Federal contract award

W912DR22C0012

ECB4 DESIGN & CONSTRUCTION

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW2SD ENDIST BALTIMORE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$702.5M
Current contract value$1.3B
Potential contract value / ceiling$1.3B
Start dateMay 1, 2022
Current end dateMay 18, 2026
Potential end dateMay 18, 2026
Latest award activityMay 31, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 75 of 75 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 31, 2026A00054$214.4KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00069 CHANGE DW - REA - PP5 DSC, CONTRACT AMOUNT INCREASED $214,438.00 AND 0 CALENDAR DAY TIME EXTENSION.
Apr 28, 2026A00053$180.5KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00068 CHANGE DO - ADDITION OF AUXILIARY POWER SUPPLY, CONTRACT AMOUNT INCREASED $180,521.00 AND 0 CALENDAR DAY TIME EXTENSION.
Apr 24, 2026A00052$491.8KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00067 CHANGE DH - PDS CONNECTION - NORTH ECB4, CONTRACT AMOUNT INCREASED $491,758.00 AND 0 CALENDAR DAY TIME EXTENSION.
Mar 30, 2026A00051$0CONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00060 CHANGE DG - WEATHER DELAY, CONTRACT AMOUNT UNCHANGED AND 8 CALENDAR DAY TIME EXTENSION.
Feb 27, 2026A00050$-44.3KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00064 CHANGE DB - DELETE REPLACEMENT OF 167FT SANITARY SEWER, CONTRACT AMOUNT DECREASED ($44,263.00) AND 0 CALENDAR DAY TIME EXTENSION.
Feb 12, 2026A00049$-444.5KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00066 CHANGE CR - REDUCE NUMBER OF POWER FILTERS, CONTRACT AMOUNT DECREASED ($444,511.00) AND 0 CALENDAR DAY TIME EXTENSION.
Jan 28, 2026A00048$18.2KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00062 CHANGES DD, DI, DL, DM, CONTRACT AMOUNT INCREASED $18,190.00 AND 0 CALENDAR DAY TIME EXTENSION.
Jan 22, 2026A00047$389.9KCONTRACT FOR EAST CAMPUS BUILDING 4 (ECB4) PROJECT, AT FORT MEADE, MARYLAND. REFERENCE NO. R00065 CHANGE AV - TRAFFIC AND ROADWAY CHANGES, CONTRACT AMOUNT INCREASED $389,859.00 AND 0 CALENDAR DAY TIME EXTENSION.
Oct 21, 2025P00020$1.2MECB4 DESIGN & CONSTRUCTION
Aug 27, 2025A00046$121.2KCY, DA, DC
Jul 11, 2025P00019$-632.1KECB4 DESIGN & CONSTRUCTION
Jun 27, 2025A00045$163.9KCHANGE DJ-1
Jun 16, 2025A00044$38.3KCHANGES AR, CS, CV
May 15, 2025P00018$-1.1MECB4 DESIGN & CONSTRUCTION
May 8, 2025P00017$36.6KECB4 DESIGN & CONSTRUCTION
May 2, 2025P00016$1.2MECB4 DESIGN & CONSTRUCTION
Feb 28, 2025A00043$-4.4KCHANGES CU & CZ
Nov 21, 2024A00042$493.8KCHANGE CN
