Federal contract award

W912ES20C0001

WILD RICE RIVER STRUCTURE.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW07V ENDIST ST PAUL
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1KA — CONSTRUCTION OF DAMS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$64.7M
Current contract value$64.7M
Potential contract value / ceiling$64.7M
Start dateNov 27, 2019
Current end dateJun 17, 2026
Potential end dateJun 17, 2026
Latest award activityJun 10, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 33 of 33 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 10, 2026A00024$-65.2K(R-059) ADJUST THE CONTRACT QUANTITIES TO FINAL QUANTITIES FOR THE FOLLOWING: CLIN 0007, CLIN 0008AB, CLIN 0009AB, CLIN 0023, CLIN 0049, CLIN 0050, CLIN 0072, CLIN 1005. (R-067) RELOCATE THE GENERATOR RECEPTACLE.
Sep 18, 2025A00022$6.4K(R-066) CORRECT FLOW CALCULATION EQUATIONS FOR THE PLC SYSTEM.
Jul 2, 2025A00021$235.1KREVISE ELECTRICAL PLANS RUN NEW CONDUIT ADD A LOW FLOW RADAR AND WIRE WEIGHT MOUNT THAT RELOCATES AND REPLACES MOUNTS ADD A WIND SENSOR TOWER AND TOWER FOUNDATION REPLACE THE EXISTING SQUARE ALUMINUM LIGHT POLES.
Jun 13, 2025A00020$138.4K(R-57) CHANGE WHERE THE STAIRWELLS ON THE EAST AND WEST SIDE OF THE RIVER ARE ANCHORED TO. (R-65) RECONFIGURE THE PLC/ HMI SYSTEM AND INCLUDE MODBUS COMMUNICATION TO USGS EQUIPMENT ADD A STEEL GRAB BAR ASSEMBLY AND INSTALL A SIX-FOOT SAFETY CHAIN.
Apr 14, 2025A00019$448.9KDIRECT THE CONTRACTOR TO REMOVE AND REPLACE TURF REINFORCING MAT AND RE-SEED AREAS OF THE EMBANKMENT.
Apr 11, 2025A00018$-32.5KDEFINITIZE RECONSTRUCT EAST BERM
Mar 14, 2025P00009$1.5MSTRU - CONTROL STRUCTURE/STILLING BASINS
Mar 6, 2025A00017$64.7KSTRU - CONTROL STRUCTURE/STILLING BASINS
Feb 28, 2025A00016$-271.7KDECREASE THE CONTRACT QUANTITY TO A FINAL QUANTITY FOR CLINS 0031AB STEEL H PILE OVER 50,000 LF AND 0032AB STEEL H PILE OVER 2,000 LF, AND ADD CLIN 0085 STEEL SHEET PILE OVER 24,000 SF.
Nov 22, 2024A00015$161.2KADD R-064 STOCKPILE GRADING EAST OF THE WILD RICE RIVER, ADD 243 ADDITIONAL CALENDAR DAYS TO THE CONTRACT.
Aug 15, 2024P00008$450.0KOF THE NOT TO EXCEED PRICE PRIOR TO SUBMITTING A PRICE PROPOSAL ACCEPTABLE TO THE CONTRACTING OFFICER. THIS CONTRACT MODIFICATION OBLIGATES $450,000.00, WHICH IS 50% OF THE NOT TO EXCEED PRICE OF THIS MODIFICATION.
Mar 26, 2024A00014$229.7KTHIS CONTRACT IS MODIFIED TO: ADD 1) R-049 TRANSFORMER PAD-PLC-HANDRAIL CHANGES 2) R-050 J-BULB SEAL CHANGES 3) R-051 INSTALLATION OF SURVEY MONITORING POINTS 4) R-052 REA TEMPORARY ACCESS CROSSING 5) REA I-29 TIE-IN.
Oct 12, 2023A00013$28.1KREMOVE 10.5 INCHES FROM THE LENGTH OF THE DOGGING PLATFORM. MAKE THE ADJUSTMENTS NECESSARY TO ENSURE THE PLATFORMS NO LONGER INTERFERE WITH THE GATE OPERATION CABLES AS THE GATE RAISES AND LOWERS.
Sep 18, 2023A00012$98.7KSAFETY AND DOGGING PLATFORM REVISIONS. ADDITIONAL POST TENSIONING OF THE LONGITUDINAL PT BAR.
