Federal contract award

W912P521C0015

CONSTRUCTION OF DOWNSTREAM MONOLITHS FOR THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST NASHVILLE
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1KA — CONSTRUCTION OF DAMS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$408.1M
Current contract value$408.1M
Potential contract value / ceiling$408.1M
Start dateOct 11, 2021
Current end dateAug 24, 2027
Potential end dateAug 24, 2027
Latest award activityMay 19, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 73 of 73 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 11, 2026A00053$148.0KSCOPE OF WORK A00053 WKR049-2 M10 WATERTIGHT DOOR AND UTILITY EMBEDS (FINAL): THIS MODIFICATION IS FOR PROCURING AND INSTALLING A WATERTIGHT DOOR, PIPE SLEEVES, AND A THRU-WALL BARRIER MOUNTING FRAME AT MONOLITH M10.
May 19, 2026A00052$440.0KSCOPE OF WORK A00052 WKR079 PHASE 3 ROCK STABILIZATION: THIS MODIFICATION IS FOR STABILIZING THE PHASE 3 ROCK NEAR MONOLITH M32 BY REMOVAL OF UNSTABLE MATERIAL, WATER MITIGATION, REBAR DOWELS, FORMWORK, AND CONCRETE OVERPOUR.
May 12, 2026P00019$20.0KSCOPE OF WORK WKR072-2 BRIDGE PIER AND M17 GALLERY CHANGES (PART I-SUPPLEMENT): RESIZE/SHIFT TWO BRIDGE PIER COLUMNS, ADD ELECTRICAL BLOCK OUT, REBAR QUANTITIES, REBAR INSTALLATION, CONCRETE, CEMENT, FLY ASH, ADD FLOOR HATCH, DRAINPIPE, DRAIN COVERS.
Apr 23, 2026P00018$140.0KSCOPE OF WORK WKR100-1 M31 WEDGE TREATMENT (PART I-NTP): THE CONTRACTOR SHALL TIE INTO MONOLITH M31C FROM THE BULL NOSE OF M31 AND ALTERS THE STICK-BUILT WALL ARMOR THAT IS NO LONGER REQUIRED TO TIE INTO THE SEGMENTAL COFFERDAM.
Apr 15, 2026P00017$0SCOPE OF WORK WKR100-1 M31 WEDGE TREATMENT (PART I-NTP): THE CONTRACTOR SHALL TIE INTO MONOLITH M31C FROM THE BULL NOSE OF M31 AND ALTERS THE STICK-BUILT WALL ARMOR THAT IS NO LONGER REQUIRED TO TIE INTO THE SEGMENTAL COFFERDAM.
Apr 1, 2026A00051$0SCOPE OF WORK WKR098 WEATHER TIME EXTENSION JUL 2025-JAN 2026. THIS MODIFICATION EXTENDS TIME FOR DELAYS CAUSED BY ADVERSE WEATHER DURING THE PERIOD 01 JULY 2025 THROUGH 31 JANUARY 2026.
Feb 23, 2026P00016$20.0KSCOPE OF WORK BRIDGE PIER M17 GALLERY CHANGES WKR072THIS MODIFICATION CHANGES QUANTITIES OF REBAR, REBAR INSTALLATION, CONCRETE, CEMENT, AND FLY ASH, PLUS ADDS A FLOOR HATCH AND LADDER LEADING INTO THE GALLERY.
Feb 9, 2026A00050$23.3KSCOPE OF WORK WKR062 M17, M19, M20 DRAIN: THIS MODIFICATION INCREASES THE DRAIN SIZE TO MITIGATE WATER DRAINAGE POOLING BETWEEN THE NEW LOCK AND EXISTING LOCK.
Jan 8, 2026P00015$50.0KSCOPE OF WORK WKR096-1 U1 WALL ARMOR-CAISSON CONFLICT (PT. I NTP): THIS MODIFICATION ADDS A PERMANENT PINTLE GREASE LINE AND PROVIDES SPECIFICATIONS FOR TOLERANCES, INSTALLATION REQUIREMENTS, FIELD TESTS, AND INSPECTIONS.
Dec 22, 2025A00049$75.0KSCOPE OF WORK WKR096-1 U1 WALL ARMOR-CAISSON CONFLICT (PT. I NTP)
Nov 24, 2025A00048$82.1KCASES WKR048, -081, -084, -085, -091, -092, -094 MODIFICATION A00048 "L14 WALL & U2M/U2L FMB ELEV., HOSE CABINET RELOCATION, EPOXY GROUT CREDIT, CULVERT BULKHEAD GRATING SUPPORT, M31 JT REDUCTION, KEYWAY FORMWORK REDESIGN, LIFT STATION CLEANOUT"
