Federal contract award
W912P521C0015
CONSTRUCTION OF DOWNSTREAM MONOLITHS FOR THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W072 ENDIST NASHVILLE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1KA — CONSTRUCTION OF DAMS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $408.1M |
| Current contract value | $408.1M |
| Potential contract value / ceiling | $408.1M |
| Start date | Oct 11, 2021 |
| Current end date | Aug 24, 2027 |
| Potential end date | Aug 24, 2027 |
| Latest award activity | May 19, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 73 of 73 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 11, 2026 | A00053 | $148.0K | SCOPE OF WORK A00053 WKR049-2 M10 WATERTIGHT DOOR AND UTILITY EMBEDS (FINAL): THIS MODIFICATION IS FOR PROCURING AND INSTALLING A WATERTIGHT DOOR, PIPE SLEEVES, AND A THRU-WALL BARRIER MOUNTING FRAME AT MONOLITH M10. |
| May 19, 2026 | A00052 | $440.0K | SCOPE OF WORK A00052 WKR079 PHASE 3 ROCK STABILIZATION: THIS MODIFICATION IS FOR STABILIZING THE PHASE 3 ROCK NEAR MONOLITH M32 BY REMOVAL OF UNSTABLE MATERIAL, WATER MITIGATION, REBAR DOWELS, FORMWORK, AND CONCRETE OVERPOUR. |
| May 12, 2026 | P00019 | $20.0K | SCOPE OF WORK WKR072-2 BRIDGE PIER AND M17 GALLERY CHANGES (PART I-SUPPLEMENT): RESIZE/SHIFT TWO BRIDGE PIER COLUMNS, ADD ELECTRICAL BLOCK OUT, REBAR QUANTITIES, REBAR INSTALLATION, CONCRETE, CEMENT, FLY ASH, ADD FLOOR HATCH, DRAINPIPE, DRAIN COVERS. |
| Apr 23, 2026 | P00018 | $140.0K | SCOPE OF WORK WKR100-1 M31 WEDGE TREATMENT (PART I-NTP): THE CONTRACTOR SHALL TIE INTO MONOLITH M31C FROM THE BULL NOSE OF M31 AND ALTERS THE STICK-BUILT WALL ARMOR THAT IS NO LONGER REQUIRED TO TIE INTO THE SEGMENTAL COFFERDAM. |
| Apr 15, 2026 | P00017 | $0 | SCOPE OF WORK WKR100-1 M31 WEDGE TREATMENT (PART I-NTP): THE CONTRACTOR SHALL TIE INTO MONOLITH M31C FROM THE BULL NOSE OF M31 AND ALTERS THE STICK-BUILT WALL ARMOR THAT IS NO LONGER REQUIRED TO TIE INTO THE SEGMENTAL COFFERDAM. |
| Apr 1, 2026 | A00051 | $0 | SCOPE OF WORK WKR098 WEATHER TIME EXTENSION JUL 2025-JAN 2026. THIS MODIFICATION EXTENDS TIME FOR DELAYS CAUSED BY ADVERSE WEATHER DURING THE PERIOD 01 JULY 2025 THROUGH 31 JANUARY 2026. |
| Feb 23, 2026 | P00016 | $20.0K | SCOPE OF WORK BRIDGE PIER M17 GALLERY CHANGES WKR072THIS MODIFICATION CHANGES QUANTITIES OF REBAR, REBAR INSTALLATION, CONCRETE, CEMENT, AND FLY ASH, PLUS ADDS A FLOOR HATCH AND LADDER LEADING INTO THE GALLERY. |
| Feb 9, 2026 | A00050 | $23.3K | SCOPE OF WORK WKR062 M17, M19, M20 DRAIN: THIS MODIFICATION INCREASES THE DRAIN SIZE TO MITIGATE WATER DRAINAGE POOLING BETWEEN THE NEW LOCK AND EXISTING LOCK. |
