Federal contract award
W912P723C0005
SAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SAN FRAN |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1DZ — CONSTRUCTION OF OTHER HOSPITAL BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $65.5M |
| Current contract value | $65.5M |
| Potential contract value / ceiling | $65.5M |
| Start date | Mar 1, 2023 |
| Current end date | Mar 24, 2027 |
| Potential end date | Mar 24, 2027 |
| Latest award activity | May 18, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 80 of 80 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 18, 2026 | P00013 | $737.7K | REPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT. |
| May 12, 2026 | P00012 | $200.0K | REPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT. |
| Apr 21, 2026 | P00011 | $400.0K | CONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB. |
| Apr 3, 2026 | P00010 | $192.6K | CONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB. |
| Mar 24, 2026 | P00009 | $1.6M | COST ESCALATION FOR SIERRA ELECTRIC AND PETERSON MECHANICAL FOR DELAY. NO CHANGE IN DRAWINGS OR SPECIFICATIONS. |
| Mar 10, 2026 | A00066 | $38.8K | AS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS. |
| Mar 3, 2026 | P00008 | $448.2K | AS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS. |
| Feb 19, 2026 | A00064 | $219.0K | CONTRACTOR IS TO FURNISH LOW PROFILE LIGHTS IN CORRIDORS PER RFI-0267 |
| Feb 19, 2026 | A00065 | $68.8K | CONTRACTOR IS TO COMPLETE WORK PER RFI-0272, RFI-0279, RFI-0265, RFI-0291. |
| Feb 11, 2026 | P00007 | $1.9M | VR081-INCREASE THE PERIOD OF PERFORMANCE BY 361 CALENDAR DAYS, TO INCLUDE SHOTCRETE REMOBILIZATION AND SUPPORT, MECHANICAL/ELECTRICAL/PLUMBING STORAGE COSTS, MOBILIZATION COSTS, ADDITIONAL SHORING RENT, AND ADDITIONAL QUALITY CONTROL OVERSIGHT. |
| Feb 4, 2026 | P00006 | $104.6K | VR086-1: RFI-0303 END ROOM SLAB REBUILD CONTRACTOR IS TO BACKFILL THE SLABS ON THE WINGS PER RFI-0303. CONTRACTOR IS TO ENSURE FINAL ELEVATION OF NEW SLAB ASSEMBLY IS FLUSH WITH EXISTING STRUCTURAL SLAB. |
| Jan 22, 2026 | A00063 | $269.1K | CONTRACTOR TO DEMO ADDITIONAL MATERIAL AROUND EXISTING WINDOWS TO ACHIEVE A SUITABLE INSTALLATION SURFACE FOR THE NEW WINDOWS. |
| Jan 15, 2026 | A00062 | $50.4K | CONTRACTOR IS TO PROVIDE FIRE DAMPERS PER UPDATED SPECIFICATION 23 31 00. ADDITIONALLY, FIRE DAMPER LOCATIONS WERE REMOVED FROM THE FIRE ALARM SHEETS AND ADDED TO THE MECHANICAL POWER SHEETS. |
| Jan 6, 2026 | A00061 | $33.7K | PER RFI-0262 CONTRACTOR IS TO INFILL JOIST AS SHOWN IN UPDATED DETAIL 08/08-SS6.01. ANY INTERRUPTED BARS ARE TO FOLLOW DETAIL 02/08-SS0.22. PER RFI-0257 CONTRACTOR IS TO PROVIDE EXTERIOR STAIR ANCHOR PLATES AS SHOWN IN UPDATED DETAILS ON SHEETS. |
| Dec 18, 2025 | A00060 | $46.8K | CONTRACTOR IS TO DEMOLISH JOIST IN WAY OF COLLECTOR BARS AND INFILL RESULTING VOID ON GRIDLINE 8 ON THE FOURTH FLOOR. DEMO AND RESULTING INFILL ARE TO FOLLOW DETAIL 15B/08-SS3.42. |
