Federal contract award

W912PL24F0032

POCA TO FED-VET JV

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST LOS ANGELES
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleW912PL24D0027
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$834.2K
Current contract value$834.2K
Potential contract value / ceiling$834.2K
Start dateJul 18, 2024
Current end dateMar 15, 2025
Potential end dateMar 15, 2025
Latest award activityJan 14, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jan 14, 2025A00005$57.9KCONTRACT F OR RELOCATE ATCALS TOW ERS BLDG 1212 AT MARCH ARB. REFERENCE NO. R00005.SM004 BLDG 1210 ELECTRICAL MODIFICATIONS. TOTAL CONTRACT PRICE IS INCREASED BY $57,946.82. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 60 CALENDAR DAYS.
Dec 30, 2024A00004$0CONTRACT NO. W912PL24D0027 W912PL24F0032 RELOCATE ATCALS TOWERS BLDG 1212 MODIFICATION NO. R00004 - TIME EXTENSION FOR FUNDING DELAYS. A (45) CALENDAR DAY NON-COMPENSATORY TIME EXTENSION WAS REQUESTED FOR FUNDING DELAYS.
Dec 4, 2024A00003$0TIME EXTENSION FOR USER DELAYS CONTRACT FOR REFERENCE NO. R00003 SM008 TIME EXTENSION FOR USER DELAYS. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 15 CALENDAR DAYS BY REASON OF THIS MODIFICATION.
Oct 25, 2024A00002$0TIME EXTENSION FOR RELOCATE ATCALS TOWERS. NO. R00002 SM005 FOR PFAS DELAYS. TOTAL CONTRACT PRICE IS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 38 CALENDAR DAYS. * CORRECTION OF PERIOD OF PERFORMANCE IN PD2 INCLUDE IN MODIFICATION.