Federal contract award

W912P723C0005

SAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SAN FRAN
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1DZ — CONSTRUCTION OF OTHER HOSPITAL BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$65.5M
Current contract value$65.5M
Potential contract value / ceiling$65.5M
Start dateMar 1, 2023
Current end dateMar 24, 2027
Potential end dateMar 24, 2027
Latest award activityMay 18, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 80 of 80 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 18, 2026P00013$737.7KREPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT.
May 12, 2026P00012$200.0KREPAIR FLOORS 2-4 INFILL SLABS USING 2IN. ULTRA-HIGH PERFORMANCE LIGHTWEIGHT CONCRETE (FIBER/NON-FIBER) WITH PINNED/SEALED GALVANIZED PLATES. JOIST REPAIRS PER PLAN. DESCOPE: FIREPROOFING MEMBRANE AND FLOOR FLOAT.
Apr 21, 2026P00011$400.0KCONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB.
Apr 3, 2026P00010$192.6KCONTRACTOR SHALL REBUILD END WING SLAB TO BE FLUSH WITH THE EXISTING STRUCTURAL SLAB AND PROVIDE PRODUCT DATA AND SHOP DRAWINGS FOR FINAL APPROVAL PRIOR TO START OF WORK. REBUILD THE END WING SLABS AND PLACE FLOOR LEVELING MATERIAL ON THE NEW SLAB.
Mar 24, 2026P00009$1.6MCOST ESCALATION FOR SIERRA ELECTRIC AND PETERSON MECHANICAL FOR DELAY. NO CHANGE IN DRAWINGS OR SPECIFICATIONS.
Mar 10, 2026A00066$38.8KAS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS.
Mar 3, 2026P00008$448.2KAS A RESULT OF MODIFICATION P00007 THE PERIOD OF PERFORMANCE AND CONTRACT REQUIRED COMPLETION DATE WAS EXTENDED TO 3/20/2027. THIS CHANGE COMPENSATES ALL BRB SUBCONTRACTORS FOR ESCALATION COSTS.
Feb 19, 2026A00064$219.0KCONTRACTOR IS TO FURNISH LOW PROFILE LIGHTS IN CORRIDORS PER RFI-0267
Feb 19, 2026A00065$68.8KCONTRACTOR IS TO COMPLETE WORK PER RFI-0272, RFI-0279, RFI-0265, RFI-0291.
Feb 11, 2026P00007$1.9MVR081-INCREASE THE PERIOD OF PERFORMANCE BY 361 CALENDAR DAYS, TO INCLUDE SHOTCRETE REMOBILIZATION AND SUPPORT, MECHANICAL/ELECTRICAL/PLUMBING STORAGE COSTS, MOBILIZATION COSTS, ADDITIONAL SHORING RENT, AND ADDITIONAL QUALITY CONTROL OVERSIGHT.
Feb 4, 2026P00006$104.6KVR086-1: RFI-0303 END ROOM SLAB REBUILD CONTRACTOR IS TO BACKFILL THE SLABS ON THE WINGS PER RFI-0303. CONTRACTOR IS TO ENSURE FINAL ELEVATION OF NEW SLAB ASSEMBLY IS FLUSH WITH EXISTING STRUCTURAL SLAB.
Jan 22, 2026A00063$269.1KCONTRACTOR TO DEMO ADDITIONAL MATERIAL AROUND EXISTING WINDOWS TO ACHIEVE A SUITABLE INSTALLATION SURFACE FOR THE NEW WINDOWS.
Jan 15, 2026A00062$50.4KCONTRACTOR IS TO PROVIDE FIRE DAMPERS PER UPDATED SPECIFICATION 23 31 00. ADDITIONALLY, FIRE DAMPER LOCATIONS WERE REMOVED FROM THE FIRE ALARM SHEETS AND ADDED TO THE MECHANICAL POWER SHEETS.
