Federal contract award

W912QR21C0033

AWARD OF THE BASE PLUS ALL OPTIONS FOR THE CONSTRUCTION OF VAN VOORHIS ELEMENTARY SCHOOL - $58,989,000.00.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST LOUISVILLE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1CA — CONSTRUCTION OF SCHOOLS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$62.4M
Current contract value$62.4M
Potential contract value / ceiling$62.4M
Start dateAug 12, 2021
Current end dateJan 22, 2026
Potential end dateJan 22, 2026
Latest award activityApr 13, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 41 of 41 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 13, 2026A00037$1.7KCASE 0055
Mar 12, 2026A00036$7.8KCASE 0053 AND 0054
Nov 3, 2025A00035$49.5KCHANGE REQUEST 0050, ADD PRV TO INCOMING DOMESTIC W ATER
Oct 22, 2025A00034$62.5KADD SIDEWALK AND FENCES
Sep 24, 2025A00033$-3.0KCHANGE REQUEST 0051, PHASE 4 CHANGES 2
Sep 19, 2025A00032$17.9KCHANGE REQUEST 00049, NEW HEAT TRACE
Aug 25, 2025A00031$296.4KCHANGE REQUEST 0046 PRE K PLAYGROUND REDESIGN VVES GYM FLOOR
May 30, 2025A00030$276.9KCR 0043 ADD SWINGSET-RELOCATE PLAYGROUND
May 15, 2025A00029$58.3KCHANGE REQUEST 0048, PHASE 4 CHANGES
Apr 22, 2025A00028$93.6KCHANGE REQUEST 0042, DISHW ASHER
Mar 5, 2025A00027$29.7KCHANGE REQUEST 0045 DOOR HARDW ARE CHANGES DUCT REMOVAL CHANGE REQUEST 0047 REVISE POW ER HEATED REACH-IN CABINET WARMER
Dec 6, 2024A00026$184.4KCR 040 VARIOUS PHASE 2 COSTS #2- MUSIC ROOM DOOR REWORK, CHANGE BUILDING NUMBERS, SITE WORK FOR EMERG EGRESS PATH, RFI 397, 398, ADD DATA DROP
Oct 30, 2024A00025$87.5KCR 0041 VARIOUS PHASE 2 COSTS - CHANGE TO 20 AMP, SIGNAGE CHANGE, KILN AND VENT WORK, PROJECTOR SCREEN, ADD 30 AMP RECEPTABLES
Sep 18, 2024A00024$150.7KCR 0040 ADDITIONAL ABATEMENT - VVES GYM FLOOR VAN VOORHIS ELEMENTARY SCHOOL, FT. KNOX
Aug 20, 2024A00023$94.0KCHANGE REQUEST 0038 HARDW ARE CHANGE REQUEST 0039 WINDOW DISTORTION REA
Jul 23, 2024A00022$88.7KCR 0034 DESIGN CHANGE #9 CR 0035 DESIGN CHANGE #10 CR 0036 DESIGN CHANGE #11
May 28, 2024A00021$152.8KCHANGE REQUEST 0030, ASI 003 CHANGE REQUEST 0031, DESIGN CHANGE #7 CHANGE REQUEST 0032, DESIGN CHANGE #8
May 2, 2024A00020$70.5KCR 0037 TELECOM INFRASTRUCTURE PROCURE AND PULL REQUIRED FIBER
Mar 21, 2024A00019$51.6K0023 DESIGN CHANGE CREDITS 1 0026 RFI 291 CANOPY DETAILS 0029 DESIGN CHANGE CREDIT 2
Feb 1, 2024A00018$58.2KCHANGE REQUEST 0022 DESIGN CHANGES 6
Dec 22, 2023A00017$331.1KCR 0025 ASI002
May 18, 2023A00016$133.3KCR 0019 DESIGN CHANGE 5 VAN VOORHIS ELEMENTARY SCHOOL FORT KNOX KY
Apr 27, 2023A00015$21.0KCR 0016 DESIGN CHANGES #4
Apr 12, 2023A00014$0CR 0024 WEATHER TIME EXTENSION JUL 22-FEB 23 18 CAL DAYS FOR ADVERSE WEATHER
Mar 30, 2023A00013$322.3KBASE CONSTRUCTION
Jan 31, 2023A00012$-8.4KCR 006 DESIGN CHANGES 2 - ADD DRAIN LINES, FIRE RATED FUSIBLE LINKS, BOX OVER SPRINKLER PIPE VOID FORMS NO LONGER REQUIRED
Jan 20, 2023A00011$448.0KCR 0021 ADDITIONAL ROCK DRILLING
Dec 28, 2022A00010$50.0KBASE CONSTRUCTION
Dec 22, 2022A00009$50.4KCR 0013 DESIGN CHANGES #3 - INSTALL GAS METER, RADON REQUIREMENTS, SLEEVE GAS LINE
Dec 13, 2022A00008$35.8KCR 0012 USER REQUESTED CHANGES # 1 - TELECOM CHANGES AND DISHWASHER CR 0018 USER REQUESTED CHANGES - DOOR HARDWARE
Nov 12, 2022A00007$36.4KCR 0005 LOWER EXISTING COPPER LINE FT VAN VOORHIS ELEMENTARY SCHOOL
Aug 25, 2022A00006$0CR 0017 WEATHER TIME EXTENSION APR 22-JUN 22 VAN VOORHIS ELEMENTARY SCHOOL
Aug 24, 2022A00005$9.1KCR 0011 ADDITIONAL STEEL FOR BLAST DESIGN, DESIGN COST FOR DESIGN STEEL
Jul 25, 2022A00004$44.7KCASE 0003 EXISTING WATERLINE RELOCATION FORT KNOX KY
Jul 18, 2022P00003$0ADDITION OF FAR CLAUSES 52.211-14 & 52.211-15 TO THE VAN VOORHIS ES
Jul 11, 2022A00003$119.1KCASE 002, CASE 004, CASE 009, CASE 0010 VAN VOORHIS ELEMENTARY SCHOOL, FORT KNOX KY
Jun 29, 2022P00002$0REMOVAL OF FAR CLAUSE 52.229-12 (TAX ON CERTAIN FOREIGN PROCUREMENTS)
Jun 2, 2022A00002$18.7KCR 0007 ADD TERMITE TREATMENT FK VAN VOORHIS ELEMENTARY SCHOOL
May 19, 2022A00001$0CASE 008 WEATHER TIME EXTENSION DEC 21 - MAR 22 BASE CONSTRUCTION
Aug 30, 2021P00001$0BASE CONSTRUCTION NTP.
Aug 11, 20210$59.0MAWARD OF THE BASE PLUS ALL OPTIONS FOR THE CONSTRUCTION OF VAN VOORHIS ELEMENTARY SCHOOL - $58,989,000.00.