Federal contract award
W912DY24F0545
FORT GREGG-ADAMS SISISKY GATE AVB INSTAL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2V6 USA ENG SPT CTR HUNTSVIL |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | W912DY21D0099 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.0M |
| Current contract value | $3.0M |
| Potential contract value / ceiling | $3.0M |
| Start date | Sep 30, 2024 |
| Current end date | Aug 7, 2026 |
| Potential end date | Aug 7, 2026 |
| Latest award activity | Apr 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 14, 2026 | A00003 | $141.5K | COMPENSATES THE CONTRACTOR IN FULL FOR THE WORK REQUIRED AS OUTLINED IN THE FINAL SOW DATED 8 APRIL 2026, THE CONTRACTOR PROPOSAL SUBMITTED 8 APRIL 2026 AND EXTENDS THE PERIOD OF PERFORMANCE FROM 15 MARCH 2026 TO 7 AUGUST 2026. |
| Feb 5, 2026 | A00002 | $102.0K | COMPENSATES THE CONTRACTOR IN FULL FOR THE WORK REQUIRED AS OUTLINED IN THE FINAL SOW DATED 4 FEB 2026, THE CONTRACTOR PROPOSAL SUBMITTED 3 FEB 2026 AND DOES NOT CHANGE EXISTING POP OF 15 MARCH 2026. |
| Nov 24, 2025 | A00001 | $292.7K | COMPENSATES THE CONTRACTOR IN FULL FOR THE WORK REQUIRED AS OUTLINED IN THE FINAL SOW DATED 15 OCTOBER 2025, THE CONTRACTOR PROPOSAL SUBMITTED 5 NOVEMBER 2025 AND EXTENDS THE POP FROM 2 JANUARY 2026 TO 15 MARCH 2026. |
| Aug 29, 2025 | P00001 | $45.7K | MOD P00001 |
| Sep 27, 2024 | 0 | $2.4M | FORT GREGG-ADAMS SISISKY GATE AVB INSTAL |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.