Oct 24, 2024A00040$49.6KCHANGE BH
Oct 24, 2024A00041$-49.6KMOD TO CANCEL A00040
Sep 18, 2024A00039$-44.7KCHANGE CP DELETE ACS DESK VENONA LOBBY
Sep 6, 2024P00015$1.7MECB4 DESIGN & CONSTRUCTION
Aug 22, 2024A00038$42.5KCHANGE BJ PED STORAGE LOCKERS
Aug 21, 2024A00037$18.2KCHANGE CQ OW SEPARATOR DISCHARGE TO STORM DRAIN
Aug 20, 2024A00036$15.1KCHANGE CT HVAC REPAIRS
Aug 13, 2024A00035$67.8KCHANGE CH REVISE FAMIS SPECIFICATIONS
Aug 9, 2024P00014$-718.4KECB4 DESIGN & CONSTRUCTION
Jun 20, 2024P00012$1.4MECB4 DESIGN & CONSTRUCTION
Jun 20, 2024P00013$277.1MECB4 DESIGN & CONSTRUCTION
May 1, 2024A00034$0CHANGE BU
Apr 19, 2024A00033$-18.3KCHANGE CB
Apr 17, 2024A00032$-90.0KCHANGE BV
Apr 16, 2024A00031$277.5KCHANGES AJ, AK, & BC
Mar 12, 2024A00030$7.8KCHANGE CK
Feb 23, 2024A00029$403.2KCHANGE CE
Feb 7, 2024A00028$53.0KCHANGE CJ
Feb 6, 2024A00026$223.5KCHANGE AO
Feb 6, 2024A00027$71.7KCHANGE AQ
Feb 5, 2024A00025$-16.7KCHANGE CA
Feb 2, 2024P00011$378.4KECB4 DESIGN & CONSTRUCTION - CHANGE AF
Jan 11, 2024A00024$198.7KCHANGE BF
Jan 9, 2024A00023$195.5KCHANGE AN
Dec 22, 2023P00010$0ECB4 DESIGN & CONSTRUCTION
Nov 7, 2023A00021$273.8KCHANGE BY
Nov 7, 2023A00022$190.1KCHANGE CG DISPOSE OF POLY-CHLORINATED BIPHENYL WASTE FROM BUILDING .9827
Nov 6, 2023A00020$5.4KCHANGE BO
Nov 3, 2023A00019$-22.3KCHANGE BP
Nov 2, 2023A00017$6.3KCHANGE BH
Nov 2, 2023A00018$-11.4KCHANGE BM
Nov 1, 2023A00015$-22.5KCHANGE BE
Nov 1, 2023A00016$-20.1KCHANGE BI
Oct 31, 2023A00014$23.3KCHANGE BN
Sep 21, 2023P00009$1.1MECB4 DESIGN & CONSTRUCTION
Jun 14, 2023A00013$0CHANGE BL
Jun 13, 2023A00012$0CHANGE BK
Apr 26, 2023A00011$-45.8KCHANGE BD
Apr 12, 2023P00008$1.1MECB4 DESIGN & CONSTRUCTION
Apr 6, 2023A00010$-28.6KCHANGE BB
Apr 3, 2023A00007$49.7KCHANGE AY
Apr 3, 2023A00008$13.4KCHANGE AS
Apr 3, 2023A00009$45.3KCHANGE AM
Mar 31, 2023A00006$-7.2KCHANGE BA
Mar 29, 2023P00007$332.5MECB4 DESIGN & CONSTRUCTION
Feb 27, 2023A00005$0ECB4 DESIGN & CONSTRUCTION
Feb 22, 2023A00004$79.2KCHANGE AH
Feb 21, 2023A00003$0CHANGE AW
Jan 18, 2023A00002$-200.5KCHANGE AP DELETE 10% DESIGN LOAD S.F.
Jan 12, 2023A00001$-32.1KCHANGE AB - DELETE DEMO OF COMM HUT B
Nov 21, 2022P00006$624.6KECB4 DESIGN & CONSTRUCTION
Aug 30, 2022P00005$0ECB4 DESIGN & CONSTRUCTION
Jun 10, 2022P00004$0ECB4 DESIGN & CONSTRUCTION
Jun 2, 2022P00003$64.4MECB4 DESIGN & CONSTRUCTION
May 17, 2022P00002$0ECB4 DESIGN & CONSTRUCTION
Apr 26, 2022P00001$0ECB4 DESIGN & CONSTRUCTION
Apr 13, 20220$18.8MECB4 DESIGN & CONSTRUCTION

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.