Federal contract award

W912EK22C0016

CEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT, REACH 1 MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE- BASE PLUS OPTION A AND OPTION B.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW07V ENDIST ROCK ISLAND
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1QA — CONSTRUCTION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$17.2M
Current contract value$17.2M
Potential contract value / ceiling$25.1M
Start dateApr 14, 2022
Current end dateOct 1, 2026
Potential end dateOct 1, 2026
Latest award activityApr 21, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 21 of 21 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 10, 2026A00012$43.1KCEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE
Apr 21, 2026A00011$21.8KCEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE
Jan 28, 2026P00008$0CEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE
Oct 21, 2025P00007$4.1MCEDAR RAPIDS FLOOD RISK MANAGE PROJECT MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE AT CEDAR RAPIDS, LINN COUNTY, IA. THIS MOD IS TO EXTEND THE LEVEE DOWNSTREAM TO TIE INTO THE NEWLY CONSTRUCTED LEVEE UNDER THE CITYS CEDAR LAKE LEVEE CONTRACT.
Mar 4, 2025A00010$3.3KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Nov 26, 2024A00009$52.9KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Sep 24, 2024A00008$4.6KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Jul 18, 2024A00007$7.5KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Dec 21, 2023A00006$32.8KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Nov 16, 2023A00005$136.3KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Oct 23, 2023P00006$0CEDAR RAPIDS - CONSTRUCTION CONTRACT - MCLOUD RUN LOWER CHANNEL
Oct 10, 2023A00004$6.8KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Sep 5, 2023A00003$75.2KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Jun 27, 2023A00002$3.1KCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
May 24, 2023P00005$0CEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Apr 17, 2023P00004$5.4MCEDAR RAPIDS - CONSTRUCTION CONTRACT - M
Apr 11, 2023P00003$0MCLOUD REACH LOWER RUN-MODIFICATION TO CORRECT THE PAYMENT OFFICE AND TO EXTEND THE PERIOD FOR EXERCISING OPTION A BY 30 DAYS TO 24 MAY 2023.
Jan 24, 2023P00002$946.4KMCLOUD REACH LOWER RUN- OPTION B
Sep 16, 2022A00001$20.0KCONTRACT FOR FLOODRISKMGMT PROJECT MCLOUD REACH LOWER RUN CULVERTS&LEVEE AT CEDAR RAPIDS,LINN COUNTY,IA. REF NO CA0001-1 CHANGE ORDER FOR DIFFERING SITE CONDITIONS-CONTAMINATEDSOIL FOUND. CONTRACT PRICEINCREASEDBY $20,000.00,NO COMPLETIONDATECHANGE
Jul 22, 2022P00001$4.2MMCLOUD REACH LOWER RUN- MODIFICATION TO EXERCISE OPTION B AND SET THE COMPLETION DATE.
Apr 14, 20220$2.2MCEDAR RAPIDS FLOOD RISK MANAGEMENT PROJECT, REACH 1 MCLOUD RUN LOWER REACH CHANNEL, CULVERTS AND LEVEE- BASE PLUS OPTION A AND OPTION B.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.