Federal contract award
W912PL24F0032
POCA TO FED-VET JV
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST LOS ANGELES |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | W912PL24D0027 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $834.2K |
| Current contract value | $834.2K |
| Potential contract value / ceiling | $834.2K |
| Start date | Jul 18, 2024 |
| Current end date | Mar 15, 2025 |
| Potential end date | Mar 15, 2025 |
| Latest award activity | Jan 14, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jan 14, 2025 | A00005 | $57.9K | CONTRACT F OR RELOCATE ATCALS TOW ERS BLDG 1212 AT MARCH ARB. REFERENCE NO. R00005.SM004 BLDG 1210 ELECTRICAL MODIFICATIONS. TOTAL CONTRACT PRICE IS INCREASED BY $57,946.82. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 60 CALENDAR DAYS. |
| Dec 30, 2024 | A00004 | $0 | CONTRACT NO. W912PL24D0027 W912PL24F0032 RELOCATE ATCALS TOWERS BLDG 1212 MODIFICATION NO. R00004 - TIME EXTENSION FOR FUNDING DELAYS. A (45) CALENDAR DAY NON-COMPENSATORY TIME EXTENSION WAS REQUESTED FOR FUNDING DELAYS. |
| Dec 4, 2024 | A00003 | $0 | TIME EXTENSION FOR USER DELAYS CONTRACT FOR REFERENCE NO. R00003 SM008 TIME EXTENSION FOR USER DELAYS. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 15 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Oct 25, 2024 | A00002 | $0 | TIME EXTENSION FOR RELOCATE ATCALS TOWERS. NO. R00002 SM005 FOR PFAS DELAYS. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 38 CALENDAR DAYS. * CORRECTION OF PERIOD OF PERFORMANCE IN PD2 INCLUDE IN MODIFICATION. |