FY19 DANGEROUS CARGO PAD AND COMBAT ARMS TRAINING MAINTENANCE (CATM) FACILITY, CANNON AFB, NM
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST ALBUQUERQUE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1BD — CONSTRUCTION OF AIRPORT RUNWAYS AND TAXIWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $51.5M |
| Current contract value | $51.5M |
| Potential contract value / ceiling | $54.9M |
| Start date | Aug 1, 2022 |
| Current end date | Dec 31, 2025 |
| Potential end date | Dec 31, 2025 |
| Latest award activity | Jul 23, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 23, 2025 | A00034 | $43.1K | A00034 C-080 SUSPENSION IMPACTS TOTAL COST OF CATM FACILITY, COMPLETE |
| Jul 22, 2025 | A00033 | $48.9K | A00033 C-079 DCP STRIPING CHANGES TOTAL COST OF CATM FACILITY, COMPLETE |
| Jul 21, 2025 | A00032 | $156.6K | A000032 C-070 ADD INTERCOM SYSTEM IN CATM TOTAL COST OF CATM FACILITY, COMPLETE |
| Jul 21, 2025 | P00004 | $547.6K | P00004 C-077 ADD BARRICADES/MOVE FIRING LINE TOTAL COST OF CATM FACILITY, COMPLETE |
| Jul 18, 2025 | A00031 | $353.9K | A00031 C-033 REVISED-EM TELEPHONE/HH405/TRANSFORMER TOTAL COST OF CATM FACILITY, COMPLETE |
| May 8, 2025 | A00030 | $56.0K | A00030 C-078 REPLACE 4 RUNWAY GUARD LIGHTS & CABLE TOTAL COST OF CATM FACILITY, COMPLETE |
| Feb 3, 2025 | A00029 | $15.4K | A00029, C-073 ROOM 112 NOISE REDUCTION, C-074 DELETE SMOOTHNESS TEST C-075 SHOOTING RANGE AIRFLOW RE-TEST, C-076 LIVE FIRE TESTING TOTAL COST OF CATM FACILITY, COMPLETE |
| Dec 18, 2024 | A00027 | $184.6K | A00027 C-067 EF-110 AIR FLOW RFI-266 TOTAL COST OF CATM FACILITY, COMPLETE |
| Dec 17, 2024 | A00028 | $20.2K | DANGEROUS CARGO PAD AND CATM C-071 CATM WATER TANK HEAT TAPE C-072 CATM SIDEWALK ELEVATION CHANGE |
| Nov 1, 2024 | A00026 | $67.5K | A00026, C-030 FLAGPOLE CHANGE, C-056 ADD ABC BELOW PCC LINED DITCH C-059 VAULT WIRE MESH PARTITION, C-065 WAREHOUSE RADIANT HEATER CHANGE, C-068 PARKING LOT PAY FACTOR CREDIT C-066 CATM ADD BOILER BYPASS TOTAL COST OF CATM FACILITY, COMPLETE |
| Oct 28, 2024 | A00025 | $0 | A00025, C-069 WEATHER TIME EXTENSION FEB 24 - SEP 24 TOTAL COST OF CATM FACILITY, COMPLETE |