Federal contract award
W912EP21C0021
CENTRAL EVERGLADES PLANNING PROJECT (CEPP) CONTRACT 10A, EAA SEEPAGE AND INFLOW / OUTFLOW CANAL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST JACKSNVLLE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1KB — CONSTRUCTION OF CANALS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $102.8M |
| Current contract value | $102.8M |
| Potential contract value / ceiling | $102.8M |
| Start date | Sep 23, 2021 |
| Current end date | Sep 22, 2025 |
| Potential end date | Sep 22, 2025 |
| Latest award activity | Nov 19, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Nov 19, 2025 | P00010 | $0 | CONTRACTOR NAME CHANGED FROM PHILLIPS AND JORDAN, INC. TO PHILLIPS HEAVY, INC. |
| Sep 5, 2025 | A00012 | $-20.0K | EXCAVATION |
| Aug 14, 2025 | P00009 | $1.7M | CEPP EAA CNT 10A, MOD ER005 CLEAR, GRUBBING, AND DEMUCKING VEQ |
| Jul 16, 2025 | A00011 | $-94.3K | MODIFICATION NO. A00011 R00020 - CANAL CROSSING DE-SCOPE |
| Jul 2, 2025 | A00010 | $0 | MODIFICATION NO. A00010 R00019 - REA-003 SELECT FILL TIME IMPACTS |
| Jun 6, 2025 | A00009 | $106.0K | ER003 ADDITIONAL MUCK AND SOD INSTALLATION |
| Mar 7, 2025 | A00008 | $60.0K | CONTRACTING OFFICER TRAILER EXTENSION |
| Feb 21, 2025 | P00008 | $7.6M | REA-002 FPL CORRIDOR |
| Feb 12, 2025 | P00007 | $8.0M | TESTING FREQUENCY VARIANCE MODIFICATION |
| Jan 16, 2025 | P00006 | $-8.2M | EXCAVATION |