W912EP23C0005
CENTRAL EVERGLADES PLANNING PROJECT (CEPP) SOUTH CONTRACT 1A(R), L-67A STRUCTURES (S-631, S-632, AND S-633) SPOIL PILE REMOVAL AND AGRICULTURAL DITCH BACKFILL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST JACKSNVLLE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $66.9M |
| Current contract value | $66.9M |
| Potential contract value / ceiling | $66.9M |
| Start date | Dec 19, 2022 |
| Current end date | Mar 28, 2027 |
| Potential end date | Mar 28, 2027 |
| Latest award activity | May 5, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 20 of 20 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 5, 2026 | A00011 | $25.5K | CEPP SOUTH CNT 1A(R) |
| Dec 5, 2025 | A00010 | $84.7K | EXCAVATION |
| Sep 25, 2025 | P00008 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT FUNDING SOURCE FOR MODIFICATION P00007. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Sep 19, 2025 | A00009 | $0 | EXCAVATION |
| Sep 16, 2025 | P00007 | $2.6M | RR017 CLAIMS 001-004 SETTLEMENT |
| Sep 8, 2025 | P00006 | $975.0K | RR014 VEQ ROCK EXCAVATION 115% |
| Aug 4, 2025 | P00005 | $-277.8K | VECP CNT1 L67A TURN-AROUND |
| Jun 11, 2025 | A00008 | $11.8K | EXCAVATION |
| May 30, 2025 | A00007 | $-41.6K | EXCAVATION |
| May 22, 2025 | A00006 | $18.1K | EXCAVATION |
| May 14, 2025 | A00005 | $0 | EXCAVATION |
| Apr 17, 2025 | A00004 | $9.1K | EXCAVATION |
| Feb 13, 2025 | A00003 | $175.3K | EXCAVATION |
| Nov 8, 2024 | A00002 | $0 | EXCAVATION |
| Aug 12, 2024 | P00004 | $0 | RR005 COFFERDAM TRANSMITTALS (REA-001). |
| Aug 2, 2024 | A00001 | $493.6K | RR004 S-633 WEST COFFERDAM TEST SECTION EXCAVATION. |
| Aug 4, 2023 | P00003 | $0 | FUNDING ONLY MODIFICATION |
| May 8, 2023 | P00002 | $22.5M | EXCAVATION |
| Feb 3, 2023 | P00001 | $0 | NOTICE TO PROCEED (NTP) FOR LINE ITEMS 0001 THROUGH 0057. |
| Dec 19, 2022 | 0 | $42.3M | CENTRAL EVERGLADES PLANNING PROJECT (CEPP) SOUTH CONTRACT 1A(R), L-67A STRUCTURES (S-631, S-632, AND S-633) SPOIL PILE REMOVAL AND AGRICULTURAL DITCH BACKFILL |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
65/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 65/100. Available recorded signals: 60 points.
- Contract end 2027-03-28 (154 days from calculation)
- +35 points
- 1 historical awards in this buyer and category group
- +0 points
- 20 recorded award transactions
- +10 points
- Latest award action: 2026-05-05
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.