Federal contract award
W912DR22C0012
ECB4 DESIGN & CONSTRUCTION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST BALTIMORE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $702.5M |
| Current contract value | $1.3B |
| Potential contract value / ceiling | $1.3B |
| Start date | May 1, 2022 |
| Current end date | May 18, 2026 |
| Potential end date | May 18, 2026 |
| Latest award activity | May 31, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 75 of 75 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 31, 2026 | A00054 | $214.4K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00069 CHANGE DW - REA - PP5 DSC, CONTRACT AMOUNT INCREASED $214,438.00 AND 0 CALENDAR DAY TIME EXTENSION. |
| Apr 28, 2026 | A00053 | $180.5K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00068 CHANGE DO - ADDITION OF AUXILIARY POWER SUPPLY, CONTRACT AMOUNT INCREASED $180,521.00 AND 0 CALENDAR DAY TIME EXTENSION. |
| Apr 24, 2026 | A00052 | $491.8K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00067 CHANGE DH - PDS CONNECTION - NORTH ECB4, CONTRACT AMOUNT INCREASED $491,758.00 AND 0 CALENDAR DAY TIME EXTENSION. |
| Mar 30, 2026 | A00051 | $0 | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00060 CHANGE DG - WEATHER DELAY, CONTRACT AMOUNT UNCHANGED AND 8 CALENDAR DAY TIME EXTENSION. |
| Feb 27, 2026 | A00050 | $-44.3K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00064 CHANGE DB - DELETE REPLACEMENT OF 167FT SANITARY SEWER, CONTRACT AMOUNT DECREASED ($44,263.00) AND 0 CALENDAR DAY TIME EXTENSION. |
| Feb 12, 2026 | A00049 | $-444.5K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00066 CHANGE CR - REDUCE NUMBER OF POWER FILTERS, CONTRACT AMOUNT DECREASED ($444,511.00) AND 0 CALENDAR DAY TIME EXTENSION. |
| Jan 28, 2026 | A00048 | $18.2K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00062 CHANGES DD, DI, DL, DM, CONTRACT AMOUNT INCREASED $18,190.00 AND 0 CALENDAR DAY TIME EXTENSION. |
| Jan 22, 2026 | A00047 | $389.9K | CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00065 CHANGE AV - TRAFFIC AND ROADWAY CHANGES, CONTRACT AMOUNT INCREASED $389,859.00 AND 0 CALENDAR DAY TIME EXTENSION. |
| Oct 21, 2025 | P00020 | $1.2M | ECB4 DESIGN & CONSTRUCTION |
| Aug 27, 2025 | A00046 | $121.2K | CY, DA, DC |
| Jul 11, 2025 | P00019 | $-632.1K | ECB4 DESIGN & CONSTRUCTION |
| Jun 27, 2025 | A00045 | $163.9K | CHANGE DJ-1 |
| Jun 16, 2025 | A00044 | $38.3K | CHANGES AR, CS, CV |
| May 15, 2025 | P00018 | $-1.1M | ECB4 DESIGN & CONSTRUCTION |
| May 8, 2025 | P00017 | $36.6K | ECB4 DESIGN & CONSTRUCTION |
| May 2, 2025 | P00016 | $1.2M | ECB4 DESIGN & CONSTRUCTION |
| Feb 28, 2025 | A00043 | $-4.4K | CHANGES CU & CZ |
| Nov 21, 2024 | A00042 | $493.8K | CHANGE CN |
| Oct 24, 2024 | A00040 | $49.6K | CHANGE BH |
| Oct 24, 2024 | A00041 | $-49.6K | MOD TO CANCEL A00040 |
| Sep 18, 2024 | A00039 | $-44.7K | CHANGE CP DELETE ACS DESK VENONA LOBBY |
| Sep 6, 2024 | P00015 | $1.7M | ECB4 DESIGN & CONSTRUCTION |
| Aug 22, 2024 | A00038 | $42.5K | CHANGE BJ PED STORAGE LOCKERS |
