Federal contract award
W912EF22C0002
LOWER MONUMENTAL DAM DC SYSTEM AND LV (LOW VOLTAGE) SWITCHGEAR UPGRADES
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | US ARMY ENGINEER DISTRICT WALLA WAL |
| NAICS | 238210 — Electrical Contractors and Other Wiring Installation Contractors |
| PSC | Z2KA — REPAIR OR ALTERATION OF DAMS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $14.3M |
| Current contract value | $14.3M |
| Potential contract value / ceiling | $14.3M |
| Start date | Apr 21, 2022 |
| Current end date | Jun 2, 2025 |
| Potential end date | Jun 2, 2025 |
| Latest award activity | May 8, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 18 of 18 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 8, 2026 | A00013 | $52.3K | RELOCATE SU4 CONTRACT FOR LMA DC SYSTEM AND LV SWITCHGEAR UPGRADES AT LOWER MONUMENTAL DAMREFERENCE NO. A00012 |
| Feb 4, 2026 | A00012 | $382.5K | RELOCATE SU4 CONTRACT FOR LMA DC SYSTEM AND LV SWITCHGEAR UPGRADES AT LOWER MONUMENTAL DAMREFERENCE NO. A00012 |
| Nov 17, 2025 | A00011 | $19.4K | HEAD COVER PUMP VFD & SB CONDUIT ROUTING |
| Sep 8, 2025 | A00010 | $89.4K | FEEDERS, TRAY, WIRING CABLE. |
| Jun 23, 2025 | A00009 | $32.8K | FEEDERS AND RECEPTACLES |
| May 2, 2025 | A00008 | $-59.7K | SU CONTROL CHANGES |
| Apr 25, 2025 | A00007 | $-236.4K | SSHO REVISION |
| Mar 31, 2025 | PP0001 | $0 | IMPLEMENT EXECUTIVE ORDER 14148 INITIAL RESCISSIONS OF HARMFUL EXECUTIVE ORDERS AND ACTIONS AND CLASS DEVIATION 2025-O0004-REVOCATION OF EXECUTIVE ORDER ON SUSTAINABILITY |
| Feb 5, 2025 | A00006 | $8.1K | CE & CH LOCATIONS |
| Oct 16, 2024 | P00004 | $2.7M | INCREMENTAL CONTRACT FUNDING. |
| Oct 3, 2024 | A00005 | $31.3K | DC CONDUIT ROUTING, SOFT STARTER REMOVAL |
| Jan 31, 2024 | A00003 | $63.8K | SKIMER, PURIFIER, AMMETER, FEEDERS, CUT. |
| Jan 31, 2024 | A00004 | $5.7K | CQO4 ACCESS HATCH & CABLE ROUTING UPDATE |
| Jan 30, 2024 | A00002 | $243.0K | CABLE TRAYS CABLE AND BREAKERS CHANGES. |
| Jan 25, 2024 | A00001 | $0 | TIME EXTENSION |
| Dec 20, 2023 | P00002 | $3.8M | THE PURPOSE OF THIS MODIFICATION IS TO FUND THIS CONTRACT IN ACCORDANCE WITH INCREMENTALLY FUNDED CONTRACTS. |
| Apr 12, 2023 | P00001 | $4.4M | INCREMENTAL FUNDING MODIFICATION FOR LOWER MONUMENTAL DC SYSTEM AND LV SWITCHGEAR UPGRADES |
| Apr 21, 2022 | 0 | $2.7M | LOWER MONUMENTAL DAM DC SYSTEM AND LV (LOW VOLTAGE) SWITCHGEAR UPGRADES |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.