Federal contract award
W912HN24C5006
SAVANNAH HARBOR EXPANSION PROJECT (SHEP) 14A DIKE RAISING AND WEIR IMPROVEMENTS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST SAVANNAH |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z1KF — MAINTENANCE OF DREDGING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $12.7M |
| Current contract value | $12.7M |
| Potential contract value / ceiling | $12.7M |
| Start date | Aug 30, 2024 |
| Current end date | Apr 15, 2026 |
| Potential end date | Apr 15, 2026 |
| Latest award activity | Mar 12, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 12, 2026 | A00005 | $418.7K | THIS MODIFICATION EXTENDS THE TIME OF PERFORMANCE 90 CALENDAR DAYS AND INCREASES THE CONTRACT AMOUNT TO ACCOUNT FOR THE WORK REQUIRED TO REMEDY THE DIFFEREING SITE CONDITIONS ENCOUNTERED AT THE EXISTING WEIR PIPES. |
| Jan 6, 2026 | A00004 | $0 | THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 01 APRIL 2025 THROUGH 30 NOVEMBER 2025. THE FOLLOWING TABLE SUMMARIZES |
| Nov 4, 2025 | A00003 | $3.5K | REPAIRS AND MODIFICATIONS TO WEIRS_____ |
| Apr 8, 2025 | A00002 | $23.4K | REPAIRS AND MODIFICATIONS TO WEIRS_____ |
| Jan 10, 2025 | A00001 | $0 | REPAIRS AND MODIFICATIONS TO WEIRS_____ |
| Oct 7, 2024 | P00001 | $0 | NTP MOD - SAVANNAH HARBOR EXPANSION PROJECT (SHEP) 14A DIKE RAISING AND WEIR IMPROVEMENTS - USACE - SAVANNAH DISTRICT |