Federal contract award
W912ES21C0004
I-29 GRADE RAISE AND BORROW DITCH CROSSING OF THE FARGO MOORHEAD METROPOLITAN AREA FLOOD RISK MANAGEMENT PROJECT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W07V ENDIST ST PAUL |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $68.2M |
| Current contract value | $68.2M |
| Potential contract value / ceiling | $68.2M |
| Start date | May 7, 2021 |
| Current end date | Jun 30, 2024 |
| Potential end date | Jun 30, 2024 |
| Latest award activity | May 28, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 25 of 25 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 28, 2026 | P00008 | $1.1M | ADJUSTMENT TO LINE ITEMS |
| May 22, 2026 | P00007 | $-2.2M | ADJUSTMENT TO LINE ITEMS |
| Oct 25, 2023 | A00016 | $42.8K | R-033: THE DELETION OF THE #9 DEFORMED BARS AT MID-PANEL DEPTH AND ADJUST THE TRANSITIONS OF THE SOUTHBOUND SOUTH AND NORTH TIE-INS AS REFERENCED IN RFI-0046. R-034 TRAFFIC CONTROL CHANGES. R-036 ADDITIONAL TRAFFIC CONTROL. |
| Jul 18, 2023 | A00015 | $412.6K | INCREASE IN THE QUANTITY OF DAM AND LEVEE EMBANKMENT AND INSPECTION TRENCH DUE TO AN ERROR IN QUANTITY CALCULATION DURING THE DESIGN PHASE. |
| Jun 13, 2023 | P00006 | $129.6K | PERMANENT I-29 MAINLINE ROADWAY |
| Mar 28, 2023 | A00014 | $96.9K | TRAFFIC CONTROL REQUIRED TO CLOSE THE COUNTY ROAD 16 INTERCHANGE RAMPS TO ALLOW THE CONTRACTOR TO MOVE IN PHASE 6 AND 7 OF THE PROJECT. CONTRACTOR WILL NOT BE REQUIRED TO BUILD THE TEMPORARY RAMP CONNECTIONS. |
| Mar 20, 2023 | A00013 | $154.7K | INCORPORATE NDDOT DRAWINGS, RECOVER FIXED COSTS DUE TO AN UNDERRUN IN QUANTITY, MODIFY DRAWINGS FOR GUARDRAIL INSTALLATION. |
| Feb 24, 2023 | P00005 | $559.6K | FMM I-29 GRADE RAISE AND BORROW DITCH CROSSING - VARIATION IN ESTIMATED QUANTITY CONTRACT MODIFICATION |
| Jan 19, 2023 | A00012 | $-287.2K | THIS CONTRACT IS MODIFIED TO: ADJUST CONTRACT QUANTITIES TO INTERIM QUANTITIES FOR CLIN 0017 PIPE CONDUIT 42-INCH, AND CLIN 0018 PIPE CONDUIT 54-INCH. ADJUST CONTRACT QUANTITIES TO ACTUAL FINAL QUANTITIES FOR CLIN 0046 GRANULAR BLANKET DRAIN. |
| Nov 23, 2022 | A00011 | $407.8K | THIS CONTRACT IS MODIFIED TO CONSTRUCT 2 STABILIZATION BERMS, INCREASE THE BORROW DITCH WIDTH, EXTEND THE SOUTHERN EMBANKMENT AND TO COMPENSATE THE CONTRACTOR FOR UNRECOVERED FIXED COSTS DUE TO QUANTITY UNDERRUNS. |
| Oct 27, 2022 | A00010 | $176.8K | REMOVAL OF CROSSOVERS, ELIMINATION OF SHAPE ARRAY PIPING, ADDITION OF EXTRA SIGNS FOR TRAFFIC SAFETY. |
| Sep 27, 2022 | P00004 | $190.9K | PERMANENT I-29 MAINLINE ROADWAY |
| Sep 1, 2022 | A00009 | $182.4K | ADD SIGNS TO THE COUNTY ROAD 18/81 INTERSECTION FOR TRAFFIC SAFETY AND PERFORM BUMP REPAIR ON THE I-29 BYPASS. |
| May 3, 2022 | A00008 | $107.6K | THIS CONTRACT IS MODIFIED TO COMPENSATE THE CONTRACTOR FOR FIXED COSTS NOT RECOVERED DUE TO A REDUCTION IN QUANTITY ALONG WITH COMPENSATION FOR VARIOUS ERRORS IN THE DRAWINGS AND USER REQUESTS. |
| Apr 28, 2022 | A00007 | $-180.6K | THIS CONTRACT IS MODIFIED TO: DECREASE CLIN 0045 VERTICAL WICK DRAIN TO 380,000 LF DUE TO AN ERROR IN CALCULATIONS DURING DESIGN AND TO CAPTURE THE ACTUAL QUANTITY INSTALLED. |
| Mar 4, 2022 | A00006 | $19.2K | THIS CONTRACT IS MODIFIED TO ADD DELINEATORS, MILE MARKERS, AND OBJECT MARKERS ALONG THE I-29 TEMPORARY BYPASS AND TO ADD DELINEATORS TO THE TEMPORARY INTERSTATE RAMP CONNECTIONS INSTALLED. |
| Dec 10, 2021 | A00005 | $0 | THIS CONTRACT IS MODIFIED TO: EXTEND THE RED RIVER BORROW INTERIM COMPLETION DATE BY 12 CALENDAR DAYS FROM 16 OCTOBER 2021 TO 28 OCTOBER 2021 FOR UNUSUALLY SEVERE WEATHER DURING THE MONTH OF OCTOBER 2021. |
| Oct 15, 2021 | A00004 | $0 | THIS CONTRACT IS MODIFIED TO: THIS MODIFICATION EXTENDS THE RED RIVER BORROW INTERIM COMPLETION DATE BY 8 CALENDAR DAYS FROM 08 OCTOBER 2021 TO 16 OCTOBER 2021 FOR UNUSUALLY SEVERE WEATHER BETWEEN MAY 2021 AND SEPTEMBER 2021. |
| Sep 14, 2021 | A00003 | $8.7K | THIS CONTRACT IS MODIFIED TO INSTALL ADDITIONAL SIGNS ON HWY 81 AND REIMBURSE THE CONTRACTOR FOR THE GOVERNMENT SHARE OF THE PARTNERING EXPENSE. |
| Sep 2, 2021 | A00002 | $87.4K | THIS CONTRACT IS MODIFIED TO ADJUST THE ESTIMATED QUANTITIES TO INTERIM QUANTITIES FOR PIPE CONDUIT CLINS 0009, 0012, 0013, 0014, 15, 0016, 0017, 0018. |
| Jul 30, 2021 | A00001 | $50.0K | REMOVE THE NORTH AND SOUTH CROSSOVERS INSTALLED UNDER NDDOT CONTRACT #IM-8-029(194)053. WORK INCLUDES SALVAGED BASE COURSE REMOVAL, ASPHALT REMOVAL, GEOSYNTHETIC MATERIAL REMOVAL, MATERIAL DISPOSAL, AND NECESSARY TRAFFIC CONTROL. |
| May 24, 2021 | P00003 | $0 | I-29 GRADE RAISE NO-COST ADMINISTRATIVE MODIFICATION, FARGO, ND |
| May 4, 2021 | P00002 | $0 | I-29 GRADE RAISE NO-COST CHANGE |
| Apr 15, 2021 | P00001 | $0 | I-29 GRADE RAISE AND BORROW DITCH CROSSING MODIFICATION |
| Apr 8, 2021 | 0 | $67.0M | I-29 GRADE RAISE AND BORROW DITCH CROSSING OF THE FARGO MOORHEAD METROPOLITAN AREA FLOOD RISK MANAGEMENT PROJECT |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.