Federal contract award

W912QR21C0025

AWARD OF BASE AND OPTIONS 1A EAST SHOP SHELL, OPTION 2A WEST SHOP SHELL, AND OPTION 5 INSULATED METAL PANELS FOR REGIONAL C-5 ISOCHRONAL HANGAR AT WESTOVER AIR RESERVE BASE. PERIOD OF PERFORMANCE IS 730 DAYS FROM NTP.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST LOUISVILLE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$50.8M
Current contract value$50.8M
Potential contract value / ceiling$53.8M
Start dateJun 17, 2021
Current end dateMay 13, 2024
Potential end dateMay 13, 2024
Latest award activityApr 6, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 6, 2026A00022$734.8KA. SCOPE OF WORK REA DUE TO THE UNILATERAL MOD A00016 TO ADD THE INFRARED FLAME DETECTORS AND ASSOCIATED PANELS AS NOTED ON SHEETS FA001, FA101, FA501, FA601, FA602, AND FA603.
Dec 2, 2025A00021$5.0KCR: 00030 WINDOW TRIM
Oct 24, 2025A00020$61.7KCR: 00026 MISC. STEEL CONNECTIONS
Aug 11, 2025A00019$37.6KCR 0029 INSTALL CLIPS AT SNOW RETENTION SYSTEM
Jul 16, 2025A00018$55.8KCR 0027 MISC ELECTRICAL & MECHANICAL CHANGES- CREDIT FOR INSTALLATION OF FABRIC LINER, PROVIDE A ADA SINK, PROVIDE POWER FOR OIL WATER SEPARATOR, INCREASE CONDUIT
Jun 18, 2025A00017$23.7KCR 018-5 CLOSEOUT NTES JC0018-1 AND JC0018-2
Feb 6, 2025A00016$95.2KCR 0028 ADD IR FLAME DETECTORS
Nov 19, 2024P00009$0CR 0025 CLOSING STATEMENT CORRECTION TO A 00015 BASE 0001 - FUNDING ONLY FY 19

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.