| Jan 8, 2026 | P00015 | $50.0K | SCOPE OF WORK WKR096-1 U1 WALL ARMOR-CAISSON CONFLICT (PT. I NTP): THIS MODIFICATION ADDS A PERMANENT PINTLE GREASE LINE AND PROVIDES SPECIFICATIONS FOR TOLERANCES, INSTALLATION REQUIREMENTS, FIELD TESTS, AND INSPECTIONS. |
| Dec 22, 2025 | A00049 | $75.0K | SCOPE OF WORK WKR096-1 U1 WALL ARMOR-CAISSON CONFLICT (PT. I NTP) |
| Nov 24, 2025 | A00048 | $82.1K | CASES WKR048, -081, -084, -085, -091, -092, -094 MODIFICATION A00048 "L14 WALL & U2M/U2L FMB ELEV., HOSE CABINET RELOCATION, EPOXY GROUT CREDIT, CULVERT BULKHEAD GRATING SUPPORT, M31 JT REDUCTION, KEYWAY FORMWORK REDESIGN, LIFT STATION CLEANOUT" |
| Nov 13, 2025 | P00014 | $1.3M | CASE WKR088 MODIFICATION P00014 "QV-EXCAVATION AND DENTAL" |
| Oct 21, 2025 | P00013 | $3.0M | CASE WKR017 MODIFICATION P00013 "BULKHEAD RECESS METALS & GALLERY GUTTER" |
| Sep 30, 2025 | A00047 | $126.6K | CASE WKR077, WKR090 MODIFICATION A00047 "U1 ANCHOR CHANGE & US 2ND STAGE JOINT PREP" |
| Sep 10, 2025 | A00046 | $-67.0K | CASE WKR073, WKR080, WKR086 MODIFICATION A00046 "ACTIVE WELD, WALL ARMOR, CSG CHANGE" |
| Sep 3, 2025 | A00045 | $195.5K | CASE WKR058 MODIFICATION A00045 "CONTROL STAND GALLERY EXTENSIONS" |
| Aug 26, 2025 | A00044 | $60.0K | CASE WKR049-1 MODIFICATION A00044 "M10 WATERTIGHT DOOR & UTILITY EMBEDS" |
| Aug 22, 2025 | A00043 | $47.6K | CASE WKRO78-1 MODIFICATION A00043 C31-C32 OUTLET WORKS GEOMETRY (PART 1-NTP) |
| Jul 30, 2025 | A00042 | $0 | CASE WKRO87 MODIFICATION A00042 "WEATHER TIME EXTENSION MAY 25-JUN 25" |
| Jul 24, 2025 | A00041 | $-226.0K | WKR074 A00041 "HIGH MAST LIGHTS DESCOPE" |
| Jul 10, 2025 | A00040 | $17.0K | CASE WKR075 MODIFICATION A00040 "U1M CAISSON CHANGES" |
| Jun 2, 2025 | A00039 | $0 | CASE WKR076 MODIFICATION A00039 "WEATHER TIME EXTENSION JAN 25-APR 25" |
| May 19, 2025 | A00038 | $6.0K | CASE WKR063 MODIFICATION A00038 DRILLED SHAFT M21-P5 STEEL OBSTRUCTION |
| Apr 23, 2025 | A00037 | $13.9K | CASE WKRO61 MODIFICATION A00037 PARTNERING COSTS 2025 |
| Apr 17, 2025 | A00036 | $59.2K | CASE WKRO45 MODIFICATION A00036 FMB AIRLINES |
| Apr 10, 2025 | A00035 | $78.0K | CASE WKRO57 WATERSTOP CHANGES, CASE WKR053 BACKFILL PHASE 1, MODIFICATION A00035 |
| Mar 20, 2025 | A00034 | $150.9K | CASE WKR060 AND WKR070 MODIFICATION "MISC. MECHANICAL REPAIRS & ADDT'L JANITORIAL SERVICES" |
| Mar 5, 2025 | A00033 | $235.5K | CASE WKR065 MODIFICATION A00033 CAISSON EMBEDS & U1R METALS |
| Feb 19, 2025 | A00032 | $0 | CASE WKR067 MODIFICATION A00032 WEATHER TIME EXTENSION OCT 2024-DEC 2024 |