Jul 21, 2023A00011$147.8KSTRU - CONTROL STRUCTURE/STILLING BASINS
Jun 1, 2023A00010$196.7KSTRU - CONTROL STRUCTURE/STILLING BASINS
Sep 23, 2022P00007$1.2MSTRU - CONTROL STRUCTURE/STILLING BASINS
Aug 26, 2022A00009$-12.2KSTRU - CONTROL STRUCTURE/STILLING BASINS
Jul 14, 2022P00006$1.3MTHIS CONTRACT IS MODIFIED TO: PROVIDE THE DEWATERING BULKHEADS AND LIFTING BEAM TO REPLACE THE GIRDER AND PANEL SYSTEM THAT WAS ELIMINATED UNDER MODIFICATION P00005 DATED MARCH 22, 2021.
Apr 12, 2022A00008$2.1KMULTIPLE REVISIONS AND CLARIFICATIONS IN DESIGN SHEETS INCLUDING REVISION OF THE BRIDGE BEAM SEATS AND WIRE ROPE OPENINGS ON THE MECHANICAL PLATFORM CHANGING THE REINFORCEMENT AND PRESTRESSED STEEL STRANDS LAYOUT
Oct 15, 2021A00007$50.0KTHIS CONTRACT IS MODIFIED TO: ADD TWO ELECTRICAL LIGHT POLES ON THE EAST AND WEST ABUTMENTS, AND THE CHANGES AND ADDITIONS OF EMBEDDED ELECTRICAL CONDUITS TO SERVE THE UPSTREAM AND DOWNSTREAM GAUGE WELLS THAT WILL BE ADDED UNDER A LATER MODIFICATION.
Sep 21, 2021A00006$23.7K1) ADD DOVETAIL SLIP JOINTS 2) CHANGE ABUTMENT ANCHOR GALLERY 3) CLARIFY LIFTING EYE DOGGING BRACKET 4) CHANGE FALL PROTECTION FRAME 5) CHANGE CONTROL BUILDING ROOF 6) CHANGE ABUTMENT ANCHOR GALLERY PLATE 7) CLARIFY TRUNNION YOKE PIN DIMENSIONS
Jul 14, 2021A00005$48.8KR-029 VEQ FOR CLIN 0033AB STEEL PIPE PILE (24"X3/4")-OVER 5,800 LF
Jun 18, 2021A00004$27.3KR-015 APPROACH WALL JOINT CHANGES, R-018 TRANSVERSE TIES, R-023 TENSION HOOK CONNECTOR ADJUSTMENT
Mar 22, 2021P00005$-869.8KTHIS IS THE FIRST OF A TWO PART MODIFICATION. THIS FIRST PART REMOVES THE DEWATERING SYSTEM FROM THE CONTRACT AND CHANGES THE CONFIGURATION OF THE DEWATERING BULKHEAD SLOTS, SLOT EMBEDS AND BOTTOM SILL BEAM EMBEDS TO ACCOMMODATE BULKHEADS.
Jan 11, 2021A00003$65.7KINTERNET SERVICE TO FIELD OFFICEINCREASE PIPE PILE CAPACITY & CHANGE THE PILE TIP ELEVATION CHANGE CAST-IN-PLACE TESTING REQUIREMENTS MODIFY THE APPROACH WALL MONOLITH & FOOTING CONFIGURATION & REMOVE BOTTOM SEAL FROM TAINTER GATE DESIGN.
Sep 29, 2020P00004$-382.8KTHIS CONTRACT IS MODIFIED TO: REMOVE THE PILE LOAD TEST REQUIREMENT FROM THE CONTRACT AND COMPENSATE THE CONTRACTOR FOR ANY COSTS INCURRED TO DATE AND IMPACT COSTS DUE TO THE REMOVAL.
Sep 10, 2020A00002$23.7KTHIS CONTRACT IS MODIFIED TO R03-CLARIFY THE COLOR OF CONTROL WALLS, R05-CORRECT A TYPO ERROR IN AN OUTPUT TORQUE, R09-ADD STRUCTURAL CLARIFICATIONS TO SHEET S-400, AND R11-ADD DIMENSIONS, NOTES, CALLOUTS, AND REVISIONS TO 10 TAINTER GATE DRAWINGS.
Jun 18, 2020A00001$80.3KTHIS CONTRACT IS MODIFIED TO-EXTEND THE SAND DRAIN, TOE DRAIN COLLECTOR PIPE, AND ADD A MANHOLE AND TOE DRAIN DISCHARGE PIPE AND HEADWALL ON THE DOWNSTREAM (NORTH) SIDE OF THE DAM WHERE IT CROSSES THE EXISTING WILD RICE RIVER CHANNEL.
Apr 22, 2020P00003$663.7KWILD RICE RIVER OPTION 1
Apr 17, 2020P00002$0FUNDING CHANGE MODIFICATION.
Jan 10, 2020P00001$0MOD 1 TO EXTEND THE COMPLETION DATE DUE TO NTP NOT BEING ISSUED AS SOLICITED.
Nov 27, 20190$58.8MWILD RICE RIVER STRUCTURE.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.