Federal contract award
W912BV25C0013
REPAIR OF EROSION AT CHARLES PAGE FLOODWALL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W076 ENDIST TULSA |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.7M |
| Current contract value | $1.7M |
| Potential contract value / ceiling | $1.7M |
| Start date | Jun 9, 2025 |
| Current end date | Feb 26, 2026 |
| Potential end date | Feb 26, 2026 |
| Latest award activity | Apr 9, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 9, 2026 | A00005 | $0 | THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE ALLOWED UNDER SPECIFICATION SECTION 00 73 00 FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 21 JULY 2025 THROUGH 31 JANUARY 2026, 13 CALENDAR DAYS TIME EXTENSION. |
| Feb 5, 2026 | A00004 | $0 | CORRECTION OF PAYMENT TERMS (NET DAYS) |
| Jan 6, 2026 | A00003 | $49.6K | INCREASE OF RIP RAP QUANTITIES |
| Oct 15, 2025 | A00002 | $150.0K | RIP RAP INCREASE IN QUANTITIES |
| Aug 25, 2025 | A00001 | $0 | PERIOD OF PERFORMANCE MODIFICATION FOR SPS TO ACWS DATA MIGRATION. |
| Jul 9, 2025 | P00003 | $26.2K | THIS MODIFICATION RE-OBLIGATES OPTION 1 (CLIN 1003) AND OPTION 2 (CLIN 1004) TO CORRECT A CEFMS ERROR THAT COULD DISRUPT BILLING. |
| Jul 3, 2025 | P00002 | $-26.2K | MODIFICATION P0002 - CLINS 100 AND 1002 DE-OBLIGATED TO CORRECTLY CHANGE UNIT OF ISSUE FROM JOB TO CUBIC YARD. AN ADDITIONAL MODIFICATION IS FORTHCOMING TO REFLECT THE CORRECTION. |
| Jun 13, 2025 | P00001 | $0 | THIS MODIFICATION CHANGES THE UNIT OF ISSUE FROM JOB TO CUBIC YARD FOR CLINS 1001 AND 1002. |
| Jun 9, 2025 | 0 | $1.5M | REPAIR OF EROSION AT CHARLES PAGE FLOODWALL |