Federal contract award

W912GB23F0261

CONSTRUCTION OF BUILDING 702

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW2SD ENDIST EUROPE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleW912GB23D0030
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.8M
Current contract value$1.8M
Potential contract value / ceiling$1.8M
Start dateSep 22, 2023
Current end dateJul 11, 2025
Potential end dateJul 11, 2025
Latest award activityMar 5, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 5, 2026P00002$0MODIFICATION TO CHANGE THE CONTRACTOR NAME FROM BBGS TO PORR
Nov 6, 2025A00003$0THE MODIFICATION EXTENDS THE POP BY 2 DAYS DUE TO THE IMPLEMENTATION OF FORCE PROTECTION CONDITION CHARLIE DURING THE PERIOD OF 20 AUG 2025 TO 21 AUG 2025 WHICH CAUSED BASE ACCESS DELAYS THAT WERE BEYOND CONTROL AND WITHOUT FAULT OF THE CONTRACTOR.
Apr 2, 2025A00002$0PROVIDE ALL NON-COMPENSABLE TIME IMPACTS TO RESULTING FROM HN DELAYS IN APPROVAL OF THE B702 ASBESTOS ABATEMENT WORK PLAN, WHICH IMPACTED PHASE 1 SITE PREPARATIONS, AND ENDED WITH THE PHASE 2 FINAL AIR SAMPLING ANALYSIS COMPLETED ON 3 MARCH 2025.
Aug 23, 2024A00001$35.3KASBESTOS ABATEMENT & FPCON CHARLIE DELAY CONTRACT FOR BUILDING 702 RENOVATION AT LIVORNO, ITALY. REFERENCE NO. R00001 CR001 ASBESTOS ABATEMENT ROOMS 13 AND 14 CR002 FPCON CHARLIE DELAY
Oct 19, 2023P00001$0SOFA: ISB-23-0188 NTP ITALY
Sep 21, 20230$1.8MCONSTRUCTION OF BUILDING 702

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.