Federal contract award
W912BV22F0149
DODGE HILL BRIDGE - CONSTRUCTION, REPLACE BRIDGE 11 ON FORT SILL, OK.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W076 ENDIST TULSA |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1QA — CONSTRUCTION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE) |
| Parent award / vehicle | W912BV20D0050 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.0M |
| Current contract value | $3.0M |
| Potential contract value / ceiling | $3.0M |
| Start date | Oct 15, 2022 |
| Current end date | Apr 20, 2026 |
| Potential end date | Apr 20, 2026 |
| Latest award activity | Mar 24, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 24, 2026 | A00002 | $55.3K | EXCAVATE AND REMOVE THE STEM WALL THAT IS LOCATED BENEATH THE AREA THAT THE NEW H-PILES ARE TO BE INSTALLED ON BOTH SIDES OF THE NEW BRIDGE. PROVIDE FILL AND COMPACT AS NECESSARY TO PREPARE THE SITE FOR THE INSTALLATION OF THE NEW H-PILES. |
| Mar 5, 2026 | A00001 | $0 | TE002 CORRECT TO VALID VENDOR ID, MOD NUMBERING |
| Jun 16, 2025 | P00001 | $0 | MODIFICATION TO CORRECT DELIVERY OF 754 DAYS TO POP OF 14 NOVEMBER 2022 TO 06 DECEMBER 2024. DODGE HILL BRIDGE - CONSTRUCTION, REPLACE BRIDGE 11 ON FORT SILL, OKLAHOMA. |