| Aug 21, 2024 | A00037 | $18.2K | CHANGE CQ OW SEPARATOR DISCHARGE TO STORM DRAIN |
| Aug 20, 2024 | A00036 | $15.1K | CHANGE CT HVAC REPAIRS |
| Aug 13, 2024 | A00035 | $67.8K | CHANGE CH REVISE FAMIS SPECIFICATIONS |
| Aug 9, 2024 | P00014 | $-718.4K | ECB4 DESIGN & CONSTRUCTION |
| Jun 20, 2024 | P00012 | $1.4M | ECB4 DESIGN & CONSTRUCTION |
| Jun 20, 2024 | P00013 | $277.1M | ECB4 DESIGN & CONSTRUCTION |
| May 1, 2024 | A00034 | $0 | CHANGE BU |
| Apr 19, 2024 | A00033 | $-18.3K | CHANGE CB |
| Apr 17, 2024 | A00032 | $-90.0K | CHANGE BV |
| Apr 16, 2024 | A00031 | $277.5K | CHANGES AJ, AK, & BC |
| Mar 12, 2024 | A00030 | $7.8K | CHANGE CK |
| Feb 23, 2024 | A00029 | $403.2K | CHANGE CE |
| Feb 7, 2024 | A00028 | $53.0K | CHANGE CJ |
| Feb 6, 2024 | A00026 | $223.5K | CHANGE AO |
| Feb 6, 2024 | A00027 | $71.7K | CHANGE AQ |
| Feb 5, 2024 | A00025 | $-16.7K | CHANGE CA |
| Feb 2, 2024 | P00011 | $378.4K | ECB4 DESIGN & CONSTRUCTION - CHANGE AF |
| Jan 11, 2024 | A00024 | $198.7K | CHANGE BF |
| Jan 9, 2024 | A00023 | $195.5K | CHANGE AN |
| Dec 22, 2023 | P00010 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Nov 7, 2023 | A00021 | $273.8K | CHANGE BY |
| Nov 7, 2023 | A00022 | $190.1K | CHANGE CG DISPOSE OF POLY-CHLORINATED BIPHENYL WASTE FROM BUILDING .9827 |
| Nov 6, 2023 | A00020 | $5.4K | CHANGE BO |
| Nov 3, 2023 | A00019 | $-22.3K | CHANGE BP |
| Nov 2, 2023 | A00017 | $6.3K | CHANGE BH |
| Nov 2, 2023 | A00018 | $-11.4K | CHANGE BM |
| Nov 1, 2023 | A00015 | $-22.5K | CHANGE BE |
| Nov 1, 2023 | A00016 | $-20.1K | CHANGE BI |
| Oct 31, 2023 | A00014 | $23.3K | CHANGE BN |
| Sep 21, 2023 | P00009 | $1.1M | ECB4 DESIGN & CONSTRUCTION |
| Jun 14, 2023 | A00013 | $0 | CHANGE BL |
| Jun 13, 2023 | A00012 | $0 | CHANGE BK |
| Apr 26, 2023 | A00011 | $-45.8K | CHANGE BD |
| Apr 12, 2023 | P00008 | $1.1M | ECB4 DESIGN & CONSTRUCTION |
| Apr 6, 2023 | A00010 | $-28.6K | CHANGE BB |
| Apr 3, 2023 | A00007 | $49.7K | CHANGE AY |
| Apr 3, 2023 | A00008 | $13.4K | CHANGE AS |
| Apr 3, 2023 | A00009 | $45.3K | CHANGE AM |
| Mar 31, 2023 | A00006 | $-7.2K | CHANGE BA |
| Mar 29, 2023 | P00007 | $332.5M | ECB4 DESIGN & CONSTRUCTION |
| Feb 27, 2023 | A00005 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Feb 22, 2023 | A00004 | $79.2K | CHANGE AH |
| Feb 21, 2023 | A00003 | $0 | CHANGE AW |
| Jan 18, 2023 | A00002 | $-200.5K | CHANGE AP DELETE 10% DESIGN LOAD S.F. |
| Jan 12, 2023 | A00001 | $-32.1K | CHANGE AB - DELETE DEMO OF COMM HUT B |
| Nov 21, 2022 | P00006 | $624.6K | ECB4 DESIGN & CONSTRUCTION |
| Aug 30, 2022 | P00005 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Jun 10, 2022 | P00004 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Jun 2, 2022 | P00003 | $64.4M | ECB4 DESIGN & CONSTRUCTION |
| May 17, 2022 | P00002 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Apr 26, 2022 | P00001 | $0 | ECB4 DESIGN & CONSTRUCTION |
| Apr 13, 2022 | 0 | $18.8M | ECB4 DESIGN & CONSTRUCTION |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.