Federal contract award
W912PL23C0008
CONSTRUCT SOUTH WILMOT GATE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $15.7M |
| Current contract value | $15.7M |
| Potential contract value / ceiling | $16.6M |
| Start date | Jun 11, 2023 |
| Current end date | May 29, 2026 |
| Potential end date | May 29, 2026 |
| Latest award activity | Apr 24, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 12 of 12 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 24, 2026 | A00011 | $52.2K | CONTRACT NO. W912PL23C0008 SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, DAVIS MONTHAN AFB MODIFICATION NO. A00012 R00011 - AD013 SECURITY FENCING. THE CONTRACT AMOUNT INCREASES $52,241. THE CONTRACT COMPLETION DATE IS EXTENDED 49 CALENDAR DAYS. |
| Mar 6, 2026 | A00010 | $0 | CONTRACT NO. W912PL23C0008 SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, DAVIS MONTHAN AFB MODIFICATION NO. A00011 R00010 - AD011 WATER DRAINAGE SOUTH GATE; AD012 DELETE SHADE SCREEN. THE CONTRACT AMOUNT REMAINS UNCHANGED. THE CCD IS EXTENDED 23 CD. |
| Oct 19, 2025 | A00009 | $72.1K | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, AT DAVIS MONTHAN AFB. REFERENCE NO. R00009 AD010 PME9 RELOCATION. THE CONTRACT AMOUNT IS INCREASED $72,097. THE CONTRACT COMPLETION DATE REMAINS UNCHANGED BY REASON OF THIS MODIFICATION. |
| Jul 8, 2025 | A00008 | $125.6K | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, 29 BRAVO AT DAVIS MONTHAN AFB. REF NO. R00006 AD005 TEMPORARY POWER. THE CONTRACT AMOUNT IS INCREASED $125,606. THE CONTRACT COMPLETION DATE REMAINS UNCHANGED BY REASON OF THIS MODIFICATION. |
| Jun 24, 2025 | A00007 | $146.5K | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, AT DAVIS MONTHAN AFB. REF NO. R00008 AD009 VEHICLE BARRIER. THE CONTRACT AMOUNT IS INCREASED $146,535. THE CONTRACT COMPLETION DATE IS EXTENDED 225 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| May 2, 2025 | A00006 | $43.4K | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX, DAVIS MONTHAN AFB. REF NO. R00007 AD008 TEMP SECURITY FENCING @ PERIMETER GATE. THE CONTRACT AMOUNT IS INCREASED $43,409.67. THE CONTRACT COMPLETION DATE REMAINS UNCHANGED BY REASON OF THIS MOD. |
| Feb 25, 2025 | A00005 | $-61.5K | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, DAVIS MONTHAN AFB, REF NO. R00005/AD006 SWG FENCE SLATS DELETION. THE CONTRACT AMOUNT IS DECREASED $61,462.84. THE CONTRACT COMPLETION DATE REMAINS UNCHANGED BY REASON OF THIS MODIFICATION. |
| Jan 7, 2025 | A00004 | $0 | CONTRACT FOR SOUTH WILMOT ROAD ENTRANCE COMPLEX, AT DAVIS MONTHAN AFB. REF NO. R00003 AD003 ROUNDABOUT & MISC CHANGES. THE CONTRACT AMOUNT REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE IS EXTENDED 185 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Aug 29, 2024 | A00003 | $0 | CONTRACT FOR S WILMOT ROAD ENTRANCE COMPLEX DMAFB, 29 BRAVO AT DMAFB. REF NO. R00003 AD003 ROUNDABOUT & MISC CHANGES. THE CONTRACT AMOUNT REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE IS EXTENDED 185 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Jul 23, 2024 | A00002 | $-67.8K | SOUTH WILMOT ROAD ENTRANCE COMPLEX DMAFB, 29 BRAVO AT DAVIS MONTHAN AFB. REF NO. R00002 AD002 DELETE LIGHTNING PROTECTION SYS. THE CONTRACT AMOUNT IS DECREASED $67,762.74. THE CONTRACT COMPLETION DATE REMAINS UNCHANGED BY REASON OF THIS MODIFICATION. |
| Feb 2, 2024 | A00001 | $16.9K | CONTRACT FOR JITC LABOY BLDG, FT. HUACHUCA, AZ. REFERENCE NO. R000018/AH012 ADDED FIBER AND COPPER INFRASTRUCTURE. THE CONTRACT AMOUNT IS INCREASED $266,664. THE CONTRACT COMPLETION DATE IS EXTENDED 13 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Jun 1, 2023 | 0 | $15.3M | CONSTRUCT SOUTH WILMOT GATE |