| Feb 4, 2025 | P00012 | $701.4K | CASE WKR040 MODIFICATION P00012 M22-M25 & M30-M31 RECONFIGURATION |
| Jan 7, 2025 | A00031 | $390.7K | WKR041 A00031 L29 & M29 MACHINERY ROOM CHANGES |
| Dec 23, 2024 | P00011 | $1.3M | WKRO39 MODIFICATION P00011 GATE SPRAY INTAKE & TRASH RACKS INSTALL |
| Dec 2, 2024 | P00010 | $2.3M | CASE WKR018 MODIFICATION P00010 M31 JOINT TREATMENT |
| Nov 21, 2024 | A00030 | $114.3K | CASES WKR044, WKR047, WKR066 MODIFICATION A00030 CONTACT BLOCK, L32 BEAM SEAT REMOVAL, M19-P7 REMEDIATION |
| Nov 13, 2024 | P00009 | $4.2M | CASE WKR019 MODIFICATION P00009 MISCELLANEOUS METALS |
| Oct 21, 2024 | A00029 | $0 | CASE WKR064 MODIFICTAION A00029 WEATHER TIME EXTENSION JULY 2024-SEPTEMBER 2024 |
| Oct 10, 2024 | A00028 | $75.2K | CASE WKR024 MODIFICATION A00028 DRILLED SHAFTS REDESIGN |
| Sep 18, 2024 | A00027 | $79.0K | CASE WKR055 MODIFICATION A00027 SFTP DATA TRANSITION |
| Aug 20, 2024 | A00026 | $32.2K | CASE WKR056 MODIFICATION A00026 RISK MANAGEMENT PARTNERING COSTS 2024 |
| Aug 15, 2024 | A00025 | $0 | CASE WKR059 MODIFICATION A00025 WEATHER TIME EXTENSION APRIL-JUNE 2024 |
| Aug 12, 2024 | A00024 | $11.9K | CASE WKR052 MODIFICATION A00024 "STAFF GAGES & L28/M28 PROTECTION" |
| Jul 3, 2024 | A00023 | $29.7K | CASE WKR051 MODIFICATION A00023 "CAISSON RECESS FILLER HANGER BEVELING" |
| Jun 17, 2024 | P00008 | $988.0K | CASE WKR054 MODIFICATION P00008 "QV-6-IN DRILLED SHAFTS" |
| May 1, 2024 | A00022 | $0 | CASE WKR050 MODIFICATION A00022 "WEATHER TIME EXTENSION JAN 2024-MAR 2024" |
| Apr 12, 2024 | A00021 | $408.9K | CASE WKR043 MODIFICATION A00021 "DRILLED SHAFT BEAM STIFFENERS" |
| Mar 25, 2024 | A00020 | $421.4K | CASE WKR046 MODIFICATION A00020 "MISCELLANEOUS METALS MATERIALS" |
| Feb 13, 2024 | A00019 | $13.7K | CASE WKR037 MODIFICATION A00019 "PARTNERING COSTS 2024" |
| Feb 8, 2024 | A00018 | $0 | CASE WKR042 MODIFICATION A00018 "WEATHER TIME EXTENSION NOV 2021-DEC 2023" |
| Jan 25, 2024 | A00017 | $350.0K | CASE WKR031 MODIFICATION A00017 "FMB BLOCKOUT REINFORCEMENT INSTALLATION" |
| Jan 11, 2024 | A00016 | $16.2K | CASE WKR035 MODIFICATION A00016 EXISTING SEWER LINE INSULATION REPAIRS |
| Dec 20, 2023 | A00015 | $106.0K | GATE SPRAY MATERIAL |
| Dec 4, 2023 | A00014 | $158.2K | CASE WKR022, WKR023 MODIFICATION A00014 "LIFT STATION, FLOW METERS, PARTNERING" |
| Nov 6, 2023 | A00013 | $-46.3K | CASE WKR032, WKR033, WKR036 MODIFICATION A00013 "PIEZOMETER, TILTMETER, WALL ARMOR REPAIR" |
| Jul 31, 2023 | A00012 | $157.5K | CASE WKR029 MODIFICATION A00012 "FMB BLOCKOUT REINFORCEMENT MATERIAL" |