Jan 6, 2026A00061$33.7KPER RFI-0262 CONTRACTOR IS TO INFILL JOIST AS SHOWN IN UPDATED DETAIL 08/08-SS6.01. ANY INTERRUPTED BARS ARE TO FOLLOW DETAIL 02/08-SS0.22. PER RFI-0257 CONTRACTOR IS TO PROVIDE EXTERIOR STAIR ANCHOR PLATES AS SHOWN IN UPDATED DETAILS ON SHEETS.
Dec 18, 2025A00060$46.8KCONTRACTOR IS TO DEMOLISH JOIST IN WAY OF COLLECTOR BARS AND INFILL RESULTING VOID ON GRIDLINE 8 ON THE FOURTH FLOOR. DEMO AND RESULTING INFILL ARE TO FOLLOW DETAIL 15B/08-SS3.42.
Dec 16, 2025A00059$80.4KCONTRACTOR IS TO DEMOLISH TOPPING LAYERS DOWN TO BOTTOM STRUCTURAL LAYER WITH LARGE AGGREGATE. ONCE FLOOR IS DOWN TO STRUCTURE, CONTRACTOR IS TO SURVEY ELEVATIONS OF STRUCTURAL SLAB. THIS IS TO OCCUR ON ALL FLOOR BOTH NORTH AND SOUTH.
Dec 15, 2025A00058$104.9KALL INTERIOR DOORS ARE TO BE 7FT. TALL PER UPDATED DOOR SCHEDULE AND INTERIOR ELEVATIONS. CONTRACTOR IS TO MOVE THE UFER GROUND IN THE NORTH STAIR TOWER TO A SECTION OF CONCRETE THAT IS NOT WRAPPED IN WATERPROOFING.
Dec 3, 2025A00057$9.3KCONTRACTOR IS TO VACATE THE LAYDOWN YARD TO THE WEST OF BLDG. 209. THE MEDICAL CENTER AWARDED A NEW CONTRACT AND HAS RESCINDED THE RIGHT TO USE THE LAYDOWN SPACE. BRICE HAS TO MOVE OUT BY 01 NOVEMBER 2025.
Oct 20, 2025A00056$19.1KSF VA BUILDING 8
Oct 10, 2025A00055$65.3KSF VA BUILDING 8
Oct 9, 2025A00054$59.0KSF VA BUILDING 8
Aug 13, 2025A00053$100.0KSF VA BUILDING 8. BILATERAL. VR053 RFP0053 WINDOW UPDATE.
Jul 25, 2025A00052$129.2KSF VA BUILDING 8 VR070 ELEVATOR LOBBY SLAB REFERENCE NO. R00057 TOTAL CONTRACT PRICE INCREASED BY $129,194.76. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jul 17, 2025A00051$77.4KSF VA BUILDING 8 VR055 ENTRYWAY DRAIN REFERENCE NO. R00056 TOTAL CONTRACT PRICE INCREASED BY $77,355.63. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jul 15, 2025A00050$-15.1KSF VA BUILDING 8
Jun 6, 2025A00049$199.2KSF VA BUILDING 8 VR063 SLAB JOIST INFILLS UPDATES REFERENCE NO. R00054 TOTAL CONTRACT PRICE INCREASED BY $199,216.12. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jun 4, 2025A00047$45.1KSF VA BUILDING 8 VR067 RAT SLAB REMOVAL REFERENCE NO. R00052 TOTAL CONTRACT PRICE INCREASED BY $45,102.45. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jun 4, 2025A00048$-4.5KSF VA BUILDING 8 VR062 PULL TEST CREDIT TOTAL CONTRACT PRICE DECREASED BY $4500. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jun 3, 2025A00046$65.0KSF VA BUILDING 8, CHANGE VR054/RFP055
May 7, 2025A00045$13.4KSF VA BUILDING 8 ADDITIONAL MEP CURB RFI-0201 VR061 +$13,432.38
Mar 27, 2025A00044$3.5KSF VA BUILDING 8 VR060 DEDICATED TMS CIRCUITS (REFERENCE NO. R00049) TOTAL CONTRACT PRICE IS INCREASED BY $3,546.61. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Mar 25, 2025A00043$42.0KSF VA BUILDING 8 VR057 CHILLER UPDATE, REFERENCE NO. R00048 TOTAL CONTRACT PRICE IS INCREASED BY $41,957.93. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Mar 21, 2025A00042$318.2KSF VA BUILDING 8 VR056 ADDITIONAL FLOOR FLOAT & CHILLER WELL REFERENCE NO R00047 THE TOTAL CONTRACT PRICE IS INCREASED BY $ 318,234.28 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Mar 20, 2025A00041$7.3KSF VA BUILDING 8, CHANGE VR058/RFP-059