Nov 13, 2025P00014$1.3MCASE WKR088 MODIFICATION P00014 "QV-EXCAVATION AND DENTAL"
Oct 21, 2025P00013$3.0MCASE WKR017 MODIFICATION P00013 "BULKHEAD RECESS METALS & GALLERY GUTTER"
Sep 30, 2025A00047$126.6KCASE WKR077, WKR090 MODIFICATION A00047 "U1 ANCHOR CHANGE & US 2ND STAGE JOINT PREP"
Sep 10, 2025A00046$-67.0KCASE WKR073, WKR080, WKR086 MODIFICATION A00046 "ACTIVE WELD, WALL ARMOR, CSG CHANGE"
Sep 3, 2025A00045$195.5KCASE WKR058 MODIFICATION A00045 "CONTROL STAND GALLERY EXTENSIONS"
Aug 26, 2025A00044$60.0KCASE WKR049-1 MODIFICATION A00044 "M10 WATERTIGHT DOOR & UTILITY EMBEDS"
Aug 22, 2025A00043$47.6KCASE WKRO78-1 MODIFICATION A00043 C31-C32 OUTLET WORKS GEOMETRY (PART 1-NTP)
Jul 30, 2025A00042$0CASE WKRO87 MODIFICATION A00042 "WEATHER TIME EXTENSION MAY 25-JUN 25"
Jul 24, 2025A00041$-226.0KWKR074 A00041 "HIGH MAST LIGHTS DESCOPE"
Jul 10, 2025A00040$17.0KCASE WKR075 MODIFICATION A00040 "U1M CAISSON CHANGES"
Jun 2, 2025A00039$0CASE WKR076 MODIFICATION A00039 "WEATHER TIME EXTENSION JAN 25-APR 25"
May 19, 2025A00038$6.0KCASE WKR063 MODIFICATION A00038 DRILLED SHAFT M21-P5 STEEL OBSTRUCTION
Apr 23, 2025A00037$13.9KCASE WKRO61 MODIFICATION A00037 PARTNERING COSTS 2025
Apr 17, 2025A00036$59.2KCASE WKRO45 MODIFICATION A00036 FMB AIRLINES
Apr 10, 2025A00035$78.0KCASE WKRO57 WATERSTOP CHANGES, CASE WKR053 BACKFILL PHASE 1, MODIFICATION A00035
Mar 20, 2025A00034$150.9KCASE WKR060 AND WKR070 MODIFICATION "MISC. MECHANICAL REPAIRS & ADDT'L JANITORIAL SERVICES"
Mar 5, 2025A00033$235.5KCASE WKR065 MODIFICATION A00033 CAISSON EMBEDS & U1R METALS
Feb 19, 2025A00032$0CASE WKR067 MODIFICATION A00032 WEATHER TIME EXTENSION OCT 2024-DEC 2024
Feb 4, 2025P00012$701.4KCASE WKR040 MODIFICATION P00012 M22-M25 & M30-M31 RECONFIGURATION
Jan 7, 2025A00031$390.7KWKR041 A00031 L29 & M29 MACHINERY ROOM CHANGES
Dec 23, 2024P00011$1.3MWKRO39 MODIFICATION P00011 GATE SPRAY INTAKE & TRASH RACKS INSTALL
Dec 2, 2024P00010$2.3MCASE WKR018 MODIFICATION P00010 M31 JOINT TREATMENT
Nov 21, 2024A00030$114.3KCASES WKR044, WKR047, WKR066 MODIFICATION A00030 CONTACT BLOCK, L32 BEAM SEAT REMOVAL, M19-P7 REMEDIATION
Nov 13, 2024P00009$4.2MCASE WKR019 MODIFICATION P00009 MISCELLANEOUS METALS
Oct 21, 2024A00029$0CASE WKR064 MODIFICTAION A00029 WEATHER TIME EXTENSION JULY 2024-SEPTEMBER 2024
Oct 10, 2024A00028$75.2KCASE WKR024 MODIFICATION A00028 DRILLED SHAFTS REDESIGN
Sep 18, 2024A00027$79.0KCASE WKR055 MODIFICATION A00027 SFTP DATA TRANSITION
Aug 20, 2024A00026$32.2KCASE WKR056 MODIFICATION A00026 RISK MANAGEMENT PARTNERING COSTS 2024
Aug 15, 2024A00025$0CASE WKR059 MODIFICATION A00025 WEATHER TIME EXTENSION APRIL-JUNE 2024
Aug 12, 2024A00024$11.9KCASE WKR052 MODIFICATION A00024 "STAFF GAGES & L28/M28 PROTECTION"
Jul 3, 2024A00023$29.7KCASE WKR051 MODIFICATION A00023 "CAISSON RECESS FILLER HANGER BEVELING"
Jun 17, 2024P00008$988.0KCASE WKR054 MODIFICATION P00008 "QV-6-IN DRILLED SHAFTS"
May 1, 2024A00022$0CASE WKR050 MODIFICATION A00022 "WEATHER TIME EXTENSION JAN 2024-MAR 2024"
Apr 12, 2024A00021$408.9KCASE WKR043 MODIFICATION A00021 "DRILLED SHAFT BEAM STIFFENERS"
