Federal contract award
W912QR23C0005
FT KNOX TARGET TRAINING STRUCTURE
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W072 ENDIST LOUISVILLE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | C219 — Other Architect and Engineering Services |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $26.6M |
| Current contract value | $26.6M |
| Potential contract value / ceiling | $26.6M |
| Start date | Dec 29, 2022 |
| Current end date | Jul 28, 2025 |
| Potential end date | Jul 28, 2025 |
| Latest award activity | May 26, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 20 of 20 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 26, 2026 | A00018 | $0 | CASE 0019 |
| Jan 27, 2026 | A00017 | $105.1K | CASE 0013-1 |
| Jan 22, 2026 | A00016 | $0 | CASE 0016 |
| Nov 6, 2025 | A00015 | $-2.3K | CR 0012-2 WALL FOOTING ELEVATION ADJUSTMENT, PART II FINAL |
| Oct 23, 2025 | A00014 | $0 | CR 0015 FUNERAL TIME EXTENSION - EXCUSABLE DELAY FOR FUNERAL OF 1 DAY |
| Sep 25, 2025 | A00013 | $0 | CR 0014 WEATHER TIME EXTENSION MAY 25 - AUG 25 - 7 DAYS WEATHER |
| Sep 12, 2025 | A00012 | $100.0K | CR 0012-1 WALL FOOTING ELEVATION ADJUSTMENT, PRT I NTP |
| Jun 6, 2025 | A00011 | $0 | CR 10 WEATHER TIME EXTENSION FEB 25-APR 25 |
| Mar 3, 2025 | A00010 | $0 | WEATHER TIME EXTENSION JUL 2023 JAN 2025 |
| Feb 10, 2025 | A00009 | $249.0K | CHANGE REQUEST 0009, SLUMP LOSS DUE TO PUMPING - REA |
| Dec 11, 2024 | A00008 | $30.0K | CR 008 DSC UNSUITABLE SOILS |
| Feb 20, 2024 | A00007 | $0 | TELECOMMUNICATIONS LINE CHANGES |
| Sep 20, 2023 | A00006 | $0 | CR 0004 TELECOMMUNICATIONS LINE CHANGES FORT KNOX KY |
| Sep 18, 2023 | A00005 | $59.3K | UNSUITABLE SOIL IN DRAW AND CRATER - PART 2 FINAL |
| Sep 6, 2023 | A00004 | $0 | CR 006 WEATHER TIME EXTENSION APR 23 - JUN 23 PRIMARY FACILITIES & SITEWORK |
| Aug 2, 2023 | A00003 | $0 | CHANGE REQUEST 00005-1, STRUCT.AND CU CHANGES - PART 1 NTP |
| Jul 13, 2023 | A00002 | $40.0K | CR 0003 - 1 DSC UNSUITABLE SOIL IN DRAW AND CRATER FORT KNOX KY |
| Jul 10, 2023 | A00001 | $42.7K | PRIMARY FACILITIES & SITEWORK CR 0002 CHANGE HDPE PIPE TO PVC C900 |
| Feb 2, 2023 | P00001 | $0 | ADMINISTRATIVE MOD TO CORRECT THE CONTRACT COMPLETION DATE. |
| Dec 29, 2022 | 0 | $26.1M | FT KNOX TARGET TRAINING STRUCTURE |