Federal contract award
W912QR22C0010
DESIGN/BID/BUILD PROJECT TO REMOVE THE EXISTING STEAM HEATING SYSTEM IN THE WAREHOUSE AREAS OF THE BUILDING 10 AND INSTALL A GAS-FIRED HOT WATER BOILER SYSTEM AT DEFENSE SUPPLY CENTER, COLUMBUS, OH.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W072 ENDIST LOUISVILLE |
| NAICS | 238220 — Plumbing, Heating, and Air-Conditioning Contractors |
| PSC | Z1AZ — MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $3.8M |
| Current contract value | $3.8M |
| Potential contract value / ceiling | $3.8M |
| Start date | Jan 14, 2022 |
| Current end date | May 31, 2026 |
| Potential end date | May 31, 2026 |
| Latest award activity | May 11, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 18 of 18 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 11, 2026 | A00011 | $37.6K | CR 16, REA-MECH. RM. CEILING |
| Apr 29, 2026 | A00010 | $79.0K | CR 13-2, REMOVE TRACED WIRING - FINAL |
| Apr 20, 2026 | A00009 | $19.2K | CR 12-2, TRACE CONTROL WIRING PT. 2 FINAL |
| Apr 9, 2026 | A00008 | $0 | CR 15, TIME EXTENSION |
| Dec 2, 2025 | A00007 | $30.8K | CHANGE REQUEST 0014, ALTERNATE MATERIAL FOR CHEMICAL SHOT FEE |
| Mar 20, 2025 | A00006 | $-3.0K | CR 0010 CREDIT FOR PAINTER SPECIFICATION BLDG 10 DECENTRALIZED BOILER |
| Feb 12, 2025 | P00006 | $14.0K | CR 0013-1 REMOVE TRACED WIRING, PART I NTPBLDG 10 DECENTRALIZED BOILER |
| Dec 20, 2024 | P00005 | $410.5K | CR 003-2 RESEQUENCING OF PHASES, PART II FINAL BLDG 10 DECENTRALIZED BOILER |
| Dec 11, 2024 | P00004 | $26.4K | CR 011 ABANDONED CONDUIT ON WALLS IN MECH ROOM BLDG 10 DECENTRALIZED BOILER |
| Dec 5, 2024 | P00003 | $15.0K | CR 0012-1 TRACING OF EXISTING CONTROL WIRING, PART I NTP BLDG 10 DECENTRALIZED BOILER |
| Sep 18, 2024 | A00005 | $41.4K | CR 0007 LOCATION OF UTILITIES FOR GAS METER BLDG 10 DECENTRALIZED BOILER |
| Jul 1, 2024 | A00004 | $76.3K | CR 006 CONDENSATE PIPING SERVING BLDG 9 BLDG 10 DECENTRALIZED BOILER |
| Jun 24, 2024 | A00003 | $16.3K | CR05 NG PRESSURE & LOAD VERIFICATION |
| Mar 20, 2024 | A00002 | $13.4K | CR 004 BURIED SLAB MECHANICAL ROOM BLDG 10 DECENTRALIZED BOILER |
| Jun 20, 2023 | A00001 | $5.0K | CR 003-1 RESEQUENCING OF PHASES-TIME EXT PART I , NTPBLDG 10 DECENTRALIZED BOILER |
| May 15, 2023 | P00002 | $-117.8K | CR 0002 ACCESS STAIR CHANGE TO ROOF HATCH BLDG 10 DECENTRALIZED BOILER |
| Feb 16, 2022 | P00001 | $0 | ISSUANCE OF NOTICE TO PROCEED |
| Jan 14, 2022 | 0 | $3.1M | DESIGN/BID/BUILD PROJECT TO REMOVE THE EXISTING STEAM HEATING SYSTEM IN THE WAREHOUSE AREAS OF THE BUILDING 10 AND INSTALL A GAS-FIRED HOT WATER BOILER SYSTEM AT DEFENSE SUPPLY CENTER, COLUMBUS, OH. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.