Federal contract award
W912HP24F1190
REPLACE TWO (2-EACH) 200-TON CHILLERS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W074 ENDIST CHARLESTON |
| NAICS | 561210 — Facilities Support Services |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | 47QSHA23D0002 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.9M |
| Current contract value | $1.9M |
| Potential contract value / ceiling | $1.9M |
| Start date | Sep 19, 2024 |
| Current end date | Aug 10, 2026 |
| Potential end date | Aug 10, 2026 |
| Latest award activity | Mar 27, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 27, 2026 | P00011 | $346.4K | BLDG. 787 - USACE FINANCE CENTER NAVAL SUPPORT ACTIVITY - MILLINGTON, TNREPLACE TWO (2-EACH) 200-TON CHILLERS PROJECT5722 INTEGRITY DRIVE,MILLINGTON, TN 38054PERFORMANCE WORK STATEMENTUSACE CHARLESTON DISTRICTFOR:BLDG. 787 - ARMY CORPS |
| Feb 25, 2026 | P00010 | $0 | BLDG. 787 - USACE FINANCE CENTER NAVAL SUPPORT ACTIVITY - MILLINGTON, TNREPLACE TWO (2-EACH) 200-TON CHILLERS PROJECT5722 INTEGRITY DRIVE,MILLINGTON, TN 38054PERFORMANCE WORK STATEMENTUSACE CHARLESTON DISTRICTFOR:BLDG. 787 - ARMY CORPS |
| Dec 19, 2025 | P00009 | $0 | BLDG. 787 - USACE FINANCE CENTER NAVAL SUPPORT ACTIVITY - MILLINGTON, TNREPLACE TWO (2-EACH) 200-TON CHILLERS PROJECT5722 INTEGRITY DRIVE,MILLINGTON, TN 38054PERFORMANCE WORK STATEMENTUSACE CHARLESTON DISTRICTFOR:BLDG. 787 - ARMY CORPS |
| Oct 27, 2025 | P00008 | $0 | MODIFICATION TO EXTEND PERIOD OF PERFORMANCE FOR REPLACE TWO (2-EACH) 200-TON CHILLERS |
| Aug 19, 2025 | P00007 | $80.8K | MOD TO FURNISH AND INSTALL 2 MANUALLY OPERATED ISOLATION VALVES ON THE EXISTING CHILLED WATER CROSS-CONNECTION PIPING BETWEEN CONDENSER PUMPS TO ENABLE PROPER INSTALLATION AND THE OPERATIONAL CONTROL OF THE SYSTEM. |
| May 8, 2025 | P00006 | $88.7K | MOD TO ADD ADDITIONAL IN-SCOPE WORK FOR ALSO REPLACING THE CONTROL PANELS FOR THE TWO (2-EACH) 200-TON CHILLERS |
| Apr 16, 2025 | P00005 | $298.5K | MOD TO PROVIDE NEW E2 CONTROLLERS FOR ALL FAN TERMINAL UNITS WITH NEW ETHERNET COMMUNICATIONS CABLE. |
| Mar 6, 2025 | P00004 | $46.8K | MOD TO REPLACE IMMERSION HEATERS, CHEMICAL INJECTION PUMPS, AND BOOSTER CIRCULATION PUMP |
| Dec 5, 2024 | P00003 | $0 | REPLACE TWO (2-EACH) 200-TON CHILLERS |
| Nov 8, 2024 | P00002 | $10.8K | MODIFICATION TO ADD AN ENVIRONMENTAL MANAGER TO THE CONTRACT TO OVERSEE THE PWS ATTACHMENT 4 SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS 2024.09 THAT WAS ADDED TO THE CONTRACT ON 08 OCT 2024. |
| Oct 15, 2024 | P00001 | $0 | REPLACE TWO (2-EACH) 200-TON CHILLERS |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.