Federal contract award
W912HP21C2001
BASE: CONSTRUCTION RECEPTION COMPLEX PHASE I
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST CHARLESTON |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $82.5M |
| Current contract value | $82.5M |
| Potential contract value / ceiling | $82.5M |
| Start date | May 1, 2021 |
| Current end date | May 5, 2025 |
| Potential end date | May 5, 2025 |
| Latest award activity | Jun 3, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 104 of 104 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 3, 2026 | A00031 | $54.6K | R00103 (BCD 00143) REA 0025 RETESTING OSP FIBER OPTIC CABLE |
| May 20, 2026 | A00030 | $38.0K | R00102 (BCD 00139) CIIP ERV 2 DUCTWORK REROUTE |
| May 12, 2026 | A00029 | $29.2K | R00101 (BCD 00135) FIBER SC CONNECTOR/DOOR CHANGE |
| Apr 10, 2026 | A00028 | $68.4K | R00100 (BCD 00132) KNIFE EDGE RELOCATION/PLATFORM FNSH SCH |
| Mar 18, 2026 | A00027 | $25.0K | R00099 (BCD 00136) DFAC ROOM 153 DEPRESSED SLAB CORRECTION |
| Mar 17, 2026 | A00026 | $5.9K | R00097 (BCD 00128) CIIP CABINET AND PLATFORM CHANGES |
| Feb 24, 2026 | A00025 | $17.5K | R00097 (BCD 00128) CIIP CABINET AND PLATFORM CHANGES |
| Feb 12, 2026 | A00024 | $2.7K | R00096 (BCD 00133) CIIP ERV-2 MOTOR UPGRADE REA |
| Feb 6, 2026 | A00023 | $57.3K | R00095 (BCD 00131) CIIP FIRE LANE EXTENSION |
| Jan 27, 2026 | A00022 | $38.0K | R00094 (BCD 00124) TDFAC REPAIRS (APRIL - JULY 2025) |
| Dec 19, 2025 | A00021 | $104.4K | R00093 (BCD 00046) DFAC+CIIP - STORM DRAIN REVISIONS |
| Nov 25, 2025 | A00019 | $83.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 25, 2025 | A00020 | $92.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 14, 2025 | P00072 | $200.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 28, 2025 | A00018 | $-52.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 2, 2025 | P00071 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 30, 2025 | P00070 | $9.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 23, 2025 | A00017 | $1.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 11, 2025 | A00016 | $36.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 4, 2025 | A00015 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 22, 2025 | A00014 | $43.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 21, 2025 | A00013 | $15.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jun 27, 2025 | A00012 | $43.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jun 4, 2025 | A00011 | $63.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 14, 2025 | A00010 | $114.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 9, 2025 | A00009 | $8.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 25, 2025 | A00008 | $39.8K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 16, 2025 | A00007 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Mar 27, 2025 | A00006 | $315.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 20, 2025 | A00005 | $50.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 11, 2025 | A00004 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 6, 2025 | A00003 | $-32.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 31, 2024 | P00069 | $762.8K | MOD FOR TDFAC REA |
| Dec 16, 2024 | A00002 | $107.3K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 11, 2024 | P00068 | $9.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 3, 2024 | P00067 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 2, 2024 | P00066 | $21.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 29, 2024 | P00065 | $-23.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 23, 2024 | P00064 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 16, 2024 | P00063 | $60.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 21, 2024 | P00062 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 7, 2024 | P00061 | $290.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 24, 2024 | P00060 | $151.3K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 10, 2024 | P00059 | $3.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 9, 2024 | P00058 | $42.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jun 28, 2024 | P00057 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jun 18, 2024 | P00056 | $-115.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 22, 2024 | A00001 | $112.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 14, 2024 | P00055 | $4.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 9, 2024 | P00054 | $95.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 30, 2024 | P00052 | $3.3K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 30, 2024 | P00053 | $6.5M | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 23, 2024 | P00051 | $10.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 2, 2024 | P00050 | $45.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Mar 20, 2024 | P00049 | $775.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Mar 14, 2024 | P00048 | $15.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Mar 2, 2024 | P00047 | $-13.3K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 29, 2024 | P00046 | $55.2K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jan 9, 2024 | P00045 | $367.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jan 5, 2024 | P00044 | $5.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 5, 2023 | P00043 | $19.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 8, 2023 | P00042 | $13.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 7, 2023 | P00041 | $10.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 31, 2023 | P00040 | $20.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 12, 2023 | P00039 | $88.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 10, 2023 | P00038 | $1.3M | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 28, 2023 | P00036 | $6.6K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 28, 2023 | P00037 | $1.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 24, 2023 | P00035 | $78.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 21, 2023 | P00034 | $3.8K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 18, 2023 | P00033 | $18.8K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Aug 17, 2023 | P00032 | $349.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 22, 2023 | P00031 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 19, 2023 | P00030 | $8.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 13, 2023 | P00029 | $16.2K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 6, 2023 | P00028 | $173.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Mar 13, 2023 | P00027 | $-1.2K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 13, 2023 | P00026 | $34.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 10, 2023 | P00025 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jan 31, 2023 | P00024 | $1.6K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jan 18, 2023 | P00023 | $20.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 16, 2022 | P00022 | $240.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 8, 2022 | P00021 | $59.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Nov 1, 2022 | P00020 | $18.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Oct 4, 2022 | P00019 | $3.6K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 14, 2022 | P00018 | $100.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 12, 2022 | P00017 | $21.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 9, 2022 | P00015 | $6.4K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Sep 9, 2022 | P00016 | $5.0K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 20, 2022 | P00014 | $9.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 14, 2022 | P00013 | $686.8K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 13, 2022 | P00012 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jul 12, 2022 | P00011 | $3.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Jun 7, 2022 | P00010 | $5.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 6, 2022 | P00009 | $0 | MOD TO INCLUDE DPAS PRIORITY RATING |
| Apr 26, 2022 | P00008 | $32.6K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 12, 2022 | P00007 | $4.1K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 1, 2022 | P00006 | $24.3M | MODIFICATION TO EXERCISE OPTION 1 |
| Mar 22, 2022 | P00005 | $3.7K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Feb 7, 2022 | P00004 | $2.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 13, 2021 | P00003 | $4.5K | BASE: CONSTRUCT CIIP HIGH-BAY |
| Dec 1, 2021 | P00002 | $25.9K | BASE: CONSTRUCT CIIP HIGH-BAY |
| May 12, 2021 | P00001 | $0 | BASE: CONSTRUCT CIIP HIGH-BAY |
| Apr 5, 2021 | 0 | $44.0M | BASE: CONSTRUCTION RECEPTION COMPLEX PHASE I |