Feb 19, 2025A00040$42.1KSF VA BUILDING 8 VR050 NEW CAMPUS NETWORK CONNECTION REFERENCE NO. R00045
Feb 10, 2025A00039$36.5KSF VA BUILDING 8, CHANGE VR044/RFP-054
Dec 18, 2024A00038$15.7KVR047 GRAVITY BEAM CHANGES CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO. REFERENCE NO. R00043 TOTAL CONTRACT PRICE IS INCREASED BY $15,736.06. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Dec 13, 2024A00037$151.5KSF VA BUILDING 8 VR024 PLUMBING CHANGE REFERENCE NO.R00042 TOTAL CONTRACT PRICE IS INCREASED BY $151,537.04 THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Nov 20, 2024A00036$11.2KSF VA BUILDING 8 REFERENCE NO. R00041 VR043 DOOR CHANGES
Nov 12, 2024A00035$165.2KSF VA BUILDING 8 REFERENCE NO. R00040 VR037 SHEARWALLS AT GL 4&10 TOTAL CONTRACT PRICE IS INCREASED BY $165,230.04. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Nov 7, 2024A00034$54.7KSF VA BUILDING 8 BIM MODEL INTEGRATION CONTRACT FOR BLDG 8 SEISMIC RETROFIT AT 4150 CLEMENT STREET, SAN FRANCISCO, CA 94121. REFERENCE NO. R00039 VR048 BIM MODEL INTEGRATION (+$54,695.69, 0 CD)
Oct 22, 2024A00033$165.5KSF VA BUILDING 8 VR 038 MEP SHAFT GS 5 & A
Oct 18, 2024A00032$57.4KSF VA BUILDING 8 VR046 MICROPILE WATERPROOFING
Oct 4, 2024P00005$2.1MSF VA BUILDING 8 SEISMIC RETROFIT- DEFINITIZE P00003 FOR PILE CAP AND GRADE BEAM DEPTHS.
Oct 3, 2024A00031$212.9KSF VA BUILDING 8 VR041 ADDITIONAL DOBIE DATA
Sep 19, 2024A00030$0SF VA BUILDING 8 VR045 ELECTRICAL ROOM SWITCH
Sep 6, 2024A00029$126.8KSF VA BUILDING 8 VR035 JANITOR'S CLOSETS
Sep 3, 2024A00028$59.8KSF VA BUILDING 8 VR036 MEP ROOF STRUCTURE INFILL
Aug 14, 2024A00027$0SF VA BUILDING 8 VR042 SPALLING INVESTIGATION
Aug 7, 2024A00026$18.5KSF VA BUILDING 8 VR040, EXISTING ELEVATOR SHAFT CHANGES
Aug 6, 2024A00025$361.4KSF VA BUILDING 8 VR032 ADDITIONAL JOIST INFILL
Aug 5, 2024P00004$568.9KSF VA BUILDING 8 VR034 WESTERN STAIR GRADEBEAM ACCESS
Jul 30, 2024A00024$0SF VA BUILDING 8 VR025, FIRE SAFETY UPDATES
Jun 4, 2024A00022$108.0KREFERENCE NO. R00025 VR029 ADDITIONAL ACM TOTAL CONTRACT PRICE IS INCREASED BY $108,027.91. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jun 4, 2024A00023$14.8KSF VA BUILDING 8 VR031, DCP REVISION REQUEST
May 30, 2024P00003$588.4KR00024 VR030-1 PILE CAP AND GRADE BEAM DEPTH TOTAL CONTRACT PRICE IS INCREASED BY $588,364.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
May 28, 2024A00021$16.4KREFERENCE NO. R00023 VR023 SLAB THICKNESS TOTAL CONTRACT PRICE IS INCREASED BY $16,438.17. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
May 23, 2024A00020$36.2KSF VA BUILDING 8
May 22, 2024A00019$8.4KREFERENCE NO. R00021 VR026 RFI-0122 RWL/OFC FURRED WALL AT PENTHOUSE TOTAL CONTRACT PRICE IS INCREASED BY $8,377.81. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
May 21, 2024P00002$1.6MDEFINITIZE UNILATERAL MOD P00001 FOR COST AND TIME & W/BILATERAL AGREEMENT.
