Federal contract award
W912P721C0010
CONSTRUCTION OF THE SOUTH SAN FRANCISCO BAY SHORELINE REACH 1-3 PROJECT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SAN FRAN |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $154.6M |
| Current contract value | $154.6M |
| Potential contract value / ceiling | $154.6M |
| Start date | Aug 13, 2021 |
| Current end date | Aug 23, 2026 |
| Potential end date | Aug 23, 2026 |
| Latest award activity | May 1, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 1, 2026 | P00017 | $861.0K | A. SCOPE OF WORK PROVIDE ALL LABOR, EQUIPMENT, MATERIALS, INCIDENTALS, SUPERVISION AND ADMINISTRATION TO COVER OPERATIONAL AND TIME IMPACT COSTS RESULTING FROM REACH 1 HYDROGEN SULFIDE MITIGATION WORK FROM 8/15/2022 THROUGH THE COMPLETION OF REACH 1 |
| May 30, 2025 | A00025 | $0 | SR020 WEATHER TIME EXTENSION FEB 25 - MAR 25 |
| May 12, 2025 | A00024 | $0 | SR018 WEATHER TIME EXT NOV 24 - DEC 24 |
| Apr 15, 2025 | A00023 | $29.4K | SR015 GRAND BLVD WATER LINE REPAIR II |
| Apr 1, 2025 | A00022 | $401.5K | VR018-MISSING GOV FILL |
| Dec 20, 2024 | P00016 | $1.6M | CHANGE VR026, RFP-0009 - H2S TIME & OPERATIONS IMPACTS REACH 2/3. BILATERAL AGREEMENT. |
| Nov 6, 2024 | A00021 | $167.3K | SF SHORELINE REACHES 1-3 SR014- GRAND BLVD WATER LINE REPAIR |
| Oct 21, 2024 | P00015 | $2.3M | VR014 FOR RFP007 BILATERAL AGREEMENT. |