Federal contract award

W912P821C0002

NOV-NF-06A.2

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW07V ENDIST NEW ORLEANS
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$73.7M
Current contract value$73.7M
Potential contract value / ceiling$82.2M
Start dateOct 30, 2020
Current end dateJul 7, 2026
Potential end dateJul 7, 2026
Latest award activityJun 4, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 41 of 41 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 4, 2026A00033$41.1KREA: ASPHALTIC PAVEMENT CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT,POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANAREFERENCE NO. R00040
Sep 22, 2025A00032$0WEATHER (5/1/2025 - 7/31/2025) CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA REFERENCE NO. R00039
Jun 30, 2025A00031$-40.2KQTY VAR CLIN'S: 0023, 0037, 0038, 0046 CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA
Jun 9, 2025A00030$0WEATHER (2/1/2025 - 4/30/2025) CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA
Jun 2, 2025P00007$2.0MC015 POST IDA DITCH RE-EXCAVATION
Apr 10, 2025P00006$544.0K21C0002 NOV 6A.2 VEQ P00007
Feb 27, 2025A00029$0WEATHER (9/1/2024 - 1/31/2025) CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA REFERENCE NO. R00035
Jan 27, 2025P00005$3.6MVEQ - ADDITIONAL EMBANKMENT, COMPACTED FILL
Sep 24, 2024A00028$0WEATHER (6/1/2024-8/31/2024) CONTRACT FOR NEW ORLEANS TO VENICE, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA REF NO. R00032 T009 WEATHER (6/1/2024-8/31/2024)
Jul 17, 2024A00027$49.6KCONTRACT FOR NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00030 C014 SLIP JOINT REVISION & CONCRETE PILASTER
Jun 28, 2024A00026$0WEATHER (3/1/2024-5/31/2024) CONTRACT FOR NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO W POINTE A LA HACHE, PLAQUEMINES PARISH, LA REF NO. R00031 T008 WEATHER (3/1/2024-5/31/2024)
May 21, 2024P00004$1.8MV006 - EMBANKMENT, COMPACTED FILL
Apr 22, 2024A00025$0WEATHER (12/1/2023-2/29/2024) CONTRACT FOR NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 FIRST LIFT LEVEE & DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO W POINTE A LA HACHE, PLAQUEMINES PARISH, LA REF NO. R00028 T007 WEATHER (12/1/2023-2/29/2024)
Mar 5, 2024P00003$1.8MEMBANKMENT, COMPACTED FILL
Feb 16, 2024A00024$0WEATHER(9/1/2023-11/30/2023) CONTRACT NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, PT CELESTE TO WEST PT A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REF NO. R00026 T006 WEATHER(9/1/2023-11/30/2023)
Jan 11, 2024A00023$65.2KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO.R00027 C013 SANDBAG REMOVAL & EMB. REPLACEMENT
Oct 25, 2023A00022$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA REFERENCE NO R00022 T005 WEATHER (4/1/2023 - 8/31/2023)
Oct 11, 2023A00021$17.4KCONTRACT FOR NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REF. NO. R00024 C012 REVISED BULKHEAD FABRICATION SEE PAGE 2.
Sep 12, 2023A00020$486.0KREFERENCE NO. R00023 V005 QTY VARIATION CLIN 0021 SEE PAGE 2.
Jul 13, 2023A00019$498.9KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00021 V004 QTY VAR CLIN'S: 0021, 0024
Jul 10, 2023A00018$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00020 T004 WEATHER (1/1/2023 - 3/31/2023)
Jul 7, 2023A00017$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00019 T003 WEATHER (6/1/2022 - 12/31/2022)
Jul 5, 2023A00016$75.0KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REFERENCE NO. R00017 C011 DEF. OF C011A: LEVEE CUT REINFORCEMENT
Jul 3, 2023A00015$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00016 T002 WEATHER (8/1/2021 - 5/31/2022)
Jun 30, 2023A00014$438.1KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00015 V002 QTY VARIATION CLINS 0022 & 0045
Jun 29, 2023A00013$206.7KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00013
Jun 28, 2023A00012$179.1KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00012 V001 QTY VARIATION CLIN 0017
Jun 26, 2023A00011$292.9KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REFERENCE NO. R00010 C006 DEF. C006A (A00002), FABRIC/TEMP/PH CON
Jun 22, 2023A00010$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00011 C011A LEVEE CUT REINFORCEMENT
May 30, 2023A00009$0CONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REFERENCE NO. R00001 T001 WEATHER (12/14/2020 - 7/31/2021)
May 24, 2023A00008$25.9KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE & DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REFERENCE NO. R00008 C009 REPLACE EXISTING DAMAGED CULVERT (CUL-4)
May 23, 2023A00007$31.2KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REF. NO. R00009 C010 BOARD MAT FOUND. 48" DRAIN STA 868+45
May 3, 2023A00006$19.9KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REF. NO. R00007 C008 REPLACE EXISTING DAMAGED CULVERT (CUL-5)
Apr 21, 2023P00002$900.0KEMBANKMENT, COMPACTED FILL
Apr 20, 2023A00005$119.0KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REF. NO. R00006 C004 DEGRADE PRELOAD STA 99+24.86-103+30.70
Apr 10, 2023A00004$6.9KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REF. NO. R00005 C005 REPLACE EXISTING DAMAGED CULVERT (CUL-9)
Mar 20, 2023A00003$75.0KCONTRACT FOR NEW ORLEANS TO VENICE, LOUISIANA, NOV-NF-W-06A.2 FIRST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO WEST POINTE A LA HACHE, PLAQUEMINES PARISH, LOUISIANA. REF. NO. R00004 C002 TEMPORARY BYPASS DITCH AT WTIX CANAL
Jan 6, 2023A00002$0CONTRACT FOR NEW ORLEANS TO VENICE, LA, NOV-NF-W-06A.2 1ST LIFT LEVEE AND DRAINAGE CANAL RELOCATION PROJECT, POINTE CELESTE TO W. POINTE A LA HACHE, PLAQUEMINES PARISH, LA. REFERENCE NO.R00003 C006A FABRIC/TEMPLATE/PHASED STA 220+15-240+25 SEE PG. 2.
Oct 31, 2022A00001$46.5KC003 BOARD MAT FOUND. 48" DRAIN STA 817+89.50
Sep 21, 2022P00001$1.0MEMBANKMENT, COMPACTED FILL
Nov 3, 20200$59.3MNOV-NF-06A.2