Federal contract award

W912P520C0018

BARKLEY POWER PLANT TURBINE GENERATOR REHABILITATION FOR UNITS 1-4.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST NASHVILLE
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCZ2PZ — REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$80.4M
Current contract value$80.4M
Potential contract value / ceiling$84.0M
Start dateSep 29, 2020
Current end dateSep 15, 2027
Potential end dateSep 15, 2027
Latest award activityMay 15, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 40 of 40 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 15, 2026P00017$741.8KW912P5-20-C-0018 P00017: BAR-TG - BH010-2, BH016-2, BH021 AND BH027-2
May 7, 2026A00022$161.3KBAR TG MOD A00021 - CASE BH035, VEQ FOR OPTIONS CLINS ABOVE 115 PERCENT
Feb 27, 2026A00021$263.5KBAR TG MOD A00021 - CASE BH035, VEQ FOR OPTIONS CLINS ABOVE 115 PERCENT
Oct 10, 2025A00020$25.3KA00020 BH038 UNIT 3 TO UNIT 2 OUTAGE RESEQUENCE
Sep 26, 2025P00016$0DESIGN, MANUFACTURE, TEST AND DELIVER
Sep 24, 2025P00015$396.0KDESIGN, MANUFACTURE, TEST AND DELIVER
Sep 22, 2025A00019$-3.5KMODIFICATION A000019 BH002 GENERATOR & STATION PUMP WATER FLOWMETER
Sep 19, 2025A00018$280.3KMODIFICATION A00018 BH036 UNIT 4 LOWER BRACKET REPAIRS
Aug 28, 2025A00017$92.0KA00017 BH041 POWERHOUSE MVMT U4 NCR 9801 259 PART 1
Jul 16, 2025A00016$94.5KCASE A00016 BH022 HEAD COVER BOLTED CONNECTION UNIT 4
Jul 8, 2025P00014$0TGB COVERS CHANGE MOD
May 5, 2025A00015$50.7KCASE BH030 & BH034 A00015 "INC. OPT. CLINS 115% / PARTNERING 2025"
Apr 24, 2025P00013$160.4KEXERCISE OPTIONS 0538 & 0548
Apr 2, 2025A00014$269.8KDESIGN, MANUFACTURE, TEST AND DELIVER
Feb 28, 2025P00012$35.3KEXERCISE OPTION 539 MACHINIST HIRE.
Feb 18, 2025A00013$87.0KMODIFICATION BH018 A00013 "POTENTIAL TRANSFORMER"
Jan 29, 2025A00012$7.2KCASE BH017 MODIFICATION A00012 GUIDE BEARING PUCKS
Dec 11, 2024A00011$20.3KA00011 BH029 TECH SUB ADD WORK 4. INTERMEDIATE SHAFT
Dec 9, 2024A00010$40.0KCASE A00010 BH027 "UNIT 4 DR LINER CONTRACTION PART 1 NTP"
Nov 26, 2024P00011$200.0KDESIGN, MANUFACTURE, TEST AND DELIVER
Nov 25, 2024A00009$64.6KMODIFICATION A00009 TECHNICAL SUBMITTAL ADDITIONAL WORK 3
Nov 20, 2024A00008$247.5KMOD A00008 CASE BH025
Nov 15, 2024A00007$100.0KCASE BH-019-1 TECHNICAL SUBMITTAL ADDITIONAL WORK 1 MOD A00007
Nov 13, 2024A00006$140.0KDESIGN, MANUFACTURE, TEST AND DELIVER
Oct 7, 2024P00010$343.3KEXERCISE OPTIONAL CLINS 0192, 0302, 0408
Sep 20, 2024P00009$0ADDING PAYMENT PROCEDURES FOR OFF-SITE MATERIALS.
Jul 23, 2024P00008$86.8KOPTIONS 0196, 0210 AND 0215
May 3, 2024A00005$11.5KCASE BH012 MODIFICATION A00005 "PARTNERING MEETINGS 1 & 2"
Apr 17, 2024A00004$325.4KDESIGN, MANUFACTURE, TEST AND DELIVER
Apr 11, 2024P00007$108.5KBARKLEY POWER PLANT TURBINE GENERATOR REHAB: OPTIONS 0545, 0547, & 0556.
Feb 22, 2024P00006$187.4KBARKLEY TURBINE GENERATOR REHAB - EXERCISE OPTIONS
Feb 16, 2024A00003$300.1KCASE BH003 MODIFICATION A00003 DC PUMP, DRAFT TUBE, CAPILLITARY/ADDITION
Sep 8, 2023A00002$43.0KCASE BH010-1 MODIFICATION A00002 "UNIT 4 HEADCOVER SEAM WELD PART 1 NTP"
Jul 28, 2023A00001$95.0KCASE BH-004 MODIFICATION A00001 "PMG REBUILD"
Jun 30, 2023P00005$67.0KDESIGN, MANUFACTURE, TEST AND DELIVER
Mar 9, 2023P00004$162.8KDESIGN, MANUFACTURE, TEST AND DELIVER
Mar 3, 2023P00003$308.3KMODIFICATION TO EXERCISE OPTION 0206 WICKET GATE END FACES (UNIT 4)
Mar 30, 2022P00002$36.8KEXERCISE OPTION 0541, WELDING SERVICES
Feb 4, 2021P00001$0MODIFICATION IS TO ESTABLISH THE CONTRACT COMPLETION DATES WHICH ARE BASED UPON THE CONTRACTOR ACKNOWLEDGING THE NOTICE TO PROCEED ON 28 OCTOBER 2020 IN ACCORDANCE WITH FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK.
Sep 29, 20200$74.8MBARKLEY POWER PLANT TURBINE GENERATOR REHABILITATION FOR UNITS 1-4.

Estimated positioning window

Oct 25, 2026 – Mar 15, 2027

Recompete signal:
75/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 75/100. Available recorded signals: 70 points.

Contract end 2027-09-15 (325 days from calculation)
+35 points
2 historical awards in this buyer and category group
+10 points
40 recorded award transactions
+10 points
Latest award action: 2026-05-15
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.