Federal contract award
W912P523C0002
REHABILITATION OF OLD HICKORY TURBINE GENERATORS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W072 ENDIST NASHVILLE |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z2PZ — REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $92.6M |
| Current contract value | $92.6M |
| Potential contract value / ceiling | $109.6M |
| Start date | Feb 2, 2023 |
| Current end date | Oct 5, 2030 |
| Potential end date | Oct 5, 2030 |
| Latest award activity | Jun 10, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 32 of 32 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 10, 2026 | P00025 | $550.0K | MODIFICATION P00025: OLD-TG-OH018 - UNITS 1 TO 4 DATA RECORDERS REPLACEMENT |
| May 21, 2026 | PZ0024 | $1.8M | MODIFICATION P00024: OLD -TG PROVIDE ALL NECESSARY EQUIPMENT, DESIGNS, ENGINEERING AND LABOR TO CONVERT THE EXISTING MECHANICAL GOVERNORS AT OLD HICKORY POWER PLANT TO NEW DIGITAL PROGRAMMABLE LOGIC CONTROLLERS CONTROLLED GOVERNORS FOR UNITS 1-4. |
| May 7, 2026 | P00023 | $88.3K | MODIFICATION P00023: OLD-TG-OH035 EXTENDED WARRANTY AND OH064 BRAKE JACK ASSEMBLY |
| May 1, 2026 | P00022 | $711.6K | OLD-TG - OH024 OIL PURIFICATION SYSTEM |
| Apr 9, 2026 | P00021 | $143.4K | OLD TG - EXERCISE OPTION CLIN 2222 TO SHIFT THE STATOR FRAME, EXERCISE OPTION CLIN 2228 FOR WELD ROTOR POLE LAMINATIONS, QUANTITIES FOR CLINS 5001, 5003, 5005, AND 5011 ARE INCREASED TO 115% AT THEIR CONTRACT UNIT PRICES. |
| Mar 31, 2026 | P00020 | $153.5K | OLD TG - EXERCISE OPTIONS 1207, 2207, 3207 AND 2211 |
| Mar 2, 2026 | P00019 | $718.8K | OLD-TG - REIMBURSEMENT OF INCURRED REA TARIFFS MODIFICATION |
| Feb 19, 2026 | P00018 | $779.5K | EXERCISE OPTIONS 5000, 5002, 5003, 5004, 5005, 5006, 5007, 5008, AND 5009. |
| Feb 5, 2026 | P00017 | $2.5M | PART 1 MODIFICATION FOR DIGITAL GOVERNORS |
| Jan 9, 2026 | P00016 | $389.5K | PART 2 MODIFICATION FOR DSC TURBINE SHAFT |
| Dec 4, 2025 | P00015 | $102.3K | P00015 OH-050 DSC TURBINE SHAFT, PART 1 NTE |
| Dec 1, 2025 | A00006 | $37.3K | A00006 OH-045 U3 ROTOR POLE ABATEMENT |
| Sep 12, 2025 | P00014 | $250.0K | EXERCISE OPTION CLIN 5013 |
| Sep 9, 2025 | A00005 | $129.0K | A00005 OH030 UNITS 1-3 ANNUNCIATOR PANEL ADDITION |
| Sep 3, 2025 | P00013 | $32.2K | EXERCISE OPTION CLIN 2225 |
| Jun 27, 2025 | P00012 | $46.4K | EXERCISE OPTION CLIN 3214 |
| Jun 2, 2025 | A00004 | $156.9K | MODIFICATION A00004 OH26 & OH027 "UNITS RESEQUENCE & PARTERNING MEETING 2025" |
| May 7, 2025 | P00011 | $0 | ADMINISTRATION MODIFICATION TO ADD WAGE DETERMINATION TN20220205 |
| Mar 6, 2025 | P00010 | $307.9K | EXERCISE OPTIONS 1223 AND 3223 PISTON OPTIONS. |
| Feb 18, 2025 | A00003 | $292.5K | CASE OH012 OH015 OH019 A00003 MISC. CHANGES |
| Oct 3, 2024 | P00009 | $0 | ADDING PAYMENT PROCEDURES FOR OFF-SITE MATERIALS. |
| Aug 20, 2024 | P00008 | $19.8K | EXERCISE OPTION 5011 |
| Aug 14, 2024 | A00002 | $-12.5K | CASE OH003 MODIFICATION A00002 "SHAFT SLEEVE MANDREL DESCOPE" |
| Jul 1, 2024 | P00007 | $157.6K | OPTION 0201 MANDRELS AND CLAMPS |
| Jun 25, 2024 | A00001 | $10.4K | 61,600 HP KAPLAN RUNNER ASSEMBLY |
| May 21, 2024 | P00006 | $153.8K | OH TG REHAB, OPTION 2223 SERVOMOTOR BLADE |
| May 17, 2024 | P00005 | $-8.0K | 61,600 HP KAPLAN RUNNER ASSEMBLY - CLIN RE-SEQUENCE. |
| Mar 21, 2024 | P00004 | $397.0K | EXERCISE OPTION CLINS FOR UNIT #2 (0210, 2200, 2201, 2202, 2203, 2215, 2216, 2226.) |
| Dec 22, 2023 | P00003 | $51.1K | EXERCISE A QTY OF 1 EACH OF OPTION CLINS: 1212, 2212, 3212, 1217, 2217, 3217, 1219, 2219, 3219 FOR WG FINAL HEIGHT. |
| Sep 26, 2023 | P00002 | $153.0K | EXERCISE OPTION 0209 WICKET GATE, SPARE AND INCLUDE 52.204-27 BYTEDANCE CLAUSE |
| Mar 23, 2023 | P00001 | $0 | NOTICE TO PROCEED MODIFICATION |
| Feb 2, 2023 | 0 | $81.6M | REHABILITATION OF OLD HICKORY TURBINE GENERATORS |
Estimated positioning window
Oct 5, 2029 – Apr 5, 2030
45/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 45/100. Available recorded signals: 40 points.
- Contract end 2030-10-05 (1441 days from calculation)
- +5 points
- 2 historical awards in this buyer and category group
- +10 points
- 32 recorded award transactions
- +10 points
- Latest award action: 2026-06-10
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.