Federal contract award

W912J624C0001

PROJECT NO. 150084, KALAELOA READINESS CENTER ADDITION. THE BUILDING WILL BE A TWO-STORY ADDITION LOCATED ON THE WEST/MOUNTAIN SIDE OF EXISTING BUILDING 29. PROJECT SQUARE FOOTAGE IS ESTIMATED AT 34,578 SQFT.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW7M4 USPFO ACTIVITY HI ARNG
NAICS236220 — Commercial and Institutional Building Construction
PSCY1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$28.9M
Current contract value$28.9M
Potential contract value / ceiling$28.9M
Start dateNov 1, 2023
Current end dateOct 26, 2026
Potential end dateOct 26, 2026
Latest award activityJun 1, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 1, 2026P00004$491.9KCONTRACT MODIFICATION P00004
May 28, 2026P00003$109.0KCONTRACT MODIFICATION P00003
Aug 6, 2025P00002$0ADMINISTRATIVE MODIFICATION TO IMPLEMENT EXECUTIVE ORDER 14168.
Oct 8, 2024P00001$0CHANGE PERIOD OF PERFORMANCE DATES BASED ON NOTICE TO PROCEED (NTP) DATE. THIS NTP WITH WORK UNDER CONTRACT NO. W91J6-24-C-0001 WAS RECEIVED ON 07-OCT-2024. COMPLETION DATE BASED ON NTP IS ESTABLISHED AS 01-MAR-2026.
Oct 13, 20230$28.3MPROJECT NO. 150084, KALAELOA READINESS CENTER ADDITION. THE BUILDING WILL BE A TWO-STORY ADDITION LOCATED ON THE WEST/MOUNTAIN SIDE OF EXISTING BUILDING 29. PROJECT SQUARE FOOTAGE IS ESTIMATED AT 34,578 SQFT.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.