Federal contract award

W912PL23C0022

B531 INTERIOR RENOVATIONS

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST LOS ANGELES
NAICS236220 — Commercial and Institutional Building Construction
PSCZ1BZ — MAINTENANCE OF OTHER AIRFIELD STRUCTURES
Parent award / vehicleNot reported
Set-asideSERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$7.0M
Current contract value$7.0M
Potential contract value / ceiling$7.0M
Start dateSep 26, 2023
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityFeb 5, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 5, 2026A00004$0CONTRACT FOR BLDG 531 INTERIOR REPAIRS AT PLANT 42, PALMDALE, CA. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 212 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Sep 26, 2025A00003$256.1KCONTRACT FOR BUILDING 531 INTERIOR REPAIRS. REFERENCE NO. R00003, WL002 CONCRETE REPAIRS, WEATHERPROOFING, AND TRENCHING/PATCHING FOR SCE. CONTRACT PRICE IS INCREASED BY $256,142.85. CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED.
Sep 18, 2025A00002$59.4KBLDG 531 INTERIOR REPAIRS AT PLANT 42, PALMDALE, CA, REF NO. R00002, CHANGE: WL003 TITLE: SCE DESIGN FEES. TOTAL CONTRACT PRICE INCREASED BY $59,435.95. CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 168 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Feb 13, 2025A00001$137.9KCONTRACT FOR BUILDING 531 INTERIOR REPAIRS. REFERENCE NO. R00001, WL001 VARIOUS CHANGES. TOTAL CONTRACT PRICE IS INCREASED BY $137,930.84. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 180 CALENDAR DAYS BY REASON OF THIS MODIFICATION.