Federal contract award
W912ES23C0007
ROADS WEST PROJECT AT ST. CLOUD VA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W07V ENDIST ST PAUL |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z2LB — REPAIR OR ALTERATION OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $5.7M |
| Current contract value | $5.7M |
| Potential contract value / ceiling | $5.7M |
| Start date | Jun 16, 2023 |
| Current end date | Oct 31, 2025 |
| Potential end date | Oct 31, 2025 |
| Latest award activity | Mar 27, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 27, 2025 | A00005 | $115.1K | REA-003: STOCKPILING UNSUITABLE SOIL, HAULING OFF AND IMPORTING SUITABLE SOIL TO REPLACE UNACCEPTABLE MATERIAL. REA-004: RETAINING WALL FOUNDATION DEMOLITION. REA-005: ADDITIONAL ASPHALT PAVEMENT TO AN EXISTING LOW POINT. |
| Dec 18, 2024 | A00004 | $35.5K | INSTALL NEW STORM SEWER PIPING BETWEEN THE GEOTHERMAL AND LOW VOLTAGE DUCT BANKS AND CHANGE THE SLOPE OF THE STORM SEWER LINES TO ENSURE ADEQUATE CLEARANCE FOR THE GEOTHERMAL AND VOLTAGE UTILITIES LINES THAT CROSS THE STORM WATER LINES. |
| Nov 27, 2024 | A00003 | $230.5K | (REA-002) CONTAMINATED SOILS: THIS CHANGE IS BASED ON THE REQUEST FOR EQUITABLE ADJUSTMENT (REA) FOR STOCKPILING CONTAMINATED SOIL, HAULING OFF AND IMPORTING NEW SOIL TO REPLACE THE CONTAMINATED QUANTITIES. |
| Nov 20, 2024 | A00002 | $83.7K | (R-001) REMOVAL AND REPLACEMENT OF EXISTING CURB, PEDESTRIAN RAMP ON THE NORTH SIDE, ASPHALT PAVEMENT, STORM SEWER CASTING, AND ADJUSTING RINGS, BAR GRATING AND ASSOCIATE CONCRETE. |