Federal contract award
W912DQ25C1004
THE GENERAL SCOPE OF THE WORK INCLUDES, BUT IS NOT LIMITED TO DISMANTLING, DEMOLITION, REMOVAL, AND DISPOSAL OF NAVIGATION OBSTRUCTIONS AT MULLANPHY BEND, RM 18-20, WELDON SPRINGS, RM 42-44, AND DUNDEE, RM 75-76.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W071 ENDIST KANSAS CITY |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PC — CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $6.8M |
| Current contract value | $6.8M |
| Potential contract value / ceiling | $6.8M |
| Start date | Nov 11, 2024 |
| Current end date | Jul 29, 2026 |
| Potential end date | Jul 29, 2026 |
| Latest award activity | Apr 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 14, 2026 | A00003 | $0 | THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE ALLOWED UNDER SPECIFICATION SECTION 01 30 00 FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 01 DECEMBER 2025 THROUGH 31 DECEMBER 2025. |
| Mar 30, 2026 | A00002 | $0 | THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE ALLOWED UNDER SPECIFICATION SECTION 01 30 00 FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 01 DECEMBER 2025 THROUGH 31 DECEMBER 2025. |
| Jan 30, 2026 | A00001 | $0 | THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE ALLOWED UNDER SPECIFICATION SECTION 01 30 00 FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 01 DECEMBER 2025 THROUGH 31 DECEMBER 2025. |
| Jul 2, 2025 | P00002 | $0 | THE PURPOSE OF THIS ADMIN MODIFICATION IS TO SET THE CORRECT COMPLETION DATE FOR THE UPCOMING MIGRATION TO ACWS. |
| May 15, 2025 | P00001 | $0 | ADMIN MOD |
| Nov 8, 2024 | 0 | $6.8M | THE GENERAL SCOPE OF THE WORK INCLUDES, BUT IS NOT LIMITED TO DISMANTLING, DEMOLITION, REMOVAL, AND DISPOSAL OF NAVIGATION OBSTRUCTIONS AT MULLANPHY BEND, RM 18-20, WELDON SPRINGS, RM 42-44, AND DUNDEE, RM 75-76. |