Federal contract award
W912PL24C0021
B1819 ADMIN RENOVATION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2EZ — REPAIR OR ALTERATION OF OTHER INDUSTRIAL BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | 8(A) SOLE SOURCE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $4.7M |
| Current contract value | $4.7M |
| Potential contract value / ceiling | $4.7M |
| Start date | Oct 1, 2024 |
| Current end date | Aug 10, 2026 |
| Potential end date | Aug 10, 2026 |
| Latest award activity | Apr 23, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 23, 2026 | A00010 | $10.2K | CONTRACT FOR B1819 ADMIN RENO-MDA. REFERENCE NO. R00010. TOTAL CONTRACT PRICE INCREASED BY $10,177.78.THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY REASON OF THIS MODIFICATION. |
| Apr 8, 2026 | A00009 | $0 | CONTRACT FOR B1819 ADMIN RENO-MDA. REFERENCE NO. R00009 ADD 120 CALENDAR DAYS, THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 120 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Mar 10, 2026 | A00008 | $58.3K | CONTRACT FOR B1819 ADMIN RENO-MDA. REFERENCE NO. R00008 EXTEND WALLS AND PROVIDE POWER TO VAVS. TOTAL CONTRACT PRICE INCREASED BY $58,267.59. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 12 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Jan 29, 2026 | A00007 | $0 | 59 DAY NO COST TIME EXTENSION CONTRACT FOR B1819 ADMIN RENO MDA (MX) AT VANDENBERG SFB, CA REFERENCE NO. R00007 TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 59 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Sep 10, 2025 | A00006 | $0 | CONTRACT FOR B1819 ADMIN RENO MDA (MX) AT VANDENBERG SFB, CA WC007 TITLE: 113 DAY NO COST TIME EXTENSION ADD ONE HUNDRED-THIRTEEN (113) CALENDAR DAYS AT NO COST TO THE GOVERNMENT. |
| Apr 28, 2025 | A00005 | $21.3K | PROVIDE PS200 GALVANIZED UNISTRUT BEAM CLAMPS, AND 12-GA HANGAR WIRES AT 48-INCHES ON CENTER BETWEEN EXISTING I-BEAMS TO SUSPEND NEW T-BAR CEILING SYSTEM. CONTRACT PRICE INCREASED BY $21,323.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED. |
| Apr 16, 2025 | A00004 | $12.9K | W912PL24C0021 B1819 ADMIN RENO-MDA (MX) MODIFICATION NO. R00004 - FURR OUT CMU WALLS ROOMS 102,103,105. TOTAL CONTRACT PRICE INCREASED BY $12,941.06.THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Apr 14, 2025 | A00003 | $22.3K | B1819 ADMIN RENOVATION W912PL24C0021 B1819 ADMIN RENO-MDA (MX) MODIFICATION NO. R00003 - INFILL 2ND FLOOR HVAC DUCT PENETRATIONS. TOTAL CONTRACT PRICE INCREASED BY $22,330.93. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Mar 20, 2025 | A00002 | $-6.5K | PROVIDE A CREDIT FOR CHANGING THE DRYWALL FINISHES REQUIRED IN SPECIFICATION SECTION 09 29 00, PARAGRAPH 3.3, FROM A LEVEL 5 FINISH TO A LEVEL 3 FINISH. PRICE IS DECREASED BY $6,481.72. CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MOD. |
| Feb 25, 2025 | A00001 | $142.3K | CONTRACT FOR B1819 ADMIN RENO MDA (MX) AT VANDENBERG SFB, CA REFERENCE NO. R00001 WC002 LOBBY AND CORRIDOR TOTAL CONTRACT PRICE IS INCREASED BY $142,276.97. CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION |
| Aug 27, 2024 | 0 | $4.4M | B1819 ADMIN RENOVATION |