Federal contract award

W912PL24C0013

VALB PH-D 39CA PARKING GARAGE (31)

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST LOS ANGELES
NAICS236220 — Commercial and Institutional Building Construction
PSCY1LZ — CONSTRUCTION OF PARKING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$32.0M
Current contract value$32.0M
Potential contract value / ceiling$32.0M
Start dateApr 29, 2024
Current end dateJun 28, 2026
Potential end dateJun 28, 2026
Latest award activityJun 10, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 10, 2026A00006$95.0KPS014 - TELECOMM CONNECTION TO B25 (SHACK)
Mar 10, 2026P00002$4.5MACM SOIL ABATEMENT (NORTH PILE) 110 CD $4,501,303.00
Feb 4, 2026A00005$0CONTRACT FOR W192PL24C0013 CONSTRUCTION OF NEW PARKING STRUCTURE AT VETERANS ADMINISTRATION MEDICAL CENTER. R00006/PS027 TIME EXTENSION +30 CD. TOTAL CONTRACT PRICE IS INCREASED BY $0.00. THE CONTRACT COMPLETION DATE FROM FEB 8, 2026 TO MAR 10, 2026.
Sep 8, 2025P00001$1.8MCONTRACT FOR PARKING STRUCTURE, VALB. R0005/PS001 BULLETIN 01. TOTAL CONTRACT PRICE IS INCREASED $1,820,654.00. EXTEND THE POP AN ADDITIONAL 83-CALENDAR DAYS CHANGING THE CONTRACT COMPLETION DATE FROM NOVEMBER 17, 2025 TO FEBRUARY 08, 2026
Jul 8, 2025A00004$155.0KW192PL24C0013 CNSTRCTN OF NEW PRKG STRUCTURE AT VALB. R00004/PS009 CONDT PB/PS010 TYPE 12A LIGHT FIXT/PS011 RAMP IMPRT MATRLS/PS012 2 ADD'T TELEC CONDT. TOTAL CONTRACT PRICE IS INCR BY $154,974. THE CONTRACT COMPL DATE SHALL REMAIN UNCHGD.
Jun 11, 2025A00003$145.5KCONTRACT FOR W192PL24C0013FOR CONSTRUCTION OF NEW PARKING STRUCTURE AT VA MC. R00003/PS006 COR021 SOIL IMPORT AREA C ONLY. TOTAL CONTRACT PRICE IS INCREASED BY $145,506.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MOD.
Jun 4, 2025A00002$230.7KCONTRACT FOR W192PL24C0013 FOR CONSTRUCTION OF NEW PARKING STRUCTURE AT VA MC. R00002/PS002 ERRCS REQUIREMENT & PS003 DEMO EXISTING UG CONCRETE. TOTAL CONTRACT PRICE IS INCR BY $230,724.00. THE CONTRACT COMPL DATE SHALL REMAIN UNCHANGED BY THIS MOD.
Apr 16, 2025A00001$500.0KCONTRACT FOR W192PL24C0013 FOR CONSTRUCTION OF NEW PARKING STRUCTURE AT VA MEDICAL CENTER. R00001/PS003 COR019 ACM SOIL ABATEMENT. TOTAL CONTRACT PRICE IS INCREASED BY $499,981.00. THE CONTRACT COMPL DATE SHALL REMAIN UNCHANGED BY THIS MOD.
Apr 18, 20240$23.5MVALB PH-D 39CA PARKING GARAGE (31)

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.