May 13, 2024A00016$7.8KSF VA BUILDING 8 VR017 & VR020
May 13, 2024A00017$103.0KSF VA BUILDING 8 VR019 VAPOR BARRIER TESTING AND COMMISSIONING
May 13, 2024A00018$93.4KSF VA BUILDING 8 VR027 ADDITIONAL JOIST ROUGHENING
Mar 8, 2024A00015$262.7KSF VA BUILDING 8 VR022 REMOVAL OF ADDITIONAL CONCRETE COURSE
Mar 5, 2024A00014$7.2KSF VA BUILDING 8 VR016 & VR018
Jan 24, 2024P00001$356.4KSF VA BUILDING 8 VR014 - BUILDING #24 UTILITY CONFLICT RESOLUTION.
Jan 17, 2024A00013$14.1KSF VA BUILDING 8
Jan 16, 2024A00012$0SF VA BUILDING 8
Jan 9, 2024A00011$0BUILDING 8
Oct 17, 2023A00010$18.8KCONTRACT NO. W912P723C0005 VR011 RFI-0026 ELECTRICAL TRENCH VR014 BLDG 24 FOUNDATION LOCATION
Oct 10, 2023A00009$4.1KCONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR013 (RFP-013) RFI-0030 FLOOR 2 DIAPHRAGM DEMO
Oct 4, 2023A00007$20.0KCONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR012 (RFP-012) REMOVE GOVERNMENT FIELD OFFICE VR010 (RFP-010) EXISTING UTILITY LOCATION
Oct 4, 2023A00008$435.0KCONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR009 (RFP-009) RFI-21 PROTECT FA FIBER B8 TEMP FA B212 SEE PAGE 2.
Aug 10, 2023A00006$0BUILDING 8 SEISMIC RETROFIT REFERENCE NO. R00005 VR005 SPECIFICATIONS - CONFORMED SOLICITATION
Aug 8, 2023A00005$2.2KVR007, TEMP POWER WORK - MC DELAYS
Jun 30, 2023A00004$913CONTRACT NO. W912P723C0005 BUILDING 8 SEISMIC RETROFIT
Jun 14, 2023A00003$9.8KCONTRACT NO. W912P723C0005 BLDG. 8 SEISMIC RETROFIT VR004 (RFP-0004) SECOND LAYER OF SIDEWALK SEE PAGE 2.
May 8, 2023A00002$41.8KCONTRACT NO. W912P723C0005 SFVA BLDG. 8 SEISMIC RETROFIT VR002 (RFP-002) GOVERNMENT FIELD OFFICE SEE PAGE 2.
Mar 24, 2023A00001$0VR001 CONTRACTOR FIELD OFFICE LOCATION
Feb 14, 20230$50.0MSAN FRANCISCO VA MEDICAL CENTER BUILDING 8 SEISMIC RETROFIT PROJECT

Estimated positioning window

Nov 1, 2026 – Jan 30, 2027

Recompete signal:
65/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 65/100. Available recorded signals: 60 points.

Contract end 2027-03-24 (143 days from calculation)
+35 points
1 historical awards in this buyer and category group
+0 points
80 recorded award transactions
+10 points
Latest award action: 2026-05-18
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.