Federal contract award
W912DR21C0009
CONSTRUCTION OF CONTROL TOWER AND FIRE DAY STATION, PENTAGON, ARLINGTON, VA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST BALTIMORE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1BA — CONSTRUCTION OF AIR TRAFFIC CONTROL TOWERS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $21.8M |
| Current contract value | $21.8M |
| Potential contract value / ceiling | $21.8M |
| Start date | Mar 31, 2021 |
| Current end date | Apr 25, 2025 |
| Potential end date | Apr 25, 2025 |
| Latest award activity | May 5, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 24 of 24 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 9, 2026 | A00018 | $19.4K | DESCRIPTION OF AMENDMENT/MODIFICATION CONTRACT NO. W912DR21C0009 FOR PENTAGON CONTROL TOWER AND FIRE DAY STATION AT PENTAGON, ARLINGTON, VA MODIFICATION NO. A00017 REFERENCE NO. R00020 - CHANGE BA TOWER UPS BAT, ANTENNAE, CABLES INSTALL |
| May 5, 2026 | A00017 | $46.1K | DESCRIPTION OF AMENDMENT/MODIFICATION CONTRACT NO. W912DR21C0009 FOR PENTAGON CONTROL TOWER AND FIRE DAY STATION AT PENTAGON, ARLINGTON, VA MODIFICATION NO. A00017 REFERENCE NO. R00020 - CHANGE BA TOWER UPS BAT, ANTENNAE, CABLES INSTALL |
| Sep 30, 2025 | A00016 | $120.7K | CHANGE AY DUAL MOTORIZED SHADES FOR ATC CAB |
| Dec 20, 2024 | A00015 | $0 | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AZ - TIME EXT DUE TO MANUF DELAY |
| Sep 19, 2024 | A00014 | $211.7K | CONSTRUCT OF CONTROL TOWER/DAY STATION |
| Jul 23, 2024 | A00013 | $200.5K | CONSTRUCT OF CONTROL TOWER/DAY STATION |
| Mar 1, 2024 | A00012 | $0 | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AS - TO NOT PERMIT CONSTRUCTION TRAILERS |
| Feb 2, 2024 | A00011 | $9.0K | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AU PREWIRE TEMP ATC ANTENNAS FOR GOV RADIOS |
| Nov 2, 2023 | P00004 | $2.5M | PENTAGON CONTROL TOWER AND FIRE DAY STATION AT PENTAGON RESERVATION, ARLINGTON, VA. |
| Nov 2, 2023 | P00005 | $694.0K | PENTAGON CONTROL TOWER AND FIRE DAY STATION AT PENTAGON, ARLINGTON, VA |
| Oct 25, 2023 | A00010 | $159.7K | FIELD CHANGE AO - CONTRACTOR FURNISH ATC EQUIP UPS |
| Oct 20, 2023 | P00003 | $0 | PENTAGON CONTROL TOWER & FIRE DAY STATION |
| Aug 16, 2023 | A00009 | $0 | CHANGE AR-URC TO REMOVE TIE-IN TO 84" RCP |
| Aug 15, 2023 | A00008 | $131.5K | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AQ RECONFIGURE AND FEED 2 EX LIGHT POLES |
| Jul 6, 2023 | A00007 | $16.9K | CHANGE AB - ADD'L SECURITY INFRA. IAW RFI-40 |
| Apr 7, 2023 | A00006 | $20.9K | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AL ROOF ACCESS LADDER LOCATION |
| Apr 7, 2023 | P00002 | $739.7K | CONSTRUCT PENTAGON CONTROL TOWER AND FIRE DAY STATION AT PENTAGON, ARLINGTON, VA |
| Mar 29, 2023 | A00004 | $96.1K | CHANGE AE - URC 4-WEEK DESIGN REVIEW PERIOD |
| Mar 29, 2023 | A00005 | $46.4K | CHANGE AF RELOCATE TEMP TOWER TO SOD #5 |
| Mar 28, 2023 | A00003 | $71.2K | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AH - DELAYS IN ACCESSING ATFP DESIGN CRITERIA |
| Mar 23, 2023 | A00002 | $12.2K | CONSTRUCT OF CONTROL TOWER/DAY STATION, CHANGE AG MECHANICAL DESIGN CHANGE IAW RFIS 73& 74, PENTAGON, ARLINGTON, VA |
| May 11, 2022 | A00001 | $17.3K | CHANGE AD - DIGITAL VOICE RECORDER FOR TEMPORARY TOWER CONSTRUCT OF CONTROL TOWER/DAY STATION |
| Apr 29, 2021 | P00001 | $0 | PENTAGON CONTROL TOWER/DAY STATION IN ARLINGTON, VA - NOTICE TO PROCEED MODIFICATION |
| Mar 25, 2021 | 0 | $16.7M | CONSTRUCTION OF CONTROL TOWER AND FIRE DAY STATION, PENTAGON, ARLINGTON, VA |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.