Mar 25, 2024A00020$421.4KCASE WKR046 MODIFICATION A00020 "MISCELLANEOUS METALS MATERIALS"
Feb 13, 2024A00019$13.7KCASE WKR037 MODIFICATION A00019 "PARTNERING COSTS 2024"
Feb 8, 2024A00018$0CASE WKR042 MODIFICATION A00018 "WEATHER TIME EXTENSION NOV 2021-DEC 2023"
Jan 25, 2024A00017$350.0KCASE WKR031 MODIFICATION A00017 "FMB BLOCKOUT REINFORCEMENT INSTALLATION"
Jan 11, 2024A00016$16.2KCASE WKR035 MODIFICATION A00016 EXISTING SEWER LINE INSULATION REPAIRS
Dec 20, 2023A00015$106.0KGATE SPRAY MATERIAL
Dec 4, 2023A00014$158.2KCASE WKR022, WKR023 MODIFICATION A00014 "LIFT STATION, FLOW METERS, PARTNERING"
Nov 6, 2023A00013$-46.3KCASE WKR032, WKR033, WKR036 MODIFICATION A00013 "PIEZOMETER, TILTMETER, WALL ARMOR REPAIR"
Jul 31, 2023A00012$157.5KCASE WKR029 MODIFICATION A00012 "FMB BLOCKOUT REINFORCEMENT MATERIAL"
Jun 29, 2023P00007$4.2MCASE WKR027 MODIFICATION P00007 "QUANTITY VARIATION-MUD MAT CONCRETE"
Jun 12, 2023P00006$3.2MMODIFICATION P00006 CASE WKR028 "QV-EXCAVATION AND LINE DRILLING"
May 26, 2023P00005$932.6KCASE WKRO15 MODIFICATION P00005 "FMB EMBEDDED METALS"
May 19, 2023A00011$169.8KCASE WKR023 MODIFICATION A00011 "RELOCATE MITER GATE MANHOLES"
Apr 24, 2023A00010$15.6KCASE WKR021 MODIFICATION A00010 "INSTRUMENTATION SENSORS, GATE FOBS, AND ATS REPAIR"
Apr 20, 2023A00009$98.4KCASES WKR016 AND WKR020 MODIFICATION A00009 "BIL SIGNAGE, TYPE 1L CEMENT TESTING, JIB CRANE REPAIRS, AND AERIAL PHOTOS"
Dec 28, 2022A00008$10.0KCASE WKR017 MODIFICATION A00008 PARTNERING COSTS 2023
Nov 30, 2022A00007$433.1KCASE WKR010 MODIFICATION A00007 DATA MANAGEMENT VISUALIZATION
Nov 16, 2022P00004$-1.3MCASE WKR011 MODIFICATION P00004 CULVERT LINER ANGLE DELETION
Nov 7, 2022A00006$169.6KCASE WKR013 MODIFICATION A00006 COFFERDAM CELL 1 BANDING ADDITION
Oct 6, 2022A00005$82.2KCASE WKR012 MODIFICATION A00005 "ADDITIONAL GOVERNMENT UTV'S
Aug 23, 2022A00004$95.4KCASE WKRO05, WKR0008 MODIFICATION A00004 "BONDS CREDIT AND QA LAB CHANGES"
Apr 27, 2022A00003$92.1KCASE WKR006 MOD A00003 QUANTITY VARIATION-DRILLING
Apr 13, 2022A00002$0CASE WKRO04 & WKR007 MOD A00002 DRILLING DATABASE AND DRAWING CHANGES
Mar 30, 2022P00002$0CASE WKR003 MODIFICATION P00002 "OFF-SITE STORED MATERIALS"
Mar 30, 2022P00003$213.0MEXERCISE REMAINING OPTIONS FOR THE KENTUCKY LOCK DOWNSTREAM MONOLITH PROJECT, GRAND RIVERS, KY.
Mar 16, 2022A00001$10.9KBASE: CLIN 0004, DIV 01
Dec 1, 2021P00001$0ISSUE THE NOTICE TO PROCEED (NTP) / ADD CLINS TO CONTRACT BASED ON AWARD FOR THE CONSTRUCTION OF THE DOWNSTREAM MONOLITHS AT THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY
Sep 30, 20210$166.8MCONSTRUCTION OF DOWNSTREAM MONOLITHS FOR THE KENTUCKY LOCK, GRAND RIVERS, KENTUCKY

Estimated positioning window

Oct 25, 2026 – Feb 24, 2027

Recompete signal:
75/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 75/100. Available recorded signals: 70 points.

Contract end 2027-08-24 (303 days from calculation)
+35 points
2 historical awards in this buyer and category group
+10 points
73 recorded award transactions
+10 points
Latest award action: 2026-05-19
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.