Federal contract award
W912DQ21F3006
ENVIORNMENTAL REMEDIATION CONSTRUCTION-WGGM SUPERFUND SITE-TASK ORDER
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST PHILADELPHIA |
| NAICS | 562910 — Remediation Services |
| PSC | F108 — Hazardous Substance Removal, Cleanup, and Disposal Services and Operational Support |
| Parent award / vehicle | W912DQ20D3003 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $83.8M |
| Current contract value | $89.1M |
| Potential contract value / ceiling | $89.1M |
| Start date | Jan 15, 2021 |
| Current end date | Jul 15, 2026 |
| Potential end date | Jul 15, 2026 |
| Latest award activity | Apr 13, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 40 of 40 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 13, 2026 | P00039 | $414.8K | THE STATEMENT OF WORK FOR THE REMEDIATION OF UNIT 5 IS: WELSBACH/GGM SUPERFUND SITE, CAMDEN COUNTY, NEW JERSEY - FORMER WELSBACH FACILITY UNIT 5 REMEDIATION-NO COST TIME EXTENSION |
| Jan 28, 2026 | P00038 | $3.9M | THE STATEMENT OF WORK FOR THE REMEDIATION OF UNIT 5 IS: WELSBACH/GGM SUPERFUND SITE, CAMDEN COUNTY, NEW JERSEY - FORMER WELSBACH FACILITY UNIT 5 REMEDIATION-NO COST TIME EXTENSION |
| Dec 4, 2025 | P00037 | $1.0M | THE STATEMENT OF WORK FOR THE REMEDIATION OF UNIT 5 IS: WELSBACH/GGM SUPERFUND SITE, CAMDEN COUNTY, NEW JERSEY - FORMER WELSBACH FACILITY UNIT 5 REMEDIATION-NO COST TIME EXTENSION |
| Nov 6, 2025 | P00036 | $0 | THE STATEMENT OF WORK FOR THE REMEDIATION OF UNIT 5 IS: WELSBACH/GGM SUPERFUND SITE, CAMDEN COUNTY, NEW JERSEY - FORMER WELSBACH FACILITY UNIT 5 REMEDIATION-NO COST TIME EXTENSION |
| Sep 23, 2025 | P00035 | $3.2M | ATP 037 UNIT 7- WVNS 55 AND 63 |
| Sep 16, 2025 | P00034 | $460.6K | ATP 037 UNIT 7-MVARIOUS WVNS |
| Aug 25, 2025 | P00033 | $1.6M | ATP 037 UNIT 7- FINAL FUNDING WELSBACH UNIT 5 |
| Jul 10, 2025 | P00032 | $2.2M | ATP 037 UNIT 7-FUNDING WELSBACH UNIT 5 |
| May 22, 2025 | P00031 | $672.8K | ATP 037 UNIT 7-WVN 040 COLD WEATHER CONCRETE WORK |
| May 13, 2025 | P00030 | $422.5K | ATP 037 UNIT 7- WVNS 49,56,57,60 64 AND 67 |
| Apr 7, 2025 | P00029 | $1.9M | ATP 037 UNIT 7 -WVNS 032, 034, 045, 048, AND 051 P00028 |
| Apr 4, 2025 | P00027 | $0 | ATP 037 UNIT 7 LAST FUNDING ATP 060 UNIT 5 |
| Apr 4, 2025 | P00028 | $968.9K | ATP 037 UNIT 7- WVNS 35,36,42,43,46,47,53 AND 54 |
| Feb 10, 2025 | P00026 | $1.1M | ATP 037 UNIT 7-MODIFICATION FOR WVNS 5,6,29,37,38,39,41: P00026 |
| Jan 14, 2025 | P00025 | $1.6M | ATP 037 UNIT 7, WELSBACH ATP 059 UNIT 5 INCREMENTAL FUNDS $1,600,000.00 |
| Sep 20, 2024 | P00024 | $7.6M | UNIT 5 REMEDIATION |
| Sep 10, 2024 | P00023 | $0 | ATP 037 UNIT 7- WVNS 21, 30,31 AND 33 |
| Aug 19, 2024 | P00021 | $2.0M | ATP 037 UNIT 7. WVN 027 ELECTRICAL SUB CINTRACTOR |
| Aug 19, 2024 | P00022 | $3.3M | ATP 037 UNIT 7- WVN 014 CONCRETE FOUNDATION AND 020 GAP WORK |
| May 3, 2024 | P00020 | $4.7M | WASTE WATER TREATMENT PLANT WVNS 026 AND 028 |
| Apr 15, 2024 | P00019 | $337.7K | WELSBACH / GENERAL GAS MANTLE SUPERFUND SITE REMEDIATION - FABRICATION AND SUPPLY OF 3 FRAC TANKS WVN 008 |
| Apr 5, 2024 | P00018 | $386.8K | WELSBACH/GENERAL GAS MANTLE SUPERFUND SITE - WVN 13, 22, 23, 24, & 25 |
| Mar 25, 2024 | P00017 | $468.9K | WVNS 9, 10, 11, 12, 15, 16, 17, 18, & 19 |
| Dec 18, 2023 | P00016 | $12.0M | ATP 037 UNIT 7 FUNDING - WELSBACH GENERAL GAS MANTLE SUPERFUND SITE |
| Nov 2, 2023 | P00015 | $814.9K | 4TH AND JEFFERSON MODIFICATION ATP036 - ENVIRONMENTAL REMEDIATION CONSTRUCTION AT WELSBACH-GENERAL GAS MANTLE SUPERFUND SITE IN CAMDEN COUNTY, NEW JERSEY |
| Apr 12, 2023 | P00014 | $3.5M | WELSBACH ATP029-UNIT#7 |
| Nov 21, 2022 | P00013 | $7.1M | ATP 024 - FUNDING |
| Sep 21, 2022 | P00012 | $93.3K | WVN3-DEWATERING AND WVN4-CONTRAIL LEASE |
| Sep 17, 2022 | P00011 | $1.4M | WELSBACH_ATP 20 - FIRE PUMP |
| Aug 22, 2022 | P00010 | $0 | ADDING CLAUSE 52.215-21 TO TASK ORDER. NO FUNDING ADDED ON THIS CAR |
| Jul 27, 2022 | P00009 | $88.5K | MOD#9 : ATP 16-105 MIDDLESEX |
| May 12, 2022 | P00008 | $2.1M | WELSBACH: ATP 14 - PHASE 5 UNIT 4 |
| Mar 8, 2022 | P00007 | $7.1M | WELSBACH: ATP10 - PHASE 3 UNIT 2 |
| Mar 3, 2022 | P00004 | $265.1K | ATP 04 - 901 CHAMBERS |
| Mar 3, 2022 | P00005 | $95.1K | ATP 005 - WVN002 - LAB SERVICES |
| Mar 3, 2022 | P00006 | $8.3M | ATP 007 - WATER TREATMENT FACILITY |
| Mar 1, 2022 | P00003 | $1.7M | ATP 003 ADDITIONAL FUNDING |
| Oct 13, 2021 | P00002 | $0 | WELBACH GAS MANTLE SUPERFUND SITE |
| Jan 22, 2021 | P00001 | $0 | ENVIRONMENTAL REMEDIATION CONSTRUCTION TASK ORDER SF30 TO TRANSFER FROM USACE NWK TO USACE HAP IN ITS ENTIRETY |
| Jan 15, 2021 | 0 | $1.0M | ENVIORNMENTAL REMEDIATION CONSTRUCTION-WGGM SUPERFUND SITE-TASK ORDER |