Federal contract award

W912HY19C0016

DMPA NO. 10, SHORELINE EROSION PREVENTIO

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW076 ENDIST GALVESTON
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCZ2KF — REPAIR OR ALTERATION OF DREDGING FACILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$13.3M
Current contract value$13.3M
Potential contract value / ceiling$13.3M
Start dateSep 13, 2019
Current end dateSep 9, 2025
Potential end dateSep 9, 2025
Latest award activityOct 22, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Oct 22, 2025P00006$356.9KTHE PURPOSE OF THIS MODIFICATION IS TO RETURN FUNDS BACK TO CONTRACT.
Sep 9, 2025P00005$2.6MTHIS MOD IMPLEMENTS A SETTLEMENT AGREEMENT.
Jan 31, 2024P00004$-846.7KCORPUS CHRISTI CHIP CHANNEL, TEXAS PLACEMENT AREA 10, NUECES COUNTY. R00009 - SC008 FINAL VEQ AND TURFING DEDUCTION
May 26, 2023P00003$91.8KCONTRACTING OFFICER'S FINAL DECISION AND INTEREST
Oct 27, 2021A00004$0IGFOTIGF CTSWGCT DMPA NO. 10, SHORELINE EROSION PREVENTION A00004 - WEATHER TIME EXTENSION JUN 21 - SEP 21
Aug 17, 2021A00003$180.3KIGFOTIGF CTSWGCT CCSC PA-10 CONTAINMENT DIKE RAISE A00003 - RFI #13 AND RFI #14 CHANGES
Jul 23, 2021A00002$0IGFOTIGF CTSWGCT DMPA NO. 10 CONTAINMENT DIKE RAISE A00003 - WEATHER TIME EXTENSION MAY 21
Apr 8, 2021A00001$0CCSC PLACEMENT AREA NO.10 CONTAINMENT DIKE RAISE A00001 - WEATHER TIME EXTENSION
Dec 7, 2020P00002$409.3KDMPA NO. 10, SHORELINE EROSION PREVENTIO
Aug 24, 2020P00001$500.0KDMPA NO. 10, SHORELINE EROSION PREVENTION
Sep 13, 20190$10.0MDMPA NO. 10, SHORELINE EROSION PREVENTIO