Federal contract award

W912P721C0010

CONSTRUCTION OF THE SOUTH SAN FRANCISCO BAY SHORELINE REACH 1-3 PROJECT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SAN FRAN
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$154.6M
Current contract value$154.6M
Potential contract value / ceiling$154.6M
Start dateAug 13, 2021
Current end dateAug 23, 2026
Potential end dateAug 23, 2026
Latest award activityMay 1, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 1, 2026P00017$861.0KA. SCOPE OF WORK PROVIDE ALL LABOR, EQUIPMENT, MATERIALS, INCIDENTALS, SUPERVISION AND ADMINISTRATION TO COVER OPERATIONAL AND TIME IMPACT COSTS RESULTING FROM REACH 1 HYDROGEN SULFIDE MITIGATION WORK FROM 8/15/2022 THROUGH THE COMPLETION OF REACH 1
May 30, 2025A00025$0SR020 WEATHER TIME EXTENSION FEB 25 - MAR 25
May 12, 2025A00024$0SR018 WEATHER TIME EXT NOV 24 - DEC 24
Apr 15, 2025A00023$29.4KSR015 GRAND BLVD WATER LINE REPAIR II
Apr 1, 2025A00022$401.5KVR018-MISSING GOV FILL
Dec 20, 2024P00016$1.6MCHANGE VR026, RFP-0009 - H2S TIME & OPERATIONS IMPACTS REACH 2/3. BILATERAL AGREEMENT.
Nov 6, 2024A00021$167.3KSF SHORELINE REACHES 1-3 SR014- GRAND BLVD WATER LINE REPAIR
Oct 21, 2024P00015$2.3MVR014 FOR RFP007 BILATERAL AGREEMENT.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.