W912PL20C0020
CONSTRUCTION OF THE NEW BROWNFIELD BORDER PATROL STATION.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $45.7M |
| Current contract value | $45.7M |
| Potential contract value / ceiling | $51.1M |
| Start date | Apr 2, 2020 |
| Current end date | May 27, 2026 |
| Potential end date | May 27, 2026 |
| Latest award activity | May 27, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 32 of 32 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 27, 2026 | P00008 | $272.9K | BROWN FIELD BORDER PATROL STATION. MODIFICATION NO. R00033 - SUSPENSION OF WORK REA. TOTAL CONTRACT PRICE INCREASED BY $272,852.00. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 56 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Mar 6, 2026 | A00024 | $0 | BROWN FIELD BORDER PATROL STATION. MODIFICATION NO. R00032 - 90 DAY POP INCREASE. CONTRACT PRICE REMAINS UNCHANGED. COMPLETION DATE SHALL BE INCREASED BY 90 CALENDAR DAYS. SEE BLOCK 14 (SF30 CONTINUATION PAGE) FOR COMPLETE SCOPE. |
| Nov 3, 2025 | P00007 | $-4.2M | MAIN BUILDING FACILITY |
| Aug 4, 2025 | A00023 | $0 | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION REFNO. R00030 SD075 NO COST TIME EXTENSION 120 CD. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 120 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Feb 28, 2025 | A00022 | $26.0K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00029: SD064 SALLY PORT DOOR ELECTRICAL CHANGES. TOTAL CONTRACT PRICE IS INCREASED BY $26,044.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY REASON OF THIS MODIFICATION. |
| Jan 13, 2025 | A00021 | $46.4K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00028: SD062, SD065, SD067, SD068 - MULTIPLE CHANGES. CONTRACT PRICE IS INCREASED BY $46,373.00. THE COMPLETION DATE SHALL REMAIN UNCHANGED BY REASON OF THIS MODIFICATION. |
| Aug 1, 2024 | P00006 | $2.5M | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00027, SD060 TEMP WATER SUPPLY FOR MECHANICAL. CONTRACT PRICE IS INCREASED BY $2,522,631.00. THE COMPLETION DATE SHALL BE EXTENDED BY 346 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Apr 17, 2024 | P00005 | $713.4K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00026, SD051 LEACH FIELD CHANGES. TOTAL CONTRACT PRICE IS INCREASED BY $713,441.00. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 134 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Jan 8, 2024 | A00020 | $0 | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00025, SD063 INCREASE PERFORMANCE PERIOD 81 DAYS. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 81 CALENDAR DAYS BY THIS MODIFICATION. |
| Oct 12, 2023 | A00019 | $0 | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REF NO.R00024 SD061 TIME EXTENSION TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 60 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Aug 11, 2023 | A00018 | $0 | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00023, SD058 TIME EXTENSION. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 90 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Aug 10, 2023 | A00017 | $35.9K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00022, SD050 ADD HELIPAD GROUNDING POINT. TOTAL CONTRACT PRICE IS INCREASED BY $35,894.46. THE CONTRACT COMPLETION SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jul 19, 2023 | A00015 | $17.9K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00021. SD048, SD049, SD052. SD054, SD055, SD056, SD057. TOTAL CONTRACT PRICE IS INCREASED BY $17,860.15. COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Apr 4, 2023 | A00014 | $30 | A00005 MOD WAS INADVERTENTLY APPROVED IN PD2 FOR $30 LESS THAN THE ACTUAL MOD PRICE. MODIFICATION IN PD2 WAS APPROVED WITH AN INCREASE OF $23,091.04 AND SHOULD HAVE BEEN $23,121.04. THIS ACTION WILL CORRECT THE INCREASE TO CLIN 0002 FOR THE $30. |
