, 2024 | A00004 | $0 | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00014 WEATHER TIME EXTENSION JUN 23 - APR 24 |
| Jun 11, 2024 | A00003 | $-52.9K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00004 REDUCE FREQUENCY OF DENSITY TESTING |
| Apr 11, 2024 | A00002 | $0 | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00007 STRUCTURAL REVISIONS CLARIFICATION |
| Apr 3, 2024 | A00001 | $90.4K | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB - R00002 UG ELECTRICAL AND COMM CHANGES |
| Mar 6, 2024 | P00001 | $1.1M | CD: CONSTRUCT HELO TRF OPS FACILITY, MAFB R00001 MISC. STRUCTURAL REVISIONS |
| Mar 17, 2023 | 0 | $128.7M | MINOT HELO OPS FACILITY CONSTRUCTION, MINOT AFB, ND. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
80/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 80/100. Available recorded signals: 75 points.
- Contract end 2026-11-09 (15 days from calculation)
- +35 points
- 13 historical awards in this buyer and category group
- +15 points
- 29 recorded award transactions
- +10 points
- Latest award action: 2026-04-30
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.