Federal contract award
W912PL24C0018
GRIC PIMA-MARICOPA ENERGY PROJECT AT MARICOPA COUNTY ARIZONA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 238210 — Electrical Contractors and Other Wiring Installation Contractors |
| PSC | Y1MG — CONSTRUCTION OF EPG FACILITIES - SOLAR |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $5.9M |
| Current contract value | $5.9M |
| Potential contract value / ceiling | $5.9M |
| Start date | Sep 12, 2024 |
| Current end date | Jan 30, 2026 |
| Potential end date | Jan 30, 2026 |
| Latest award activity | Sep 29, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 29, 2025 | A00003 | $-1.1K | CONTRACT W912PL-24-C-0018 GRIC PIMA MARICOPA ENERGY PROJECT. REFERENCE R00004 AL004 CREDIT FOR FOUR SOLAR PANELS. THE CONTRACT AMOUNT IS DECREASED $1,084. THE CONTRACT COMPLETION DATE IS UNCHANGED BY REASON OF THIS MODIFICATION. |
| Sep 15, 2025 | A00002 | $21.5K | CONTRACT W912PL24C0018, GRIC PIMA-MARICOPA ENERGY PROJECT REFERENCE: R00003 (AL003 - INVERTER FRAME STABILIZER). THE CONTRACT AMOUNT IS INCREASED $21,548.00. THE CONTRACTOR COMPLETION DATE IS UNCHANGED BY REASON OF THIS MODIFICATION. |
| May 13, 2025 | P00001 | $0 | ADMINISTRATIVE MODIFICATION TO IMPLEMENT EXECUTIVE ORDER 14173 AND CHANGE PROJECT TITLE. |
| Dec 17, 2024 | A00001 | $0 | CONTRACT FOR PIMA-MARICOPA IRRIGATION ENERGY PROJECT AT MARICOPA COUNTY, AZ. REFERENCE NO. R00001 AL001 ADDENDUM NO 1- SHEET S-7. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |