Federal contract award
W912PL22F0118
BLDG 1100 RENOVATION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | W912PL22D0042 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.2M |
| Current contract value | $2.2M |
| Potential contract value / ceiling | $2.2M |
| Start date | Sep 30, 2022 |
| Current end date | Sep 15, 2025 |
| Potential end date | Sep 15, 2025 |
| Latest award activity | Sep 29, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 15 of 15 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 29, 2025 | A00014 | $0 | CONTRACT F OR NSWC-C-B 544 1103 1104 +PDS , PROJECT ALPHA REFERENCE NO. R00014. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 24 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Jun 18, 2025 | A00013 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS, PROJECT ALPHA NO R00013 WN023 TIME EXT RETURN AIR DUCTS INSTALLATION. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 21 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| May 29, 2025 | A00012 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS, PROJECT ALPHA. REF NO. R00012. TOTAL CONTRACT PRICE REMAINS UNCHANGED. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 120 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Feb 26, 2025 | A00011 | $0 | TIME EXTENSION FOR SOUND PANNELS CONTRACT FOR NSWC-C-B 544 ALPHA REFERENCE NO. R00011 WN019 TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 43 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Dec 18, 2024 | A00010 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS, PROJECT ALPHA. REFERENCE NO. R00010 WN018 TIME EXTENSION FOR CASEWORK DELAY. TOTAL CONTRACT PRICE IS UNCHANGED. THE COMPLETION DATE SHALL BE EXTENDED BY 18 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Dec 4, 2024 | A00009 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS, PROJECT ALPHA. REFERENCE NO. R00009 WN017 TIME EXTENSION FOR STEEL DOOR DEFECT. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 21 CD DAYS BY REASON OF THIS MODIFICATION. |
| Oct 25, 2024 | A00008 | $2.6K | EXISTING 2" DRAIN PIPE CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS , PROJECT ALPHA. NO. R00008 WN014 RELOCATE EXISTING 2" DRAIN PIPE. TOTAL CONTRACT PRICE IS INCREASED BY $2,647.00. CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jul 18, 2024 | A00007 | $91.5K | TELECOM BACKBONE CONNECTION TO 1202 CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS, ALPHA. REFERENCE NO. R00007 WN005, WN006, WN012 TOTAL CONTRACT PRICE IS INCREASED BY $91,540.75. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jun 12, 2024 | A00006 | $147.8K | CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS , PROJECT ALPHA. REF NO. R00006 WN010 PERIMETER WALL ASSEMBLY UPGRADE. TOTAL CONTRACT PRICE IS INCREASED BY $147,786.00. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 15 CALENDAR DAYS BY REASON OF THIS MOD. |
| Apr 17, 2024 | A00005 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 ALPHA +PDS, PROJECT ALPHA. REF NO. R00005 WN011 TIME EXTENSION FOR DELAYS. TOTAL CONTRACT PRICE IS UNCHANGED. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 193 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Feb 1, 2024 | A00004 | $80.7K | CONTRACT FOR NSWC-C-B 544 1103 1104 + PDS,PROJECT ALPHA. REFERENCE NO. R00004 WN002 ENTRY DOOR, TEMPEST UPGRADE. TOTAL CONTRACT PRICE IS INCREASED BY $80,745.59. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 7 CALENDAR DAYS. |
| Jan 24, 2024 | A00003 | $70.5K | CONTRACT OR NSWC-C-B 544 1103 1104 + PDS, PROJECT ALPHA. REFERENCE NO. R00002 WN008 PDS CABLING AND TERMINATION. TOTAL CONTRACT PRICE IS INCREASED BY $70,452.53. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Dec 21, 2023 | A00002 | $0 | TIME EXTENSION FOR DESIGN CONTRACT FOR NSWC-C-B 544 1103 1104 +PDS , PROJECT ALPHA. R00003 WN007 TIME EXTENSION FOR DESIGN. TOTAL CONTRACT PRICE IS UNCHANGED. COMPLETION DATE SHALL BE EXTENDED BY 150 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Apr 13, 2023 | A00001 | $0 | CONTRACT FOR NSWC-C-B 544 1103 1104 SCI + PDS , PROJECT ALPHA REFERENACE N0. R00001 TIME EXTENSION FOR CERTIFCATION. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 150 CALENDAR DAYS BY REASON OF THIS MODIFICATION |
| Sep 30, 2022 | 0 | $1.8M | BLDG 1100 RENOVATION |