| Dec 16, 2025 | A00059 | $80.4K | CONTRACTOR IS TO DEMOLISH TOPPING LAYERS DOWN TO BOTTOM STRUCTURAL LAYER WITH LARGE AGGREGATE. ONCE FLOOR IS DOWN TO STRUCTURE, CONTRACTOR IS TO SURVEY ELEVATIONS OF STRUCTURAL SLAB. THIS IS TO OCCUR ON ALL FLOOR BOTH NORTH AND SOUTH. |
| Dec 15, 2025 | A00058 | $104.9K | ALL INTERIOR DOORS ARE TO BE 7FT. TALL PER UPDATED DOOR SCHEDULE AND INTERIOR ELEVATIONS. CONTRACTOR IS TO MOVE THE UFER GROUND IN THE NORTH STAIR TOWER TO A SECTION OF CONCRETE THAT IS NOT WRAPPED IN WATERPROOFING. |
| Dec 3, 2025 | A00057 | $9.3K | CONTRACTOR IS TO VACATE THE LAYDOWN YARD TO THE WEST OF BLDG. 209. THE MEDICAL CENTER AWARDED A NEW CONTRACT AND HAS RESCINDED THE RIGHT TO USE THE LAYDOWN SPACE. BRICE HAS TO MOVE OUT BY 01 NOVEMBER 2025. |
| Oct 20, 2025 | A00056 | $19.1K | SF VA BUILDING 8 |
| Oct 10, 2025 | A00055 | $65.3K | SF VA BUILDING 8 |
| Oct 9, 2025 | A00054 | $59.0K | SF VA BUILDING 8 |
| Aug 13, 2025 | A00053 | $100.0K | SF VA BUILDING 8. BILATERAL. VR053 RFP0053 WINDOW UPDATE. |
| Jul 25, 2025 | A00052 | $129.2K | SF VA BUILDING 8 VR070 ELEVATOR LOBBY SLAB REFERENCE NO. R00057 TOTAL CONTRACT PRICE INCREASED BY $129,194.76. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jul 17, 2025 | A00051 | $77.4K | SF VA BUILDING 8 VR055 ENTRYWAY DRAIN REFERENCE NO. R00056 TOTAL CONTRACT PRICE INCREASED BY $77,355.63. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jul 15, 2025 | A00050 | $-15.1K | SF VA BUILDING 8 |
| Jun 6, 2025 | A00049 | $199.2K | SF VA BUILDING 8 VR063 SLAB JOIST INFILLS UPDATES REFERENCE NO. R00054 TOTAL CONTRACT PRICE INCREASED BY $199,216.12. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jun 4, 2025 | A00047 | $45.1K | SF VA BUILDING 8 VR067 RAT SLAB REMOVAL REFERENCE NO. R00052 TOTAL CONTRACT PRICE INCREASED BY $45,102.45. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jun 4, 2025 | A00048 | $-4.5K | SF VA BUILDING 8 VR062 PULL TEST CREDIT TOTAL CONTRACT PRICE DECREASED BY $4500. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jun 3, 2025 | A00046 | $65.0K | SF VA BUILDING 8, CHANGE VR054/RFP055 |
| May 7, 2025 | A00045 | $13.4K | SF VA BUILDING 8 ADDITIONAL MEP CURB RFI-0201 VR061 +$13,432.38 |
| Mar 27, 2025 | A00044 | $3.5K | SF VA BUILDING 8 VR060 DEDICATED TMS CIRCUITS (REFERENCE NO. R00049) TOTAL CONTRACT PRICE IS INCREASED BY $3,546.61. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Mar 25, 2025 | A00043 | $42.0K | SF VA BUILDING 8 VR057 CHILLER UPDATE, REFERENCE NO. R00048 TOTAL CONTRACT PRICE IS INCREASED BY $41,957.93. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Mar 21, 2025 | A00042 | $318.2K | SF VA BUILDING 8 VR056 ADDITIONAL FLOOR FLOAT & CHILLER WELL REFERENCE NO R00047 THE TOTAL CONTRACT PRICE IS INCREASED BY $ 318,234.28 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Mar 20, 2025 | A00041 | $7.3K | SF VA BUILDING 8, CHANGE VR058/RFP-059 |
| Feb 19, 2025 | A00040 | $42.1K | SF VA BUILDING 8 VR050 NEW CAMPUS NETWORK CONNECTION REFERENCE NO. R00045 |
| Feb 10, 2025 | A00039 | $36.5K | SF VA BUILDING 8, CHANGE VR044/RFP-054 |
| Dec 18, 2024 | A00038 | $15.7K | VR047 GRAVITY BEAM CHANGES CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO. REFERENCE NO. R00043 TOTAL CONTRACT PRICE IS INCREASED BY $15,736.06. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Dec 13, 2024 | A00037 | $151.5K | SF VA BUILDING 8 VR024 PLUMBING CHANGE REFERENCE NO.R00042 TOTAL CONTRACT PRICE IS INCREASED BY $151,537.04 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Nov 20, 2024 | A00036 | $11.2K | SF VA BUILDING 8 REFERENCE NO. R00041 VR043 DOOR CHANGES |
| Nov 12, 2024 | A00035 | $165.2K | SF VA BUILDING 8 REFERENCE NO. R00040 VR037 SHEARWALLS AT GL 4&10 TOTAL CONTRACT PRICE IS INCREASED BY $165,230.04. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Nov 7, 2024 | A00034 | $54.7K | SF VA BUILDING 8 BIM MODEL INTEGRATION CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO, CA 94121. REFERENCE NO. R00039 VR048 BIM MODEL INTEGRATION (+$54,695.69, 0 CD) |
| Oct 22, 2024 | A00033 | $165.5K | SF VA BUILDING 8 VR 038 MEP SHAFT GS 5 & A |
| Oct 18, 2024 | A00032 | $57.4K | SF VA BUILDING 8 VR046 MICROPILE WATERPROOFING |
| Oct 4, 2024 | P00005 | $2.1M | SF VA BUILDING 8 SEISMIC RETROFIT- DEFINITIZE P00003 FOR PILE CAP AND GRADE BEAM DEPTHS. |
| Oct 3, 2024 | A00031 | $212.9K | SF VA BUILDING 8 VR041 ADDITIONAL DOBIE DATA |
| Sep 19, 2024 | A00030 | $0 | SF VA BUILDING 8 VR045 ELECTRICAL ROOM SWITCH |
| Sep 6, 2024 | A00029 | $126.8K | SF VA BUILDING 8 VR035 JANITOR'S CLOSETS |
| Sep 3, 2024 | A00028 | $59.8K | SF VA BUILDING 8 VR036 MEP ROOF STRUCTURE INFILL |
| Aug 14, 2024 | A00027 | $0 | SF VA BUILDING 8 VR042 SPALLING INVESTIGATION |
| Aug 7, 2024 | A00026 | $18.5K | SF VA BUILDING 8 VR040, EXISTING ELEVATOR SHAFT CHANGES |
| Aug 6, 2024 | A00025 | $361.4K | SF VA BUILDING 8 VR032 ADDITIONAL JOIST INFILL |
| Aug 5, 2024 | P00004 | $568.9K | SF VA BUILDING 8 VR034 WESTERN STAIR GRADEBEAM ACCESS |
| Jul 30, 2024 | A00024 | $0 | SF VA BUILDING 8 VR025, FIRE SAFETY UPDATES |
| Jun 4, 2024 | A00022 | $108.0K | REFERENCE NO. R00025 VR029 ADDITIONAL ACM TOTAL CONTRACT PRICE IS INCREASED BY $108,027.91. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jun 4, 2024 | A00023 | $14.8K | SF VA BUILDING 8 VR031, DCP REVISION REQUEST |
| May 30, 2024 | P00003 | $588.4K | R00024 VR030-1 PILE CAP AND GRADE BEAM DEPTH TOTAL CONTRACT PRICE IS INCREASED BY $588,364.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| May 28, 2024 | A00021 | $16.4K | REFERENCE NO. R00023 VR023 SLAB THICKNESS TOTAL CONTRACT PRICE IS INCREASED BY $16,438.17. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| May 23, 2024 | A00020 | $36.2K | SF VA BUILDING 8 |
