Federal contract award
W912EP24C0021
COMPREHENSIVE EVERGLADES RESTORATION PLAN, INDIAN RIVER LAGOON SOUTH, C-23/C-24 NORTH RESERVOIR, S-426, CONTRACT 4A PROJECT, ST. LUCIE COUNTY, FLORIDA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST JACKSNVLLE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1KB — CONSTRUCTION OF CANALS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $196.0M |
| Current contract value | $196.0M |
| Potential contract value / ceiling | $196.0M |
| Start date | Oct 15, 2024 |
| Current end date | May 10, 2028 |
| Potential end date | May 10, 2028 |
| Latest award activity | May 6, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 30 of 30 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 6, 2026 | A00024 | $-59.9K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Apr 29, 2026 | A00023 | $24.0K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Apr 27, 2026 | A00022 | $20.3K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Apr 20, 2026 | A00021 | $214.2K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Mar 24, 2026 | A00020 | $63.1K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Mar 3, 2026 | A00018 | $337.2K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Mar 3, 2026 | A00019 | $110.3K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Feb 27, 2026 | A00017 | $198.0K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Feb 25, 2026 | A00016 | $28.6K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Feb 5, 2026 | A00015 | $90.0K | IRL-S C-23/24 NORTH RESERVOIR S-426 CNT 4A |
| Dec 5, 2025 | A00013 | $287.7K | WR019 MUCK AREA ACCESS ROAD MITIGATION |
| Dec 5, 2025 | A00014 | $498.4K | WR010 REVISION OF PUMP STATION CONTROL SHEETS |
| Dec 1, 2025 | A00012 | $23.9K | WR023 (REA-001), WR024 (REA-002), WR025 (REA-003), WR027 (REA-004) |
| Nov 18, 2025 | A00011 | $-39.6K | WR017 BENTONITE CHIP VARIANCE |
| Oct 27, 2025 | A00010 | $27.3K | WR026 PERMANENT POWER CONDUIT INSTALLATION |
| Oct 1, 2025 | P00005 | $0 | NTP PHASE III |
| Sep 29, 2025 | P00004 | $702.0K | WR012 - INTERIM VEQ FOR CLIN 0056 EXISTING CANALS AND DITCHES EXCAVATION |
| Sep 25, 2025 | A00009 | $62.3K | WR015& WR016 - G-791 & PC-37 JOINT REVISIONS/WEATHER TIME EXT. JUL - AUG |
| Sep 4, 2025 | A00008 | $19.1K | WR0011 - SWITCH BOX ACCESS ROAD |
| Aug 20, 2025 | A00007 | $109.9K | WR009 VERTICAL PUMPS MISC. ADJUSTMENTS |
| Jul 31, 2025 | A00006 | $0 | WR014 TIME EXTENSION JAN 25- JUN 25 |
| Jun 12, 2025 | A00005 | $33.3K | WR001 PC-37 & G-791 REINFORCEMENT |
| Jun 12, 2025 | P00003 | $0 | S-426 CIP CONCRETE AND REINFORCEMENT -- CLAUSES UPDATE MOD TO IMPLEMENT EXECUTIVE ORDER 14173 |
| Jun 4, 2025 | A00004 | $4.5K | WR005 ROW DESCOPE & RELOCATION |
| Jun 3, 2025 | A00003 | $188.6K | WR007 PARTNERING EXTENSIONS |
| Apr 24, 2025 | P00002 | $0 | PARTIAL NTP TO BEGIN WORK UNDER THE SUBJECT CONTRACT FOR PHASE 3 ON CLIN 0004 G-791 UNGATED CULVERT. |
| Apr 17, 2025 | A00002 | $95.5K | WR002 ADDITIONAL FENCING |
| Mar 14, 2025 | A00001 | $0 | WR003 BORROW SHIFT /WR006 EM-385-1-1 UPDATE |
| Oct 29, 2024 | P00001 | $0 | S-426 CIP CONCRETE AND REINFORCEMENT |
| Sep 30, 2024 | 0 | $192.8M | COMPREHENSIVE EVERGLADES RESTORATION PLAN, INDIAN RIVER LAGOON SOUTH, C-23/C-24 NORTH RESERVOIR, S-426, CONTRACT 4A PROJECT, ST. LUCIE COUNTY, FLORIDA. |
Estimated positioning window
May 10, 2027 – Nov 10, 2027
70/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 70/100. Available recorded signals: 65 points.
- Contract end 2028-05-10 (556 days from calculation)
- +25 points
- 9 historical awards in this buyer and category group
- +15 points
- 30 recorded award transactions
- +10 points
- Latest award action: 2026-05-06
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.