Federal contract award
W912BU19C0017
IGF::OT::IGF PHASE 1
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST PHILADELPHIA |
| NAICS | 237110 — Water and Sewer Line and Related Structures Construction |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $50.1M |
| Current contract value | $50.1M |
| Potential contract value / ceiling | $50.1M |
| Start date | Feb 27, 2019 |
| Current end date | Jun 19, 2025 |
| Potential end date | Jun 19, 2025 |
| Latest award activity | Jun 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 26 of 26 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 4, 2026 | P00008 | $-4.7M | PROJECT TITLE: WELCH ELEMENTARY SCHOOL / DOVER AIR BASE MIDDLE SCHOOL REPLACEMENT, DOVER AIR FORCE BASE, DELAWARE |
| May 29, 2026 | A00017 | $26.0K | PROJECT TITLE: WELCH ELEMENTARY SCHOOL / DOVER AIR BASE MIDDLE SCHOOL REPLACEMENT, DOVER AIR FORCE BASE, DELAWARE |
| Feb 25, 2026 | A00016 | $57.7K | CHANGES CD22, CD24, CD28, CD34 |
| Dec 15, 2025 | A00015 | $12.5K | CHANGES CD 025 & CD 035 |
| Nov 20, 2025 | A00014 | $1.4K | CHANGE CD-019 |
| Sep 8, 2025 | A00013 | $16.2K | CHANGE CD-20 H-0129 - RFI-289 STATIC FLOORING |
| Aug 21, 2025 | A00012 | $3.4K | CHANGE CD012 MODIFICATION A00012 |
| Aug 20, 2025 | P00007 | $19.1K | PARTNERING |
| May 30, 2025 | P00006 | $0 | PHASE 1 |
| Nov 27, 2024 | A00011 | $78.3K | CONTRACT NO. W912BU-19-C-0017 WELCH ELEMENTARY SCHOOL MODIFICATION NO. A00011 R00015 - H-092, H-101, H-105, H-107 |
| Nov 26, 2024 | A00010 | $24.2K | CONTRACT NO. W912BU-19-C-0017 WELCH ELEMENTARY SCHOOL MODIFICATION NO. A00010 R00014 - CD-16 LG GOV'T TRAILER ADDITIONAL COST |
| Nov 25, 2024 | A00009 | $21.9K | CHANGE CD21 MODIFICATION A00009 |
| Feb 9, 2023 | P00004 | $0 | NO COST WEATHER TIME EXTENSION |
| Feb 9, 2023 | P00005 | $0 | TRANSFER MOD |
| Feb 7, 2023 | P00003 | $0 | TRANSFER CONTRACT AUTHORITY TO BALTIMORE DISTRICT |
| Jul 7, 2022 | A00008 | $22.8K | PHASE 1 |
| Dec 17, 2021 | A00007 | $20.4K | PHASE 1 |
| Jun 22, 2021 | A00006 | $110.5K | PHASE 1 |
| Mar 4, 2021 | A00005 | $235.6K | PHASE 1 |
| Mar 3, 2021 | A00004 | $21.6K | PHASE 1 |
| Feb 25, 2021 | A00003 | $38.9K | PHASE 1 |
| Dec 8, 2020 | A00002 | $44.7K | PHASE 1 |
| Oct 29, 2020 | A00001 | $125.9K | PHASE 1 |
| Jun 25, 2020 | P00002 | $1.2M | PHASE 2 - WELCH SCHOOL DAFB - VAPOR INTRUSION AND 174 DAY TIME EXTENSION |
| Mar 30, 2019 | P00001 | $0 | IGF::OT::IGF PHASE 1 |
| Feb 27, 2019 | 0 | $48.0M | IGF::OT::IGF PHASE 1 |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.