Federal contract award

W9128F23C0043

DESIGN/BUILD- L536- LEVEE FOLLOW-ON REPAIR, MO

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW071 ENDIST OMAHA
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCZ1KF — MAINTENANCE OF DREDGING FACILITIES
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$3.2M
Current contract value$3.2M
Potential contract value / ceiling$5.2M
Start dateSep 30, 2023
Current end dateAug 9, 2025
Potential end dateAug 9, 2025
Latest award activityFeb 19, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 19, 2026A00008$28.0KREPAIRS OF DAMAGES SUSTAINED DURING 2019 FLOOD EVENT COMPLETION OF COMPONENTS ON NEWLY CONSTRUCTED SETBACK LEVEE SEGMENT MR LEVEE UNIT L536 IS LOCATED ALONG THE LEFT BANK OF THE MR IN ATCHISON, HOLT COUNTIES MO BTWN RIVER MILES 515.7, 522.2
Dec 16, 2025A00007$0REPAIRS OF DAMAGES SUSTAINED DURING 2019 FLOOD EVENT COMPLETION OF COMPONENTS ON NEWLY CONSTRUCTED SETBACK LEVEE SEGMENT MR LEVEE UNIT L536 IS LOCATED ALONG THE LEFT BANK OF THE MR IN ATCHISON, HOLT COUNTIES MO BTWN RIVER MILES 515.7, 522.2
Nov 30, 2025P00002$0FLOOD DAMAGE REPAIRS
Oct 9, 2025P00001$1.0MFLOOD DAMAGE REPAIRS
Aug 6, 2025A00006$175.0KCD: CONTRACT D: L536 FOLLOW-ON WORK - MISSOURI RIVER R0004-3 FLOOD DAMAGE REPAIRS (NTE) PART-3
May 5, 2025A00005$0CD: CONTRACT D: L536 FOLLOW-ON WORK - MISSOURI RIVER R0004-2 FLOOD DAMAGE REPAIRS (NTE) PART-2
Feb 10, 2025A00004$100.0KCD: CONTRACT D: L536 FOLLOW-ON WORK - MISSOURI RIVER R00004 FLOOD DAMAGE REPAIRS (NTE) PART-1
Jan 28, 2025A00003$0CD: CONTRACT D: L536 FOLLOW-ON WORK - MISSOURI RIVER R00003 WEATHER DAYS WEATHER TIME EXTENSION NOV 2024
Nov 14, 2024A00002$229.1KCD: CONTRACT D: L536 FOLLOW-ON WORK - MISSOURI RIVER R00002 NRCS BERM CLOSURE, ADDITIONAL TESTING & SEEDING

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.