Federal contract award

W912PL22C0014

DESIGN AND CONSTRUCT A 1,519 SM (16,352 SF) SINGLE STORY STAGE PROCESSING FACILITY AT NORTH BASE, VANDENBERG SFB TO SUPPORT GROUND BASED STRATEGIC DETERRENT (GBSD) TEST OPERATIONS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST LOS ANGELES
NAICS236220 — Commercial and Institutional Building Construction
PSCY1BF — CONSTRUCTION OF MISSILE SYSTEM FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$13.9M
Current contract value$13.9M
Potential contract value / ceiling$13.9M
Start dateMay 10, 2022
Current end dateSep 30, 2025
Potential end dateSep 30, 2025
Latest award activityMar 20, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 20, 2026P00001$0IN ACCORDANCE WITH FAR 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS, ADMINISTRATIVE MODIFICATION IS BEING ISSUED TO CORRECT THE PAYMENT TERMS FROM 30 DAYS TO 14 DAYS.
Jan 29, 2026A00012$198.1KINCREASE PCC PAVEMENT THICKNESS 4-INCHES TOTAL CONTRACT PRICE INCREASED BY $198,116.44. COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jun 23, 2025A00011$0WC013 TITLE: 149-CALENDAR DAY NO COST TIME EXT ADD 149-CALENDAR DAY TIME EXTENSION AT NO COST TO THE GOVERNMENT. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE COMPLETION DATE SHALL BE EXTENDED BY 149 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Jun 4, 2025A00010$-139.0KCONTRACT NO. W912PL22C0014 B6825 SPF MILCON-SENTINEL- (PVWC) MODIFICATION NO. R00011 - MOD DESCOPE SITE WATER UTILITY LINES. TOTAL CONTRACT PRICE DECREASED BY $138,974.87. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Feb 20, 2025A00009$32.9KADD $32,865. CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY AT VANDENBERG SFB REFERENCE NO. R00009TOTAL CONTRACT PRICE IS INCREASED BY $32,865.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Feb 19, 2025A00008$0R00010 WC012 FOR SEWER HOLDING TANK +75-CALENDAR DAYS AT NO COST TO THE GOVERNMENT NOT INCLUDED IN WC008/R00008. TOTAL CONTRACT PRICE IS UNCHANGED. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 75 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Feb 10, 2025A00007$77.4KTRANSITION TO SEWER HOLDING TANK CONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY GBSD SPF, VSFB R00008. TOTAL CONTRACT PRICE IS INCREASED BY $77,426.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Dec 23, 2024A00006$0MOD ADD 53-CD NO COST EXTENSION (TIA-05) CONTRACT FOR FY22 GBSD AT VANDENBERG REFERENCE NO. R00007 TOTAL CONTRACT PRICE IS UNCHANGED.THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 53 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Oct 24, 2024A00005$115.3KCONTRACT FOR FY22 GBSD STAGE PROCESSING FACILITY AT VANDENBERG SFB, CA. REFERENCE NO. R00006, WC004 STORMWATER RETENTION BASIN REDESIGN. CONTRACT PRICE IS INCREASED BY $115,297.21. THE COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.