| Jun 29, 2023 | P00007 | $4.2M | CASE WKR027 MODIFICATION P00007 "QUANTITY VARIATION-MUD MAT CONCRETE" |
| Jun 12, 2023 | P00006 | $3.2M | MODIFICATION P00006 CASE WKR028 "QV-EXCAVATION AND LINE DRILLING" |
| May 26, 2023 | P00005 | $932.6K | CASE WKRO15 MODIFICATION P00005 "FMB EMBEDDED METALS" |
| May 19, 2023 | A00011 | $169.8K | CASE WKR023 MODIFICATION A00011 "RELOCATE MITER GATE MANHOLES" |
| Apr 24, 2023 | A00010 | $15.6K | CASE WKR021 MODIFICATION A00010 "INSTRUMENTATION SENSORS, GATE FOBS, AND ATS REPAIR" |
| Apr 20, 2023 | A00009 | $98.4K | CASES WKR016 AND WKR020 MODIFICATION A00009 "BIL SIGNAGE, TYPE 1L CEMENT TESTING, JIB CRANE REPAIRS, AND AERIAL PHOTOS" |
| Dec 28, 2022 | A00008 | $10.0K | CASE WKR017 MODIFICATION A00008 PARTNERING COSTS 2023 |
| Nov 30, 2022 | A00007 | $433.1K | CASE WKR010 MODIFICATION A00007 DATA MANAGEMENT VISUALIZATION |
| Nov 16, 2022 | P00004 | $-1.3M | CASE WKR011 MODIFICATION P00004 CULVERT LINER ANGLE DELETION |
| Nov 7, 2022 | A00006 | $169.6K | CASE WKR013 MODIFICATION A00006 COFFERDAM CELL 1 BANDING ADDITION |
| Oct 6, 2022 | A00005 | $82.2K | CASE WKR012 MODIFICATION A00005 "ADDITIONAL GOVERNMENT UTV'S |
| Aug 23, 2022 | A00004 | $95.4K | CASE WKRO05, WKR0008 MODIFICATION A00004 "BONDS CREDIT AND QA LAB CHANGES" |
| Apr 27, 2022 | A00003 | $92.1K | CASE WKR006 MOD A00003 QUANTITY VARIATION-DRILLING |
| Apr 13, 2022 | A00002 | $0 | CASE WKRO04 & WKR007 MOD A00002 DRILLING DATABASE AND DRAWING CHANGES |
| Mar 30, 2022 | P00002 | $0 | CASE WKR003 MODIFICATION P00002 "OFF-SITE STORED MATERIALS" |
| Mar 30, 2022 | P00003 | $213.0M | EXERCISE REMAINING OPTIONS FOR THE KENTUCKY LOCK DOWNSTREAM MONOLITH PROJECT, GRAND RIVERS, KY. |
| Mar 16, 2022 | A00001 | $10.9K | BASE: CLIN 0004, DIV 01 |
| Dec 1, 2021 | P00001 | $0 | ISSUE THE NOTICE TO PROCEED (NTP) / ADD CLINS TO CONTRACT BASED ON AWARD FOR THE CONSTRUCTION OF THE DOWNSTREAM MONOLITHS AT THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY |
| Sep 30, 2021 | 0 | $166.8M | CONSTRUCTION OF DOWNSTREAM MONOLITHS FOR THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY |
Estimated positioning window
Oct 25, 2026 – Feb 24, 2027
75/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 75/100. Available recorded signals: 70 points.
- Contract end 2027-08-24 (303 days from calculation)
- +35 points
- 2 historical awards in this buyer and category group
- +10 points
- 73 recorded award transactions
- +10 points
- Latest award action: 2026-05-19
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.