Federal contract award
W912P822C0062
CHARENTON FLOODGATE, ST. MARY PARISH, LA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W07V ENDIST NEW ORLEANS |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $55.9M |
| Current contract value | $55.9M |
| Potential contract value / ceiling | $55.9M |
| Start date | Oct 5, 2022 |
| Current end date | Aug 18, 2025 |
| Potential end date | Aug 18, 2025 |
| Latest award activity | Apr 10, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 10, 2026 | A00026 | $0 | JAN - MAR 2026 USW DELAYS CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019)REFERENCE NO. R00026 |
| Jan 28, 2026 | A00025 | $0 | OCT 2025 - DEC 2025 USW DELAYS CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019)REFERENCE NO. R00025 |
| Oct 9, 2025 | A00024 | $0 | CONTRACT NO. W912P822C0062 CHARENTON FLOODGATE REPLACEMENT MODIFICATION NO. A00024 R00024 - JULY 2025 - SEPT 2025 USW DELAYS |
| Jul 9, 2025 | A00023 | $0 | CONTRACT NO. W912P822C0062 CHARENTON FLOODGATE REPLACEMENT MODIFICATION NO. R00023 - APR 2025 - JUN 2025 USW DELAYS |
| Apr 30, 2025 | A00022 | $0 | CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019) REFERENCE NO. R00020 OCT 2024- MARCH 2025 USW |
| Jan 3, 2025 | A00021 | $0 | CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019). REFERENCE NO. R00019 C012 ADJUST LIMITS OF CONSTRUCTION |
| Dec 11, 2024 | A00020 | $12.0K | CONTRACT NO. W912P822C0062 CHARENTON FLOODGATE REPLACEMENT FENCE POST IN MONOLITH CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019) REFERENCE NO. R00021 |
| Oct 25, 2024 | A00019 | $0 | CONTRACT FOR ATCHAFALAYA BASIN CONSTRUCTION, CHARENTON FLOODGATE REPLACEMENT, ST. MARY PARISH, LOUISIANA (ED 21-019). REFERENCE NO. R00020 T006 JULY - SEPTEMBER 2024 USW DELAYS SEE PAGE 2. |