| Nov 29, 2022 | A00013 | $123.8K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION.REFERENCE NO. R00020 SD042SD046SD047 TOTAL CONTRACT PRICE IS INCREASED BY $123,826.03. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY REASON OF THIS MODIFICATION. |
| Sep 22, 2022 | P00004 | $1.3M | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00019. SD045-2 SDG&E PULL CABINET/ELECTRICAL CHANGES. TOTAL CONTRACT PRICE IS INCREASED BY $1,264,617.00. COMPLETION DATE SHALL BE EXTENDED BY 316 CALENDAR DAYS, TO 13 JULY 2023. |
| Sep 13, 2022 | A00012 | $37.4K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00016, SD043 AV EQUIPMENT CHANGES. PCO094. TOTAL CONTRACT PRICE IS INCREASED BY $37,389.31. COMPLETION DATE REMAINS UNCHANGED. |
| Sep 6, 2022 | A00011 | $4.3K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00017. SD037 WELL H2 SANITARY SEAL & DRILLING PCO-085. SD041 DOOR PULLS AND LECTERN PC0-093. CONTRACT PRICE IS INCREASED BY $4,323.00. COMPLETION DATE SHALL REMAIN UNCHANGED. |
| Aug 15, 2022 | P00003 | $500.0K | NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00018. SD045-1 SDGE PULL CABINET/ELECTRICAL CHANGES NTE/NTP. PRICE IS INCREASED BY $500,000. LEGAL COMPLETION DATE WILL BE CHANGED & REVISED DATE WILL BE PART OF FINAL NEGOTIATIONS. |
| Jun 26, 2022 | A00010 | $87.0K | NEW BROWN FIELD BORDER PATROL STATION. REFERENCE R00015, SD039 B4 STEEL CHANGES AND SD040 LIGHT FIXTURES. CONTRACT PRICE TOO INCREASE BY $86,957. COMPLETION DATE TO REMAIN UNCHANGED BY REASON OF THIS MODIFICATION. |
| Jun 7, 2022 | A00009 | $45.4K | BROWNFIELD BORDER REFERENCE R00014 SD023 CBP LOW VOLTAGE CHANGES PCO079 SD031 SOFFIT SOLATUBES CHANGES B1 PCO082. TOTAL CONTRACT PRICE IS INCREASED BY $45,435.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY REASON OF THE MODIFICATION. |
| May 23, 2022 | A00008 | $20.4K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00013, SD033 ADDTL RETURN AIR GRILLES, SD034 GWUDI, SD035 TRANSFORMER NT12. CONTRACT PRICE INCREASE BY $20,449.00. PERIOD OF PERFORMANCE REMAINS UNCHANGED. |
| May 1, 2022 | A00007 | $4.6K | NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00011. SD029 RMV FLOOR DRAINS, ADD FLOOR SINKS PCO044, SD030 CHANGE FLOOR CLEANOUTS TO ZURN PCO045. TOTAL CONTRACT PRICE INCREASED BY $4,561. COMPLETION DATE SHALL REMAIN UNCHANGED. |
| Apr 22, 2022 | A00006 | $248.8K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00012. SD022 PROPANE TANK. TOTAL CONTRACT PRICE IS INCREASED BY $248,845.87. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGE BY THIS MODIFICATION. |
| Apr 15, 2022 | A00005 | $23.1K | NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00009, SD026 RELOCATE REMOTE ANNUNCIATOR- PCO016, SD027 RVSD ELCTRCL FEED TO B.3 PCO017, SD028 POWER TO ENTRY GATES - PCO031. PRICE IS INCREASED BY $23,121.04. COMPLETION DATE REMAINS UNCHANGED. |
| Apr 8, 2022 | A00004 | $13.5K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00010, SD025 ADD EXPANSION JOINTS. TOTAL CONTRACT PRICE IS INCREASED BY $13,480. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Feb 10, 2022 | A00003 | $156.2K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00008. SD018 ADDITIONAL DATA PORTS. SD019 ADD SECURITY MESH. TOTAL CONTRACT PRICE IS INCREASED BY $156,194. CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Feb 9, 2022 | A00002 | $240.9K | CONTRACT FOR NEW BROWN FIELD BORDER PATROL STATION. REFERENCE NO. R00002 SD009 FOUNDATION RE-DESIGN. TOTAL CONTRACT INCRESED BY $240,918.00. THE CONTRACT COMPLETION DATE SHALL TO BE EXTENDED BY 39 CD. |
| Dec 1, 2021 | A00001 | $243.5K | REFERENCE NO. R00001 SD004 PEMB REVISED DESIGN PARAMETER. TOTAL CONTRACT PRICE IS INCREASED BY $243,500.00. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 40 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Sep 17, 2021 | P00002 | $750.9K | MAIN BUILDING FACILITY |
| Jul 31, 2020 | P00001 | $4.3M | BROWNFIELD BORDER PATROL STATION CONSTRUCTION |
| Apr 2, 2020 | 0 | $38.2M | CONSTRUCTION OF THE NEW BROWNFIELD BORDER PATROL STATION. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.