| May 22, 2024 | A00019 | $8.4K | REFERENCE NO. R00021 VR026 RFI-0122 RWL/OFC FURRED WALL AT PENTHOUSE TOTAL CONTRACT PRICE IS INCREASED BY $8,377.81. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| May 21, 2024 | P00002 | $1.6M | DEFINITIZE UNILATERAL MOD P00001 FOR COST AND TIME & W/BILATERAL AGREEMENT. |
| May 13, 2024 | A00016 | $7.8K | SF VA BUILDING 8 VR017 & VR020 |
| May 13, 2024 | A00017 | $103.0K | SF VA BUILDING 8 VR019 VAPOR BARRIER TESTING AND COMMISSIONING |
| May 13, 2024 | A00018 | $93.4K | SF VA BUILDING 8 VR027 ADDITIONAL JOIST ROUGHENING |
| Mar 8, 2024 | A00015 | $262.7K | SF VA BUILDING 8 VR022 REMOVAL OF ADDITIONAL CONCRETE COURSE |
| Mar 5, 2024 | A00014 | $7.2K | SF VA BUILDING 8 VR016 & VR018 |
| Jan 24, 2024 | P00001 | $356.4K | SF VA BUILDING 8 VR014 - BUILDING #24 UTILITY CONFLICT RESOLUTION. |
| Jan 17, 2024 | A00013 | $14.1K | SF VA BUILDING 8 |
| Jan 16, 2024 | A00012 | $0 | SF VA BUILDING 8 |
| Jan 9, 2024 | A00011 | $0 | BUILDING 8 |
| Oct 17, 2023 | A00010 | $18.8K | CONTRACT NO. W912P723C0005 VR011 RFI-0026 ELECTRICAL TRENCH VR014 BLDG 24 FOUNDATION LOCATION |
| Oct 10, 2023 | A00009 | $4.1K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR013 (RFP-013) RFI-0030 FLOOR 2 DIAPHRAGM DEMO |
| Oct 4, 2023 | A00007 | $20.0K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR012 (RFP-012) REMOVE GOVERNMENT FIELD OFFICE VR010 (RFP-010) EXISTING UTILITY LOCATION |
| Oct 4, 2023 | A00008 | $435.0K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR009 (RFP-009) RFI-21 PROTECT FA FIBER B8 TEMP FA B212 SEE PAGE 2. |
| Aug 10, 2023 | A00006 | $0 | BUILDING 8 SEISMIC RETROFIT REFERENCE NO. R00005 VR005 SPECIFICATIONS - CONFORMED SOLICITATION |
| Aug 8, 2023 | A00005 | $2.2K | VR007, TEMP POWER WORK - MC DELAYS |
| Jun 30, 2023 | A00004 | $913 | CONTRACT NO. W912P723C0005 BUILDING 8 SEISMIC RETROFIT |
| Jun 14, 2023 | A00003 | $9.8K | CONTRACT NO. W912P723C0005 BLDG. 8 SEISMIC RETROFIT VR004 (RFP-0004) SECOND LAYER OF SIDEWALK SEE PAGE 2. |
| May 8, 2023 | A00002 | $41.8K | CONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR002 (RFP-002) GOVERNMENT FIELD OFFICE SEE PAGE 2. |
| Mar 24, 2023 | A00001 | $0 | VR001 CONTRACTOR FIELD OFFICE LOCATION |
| Feb 14, 2023 | 0 | $50.0M | SAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT |
Estimated positioning window
Nov 1, 2026 – Jan 30, 2027
65/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 65/100. Available recorded signals: 60 points.
- Contract end 2027-03-24 (143 days from calculation)
- +35 points
- 1 historical awards in this buyer and category group
- +0 points
- 80 recorded award transactions
- +10 points
- Latest award action: 2026-05-18
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.