W912QR22C0014

PRIMARY FACILITY - HC-130J HANGAR. THIS FUNDS THE BASE ITEMS AND OPTIONS A, B, C AND D. PERIOD OF PERFORMANCE IS 700 CALENDAR DAYS FROM NTP.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST LOUISVILLE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$29.0M
Current contract value$29.0M
Potential contract value / ceiling$29.1M
Start dateApr 4, 2022
Current end dateMay 18, 2025
Potential end dateMay 18, 2025
Latest award activityMar 11, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 10 of 10 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 11, 2026A00014$4.7KCONSTRUCT GENERAL PURPOSE MAINTENANCE HANGAR TO ACCOMMODATE ONE HC-130J AIRCRAFT AND CORROSION CONTROL, FIBERGLASS/COMPOSITES, WITH CLEAN/DIRTY TRANSITION, METALS TECH, AND STRUCTURES BACK SHOPS WITH THE HANGAR
Oct 24, 2025A00013$693CR: FC017 EMERGENCY EYEWASH/SHOWER RELOCATION
Sep 17, 2025A00012$0CR FC011 WEATHER TIME EXTENSION MAR 22 - JAN 31
Sep 2, 2025A00011$107.4KCR FC10 GFGI EQUIPMENT CHANGES-RPR LIGHTNING PROTEC. CR FC12 INSTALL STRUCTURAL DUCT SUPPORT-PROVIDE FRAMING SUPPORTS CR FC14 FAN COOLING UNIT 08-RELOCATE FCU CR FC16 ADDITIONAL WORK FOR HOSE REEL AND FCU-PROVIDE ADDTL CABINETS FOR POWER FOR REELS
Jul 31, 2025P00005$1.4MCR: FC0006-3 NEW FIRE SERVICE MAINT.
May 13, 2025P00004$0CR FC013 UFGS 32 13 14 SMALL AIRFIELD PAVING SPEC AND CR FC015 FIRE ALARM AND MASS NOTIFICATION SPEC PRIMARY FAC. FUNDING ONLY
Apr 7, 2025A00010$88.0KFC008 PARTIAL MERIT FOR REA 2.0 (DEWATERING)
Feb 20, 2025A00009$290.3KCR FC002-2 AMENDMENT FIVE, PT2 RFI-0002 ANCHOR BOLT DESIGN ISSUES, RFI-0012 ELECTRICAL MANHOLE CLARIFICATION & DISCONNECT AIRPORT LIGHTS, AND RFI-0017 ANCHOR BOLTS AT COLUMNS G/5 AND G/6BASE ITEM- PRIMARY FAC. FUNDING ONLY
Dec 11, 2024A00008$325.5KCR 006-2 UNILATERAL NEW FIRE SERVICE MAIN, PART 2
Nov 19, 2024A00007$499.7KFC009 FOAM DELETION ADDITIONAL DELAY

Research next steps